From:
WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
April
10, 2000
Plasma operations continued on Alcator C-Mod last week.
Three run days were
scheduled and completed. A total of 39 plasma shots
were produced with a
reliability of about 80%. The bus work had been
re-connected in the normal
field direction (toroidal field and plasma
current both negative). The primary
goals were to re-establish operation
with normal (negative) field; continue
machine conditioning with tokamak
plasmas; and proceed with checkout and
commissioning of diagnostics.
Plasma
operation was readily obtained, but conditioning is still
incomplete. High
disruptivity was experienced except at low density
(nebar<1.e20), and
numerous molybdenum injections were observed on the
bolometer and
spectroscopic diagnostics. The observed behavior is not atypical
of
previous campaigns at this stage of the startup process.
This week
will be a maintenance week at Alcator C-Mod. No plasma runs are
scheduled;
electron cyclotron discharge cleaning (ECDC) will be carried out
consistent
with other activities. The principal focus will be on readying the
ICRF
and DNB systems for operation into plasma.
Physics
---------
A
second array looking at neutral deuterium Lyman alpha radiation is now
operational.
This array uses a photodiode array and a very narrow filter at
1215
Angstroms. The radiation gives the local ionization rate and neutral
density
with information of the electron density and temperature. Initial
results indicate that the Lyman
alpha radiation is approximately 10 times
larger near the inner wall
compared to the radiation near the outer midplane.
Detailed analysis of
the measured profiles is under way.
The new limiter particle-flux
probes are now operating. Particle
flux
densities to the sides of the A/B and G/H limiters are recorded at 8
different
locations (4 on each limiter) by Langmuir probes operated in
an
ion-saturation mode (Isat). The probe geometry is designed so that
each
probe element integrates the cross-field profile of Isat from the
leading
edge of the limiter far into the limiter shadow.
ICRF
Systems:
--------------
Efforts continued in bringing up the
ICRF transmitters for the resumption of
operation into plasma. Transmitter tuning for maximum output power
had been
hampered by residual telemetry waveform and calibration issues,
but these are
being resolved. Lack
of transmitter access resulting from C-Mod plasma
operation has added
delays, but this will be alleviated by the scheduled
maintenance week of
4/10. Chris Brunkhorst from the PPPL rf
engineering group
will come for the week once more to help.
DNB
System:
-----------
Preparation for operating the DNB into
C-Mod continued. A problem
with
the arc crowbar was bypassed, allowing consistent formation of the
source
plasma. An interaction between the
C-Mod magnet supplies and the
DNB HV supplies was corrected, allowing a
beam to be fired into the dump
plate during a C-Mod shot. The DNB software was further checked
during
C-Mod operation. The RGA
was made operational in preparation for opening
the DNB gate valve.
Diagnostic
activities this week included installing the full set of BES fibers
in the
MSE/BES image dissector, installing the MSE polarizer, checking the PEM
control
units, and calibrating the filter temperature controls. The
BES system is now ready to make
measurements of the radial profile of the
absolute level and fluctuations
of the beam emission. Howard Yuh,
an MIT graduate student, is continuing
to write software to do calibrations
and set the timing for automated and
interactive data taking. The
filter
control calibrations were both tests of Howard's programs and
system
calibrations aimed at anticipated 5.3 T plasma and 45 keV hydrogen
DNB
operations.
Lower Hybrid Fabrication
-------------------------
Work
on the lower hybrid test stand continued. Mechanical assembly is now 98%
complete,
and wiring 90% complete. Power was applied to the focus magnet, and
testing
of the fast-off fault circuits was begun.
Travel and Visitors
--------------------
Randy
Wilson (PPPL) came to MIT for the week to help with transmitter tuning
and
debugging. Joel Hosea(PPPL) came 4/6-7 to contribute to the ICRF
startup
and for discussions with Ron Parker on the LHCD project.
Norton
Bretz(PPPL) was at MIT 4/3-5 for the MSE work.
Ron Bravenec (UTx)
visited C-Mod to work on the BES system.
Perry Phillips
also visited C-Mod and worked on hardware for the
Texas ECE system. Dave
Winslow is
presently at C-Mod working on hardware for the Texas turbulence
probe.
Dr.
Nobuyuki Asakura, from the JAERI JT-60U experiement, visited the PSFC
for
the period March 28 through April 8. He spent his time primarily on
issues
to do with transport in the SOL. More specifically the question of
how
wall recycling on different machines scales was addressed. This
involved
comparing data on midplane pressure and D_alpha, as well as plasma
profiles
in the SOL for different experiments. We compared not only C-Mod
and
JT-60U, but also data found in the literature for ASDEX Upgrade and
JET.
For the most part midplane pressures, which represent the ion flux to
the
walls (ion flux to wall = neutral flux back towards the plasma) scale
with
the operating density of the experiment. Some differences among
experiments
became apparent. All of the data will be analyzed further.
Montgomery
Grimes (MIT) traveled to CPI (the manufacturer of the LH high-power
klystrons)
to discuss the klystron operation in this application.
Miklos
Porkolab, Ian Hutchinson, and Earl Marmar attended the OFES Field Work
Proposal
Meeting in Germantown, Md., on April 5,6 .
Bob Childs attended the
Executive Council Meeting 85, chaired the Vacuum
Science Division meeting
of IUVSTA and attended the Program Committee meeting
for the International
Vacuum Congress 15 to be held in San Fransisco October
2001. These
meetings where held in Namur, Belgium from Friday March 31, to
April 2,
2000
From news@proxy2.fe.internet.bosch.de Mon Apr
10 12:41:40 2000
Return-Path:
<news@proxy2.fe.internet.bosch.de>
Received: from briar.org
(backdraft.briar.org [192.207.123.123])
by
jupiter.cs.uml.edu (8.10.0/8.10.0) with SMTP id e3AGfaZ23215