From:
WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
April
3, 2000
Plasma operation at Alcator C-Mod resumed last week.
Four run days were
scheduled and completed. All runs were devoted to
machine startup and
conditioning activities. In order to minimize time
devoted to startup
development for "reverse-field" operation
later in the campaign, this first
week of plasma runs was carried out with
current and toroidal field in the
reverse, i.e. positive, direction. A
total of 31 plasma shots were produced,
out of 69 attempts.
Operationally,
the machine performance was similar to previous startup
weeks. Breakdown
was readily obtained, with very minor adjustments from
control settings
used during the last campaign. The main difficulty was in
machine cleanup
(conditioning) which requires a significant number of tokamak
discharges.
The startup scenario in reverse field was improved by adjusting
the
vertical field ramp rate, and by the end of the week appeared to be
satisfactorily
robust. Full length (>1.6 sec) discharges at 5.4T and 800kA
were
produced. At the end of Friday's run, the walls were still not fully
conditioned,
as evidenced by the rate of gas evolution from the walls, the
high H/D
ratio, and the relatively high loop voltage.
A partial flux loop,
F28, which had been repaired during the last vent, failed
early in the
week, apparently due to disruption forces. The PCS control
algorithms were
modified to use a nearly redundant loop, F27, and operation
was
resumed.
The bus work is being re-configured for normal (negative)
field and current
operation. This week will also be a plasma startup week,
devoted to additional
conditioning discharges.
Physics:
--------
The
Thomson scattering diagnostic is ready for the run. Over the last weekend
the
laser beam was aligned, laser tuned up and tested, both core and edge
spectrometers
tested, and the diagnostic calibrated using Raman scattering in
D2.
ICRF:
-----
Work
on the transmitters has focused on operational safety and diagnostics. We
have recently imported FPA and
Driver tube models from C. Brunkhorst (PPPL).
Currently, the measured data
and model predictions significantly disagree.
We
have re-calibrated the anode voltage and current instrumentation
on the Driver
and FPA. We have
re-calibrated the RF power measurements of the IPA, Driver,
and FPA
stages. Currently the transmitters
produce 1.8 - 2.4 MW into dummy
load.
We plan to document the working status of the transmitters and
compare
them with the models. The
PLC system has been investigated for FMIT#1.
Programming modifications
were implemented to improve the information required
for operations. Future work is scheduled to transfer these
improvements to
FMIT#2-#4. A gas
barrier in E-port's matched line section has failed and
needs to be
replaced. This work will begin this
week.
Lower Hybrid System Fabrication:
--------------------------------
The
first klystron has been installed in the test stand. The filament power
supply
has been tested successfully, and emission current measured in the
tube.
Diagnostic Neutral Beam
------------------------
We
continued the conditioning of the beam and were able to operate in the
45
to 48 kV range with few arc downs.
There are some problems with the
plasma arc power supply. The connections in the oil tank appear
to be
intermittent. We tightened them, which appeared to result
in temporary
remediation, but the problem persists and will be addressed
this week. We
successfully tested
the software that we use to fire conditioning shots
between C-Mod
shots. The software also detects the
preparation for C-Mod
shots and then synchs the beam with them. The
software was demonstrated
to work.
Travel and
Visitors:
--------------------
John Rice attended the Atomic
Processes in Plasmas Meeting in Reno Mar. 19-23
and presented a poster on
Satellites to the Hign n Rydberg Series in Ar, Cl
and S from Alcator C-Mod
Plasmas.
Amanda Hubbard attended a Workshop on Core and Edge
Transport Barriers, held
at JAERI in Tokai, Japan, and presented a talk on
'Conditions for EDA H-mode'.
She also discussed with Drs. Kamada and Hatae
ideas for comparing this regime
with the 'grassy ELM' regime on JT60U.
Yongkyoon
In attended the Sherwood Fusion theory meeting, which was held in
Los
Angeles from March 27 through 29.
Perry Phillips from the Fusion Research Center has been at
MIT for the past
week installing the high resolution ECE system. He will
be here for another
week to finish the installation.
Norton
Bretz was at PPPL this week working on MSE software and preparing final
hardware
adjustments. He will be back at C-Mod
the week of 4/3. Gerd
Schilling
also spent the week at PPPL, tidying up remaining FWP issues,
collecting
fiber optic telemetry for the C-Mod ICRF transmitters, working on
obtaining
a replacement to man the MSE diagnostic next year, and trying to
arrange
for further and additional rf engineering help to finish off the
remaining
problems of the ICRF transmitters.