From:
WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
July 10, 2000
Operations
----------
Alcator
C-Mod is now in a scheduled maintenance period, which will last until
September.
Following the last plasma discharge on June 30, the C-Mod Cryo
System was
shut down, and the warm up of the machine was begun. By Thursday
of last week all machine components were well
above 0 C and preparation for
invessel work was begun with a backfill of
nitrogen gas and D2O. The heavy
water
is expected to react with the boron hydrides on the vessel wall and
allow
safe manned entry into the vacuum vessel without adding large amounts of
hydrogen
to the wall inventory, as would occur when venting to room air. The
removal of the hydrogen and the
reduction of the H to D ratio to a point
suitable for ICRF heating
experiments has been a major delay in obtaining
research grade plasma
discharges in the past. We hope this
new technique will
shorten the startup process somewhat. Entry into the vessel is expected on
Wednesday
of this week following two days of Thomson scattering calibrations.
Preparations
for invessel work are proceeding well as we are nearing the
short machine
vent scheduled for this week. The work will focus on the
modification of
the 4 strap antenna, and consists mainly of enclosing the
sides of the
antenna in order to increase its heating efficiency.
In addition, we will
substitute all molybdenum protective tiles with boron
nitride ones on all
antennas (including the two 2 straps).
The new tiles are
ready to
be installed after completion of a high temperature bake early last
week. A final MIT local review of the changes to
the j-port antenna was
held last Thursday in which all aspects of the
invessel changes were
discussed.
Disruption forces, new plate design, location of and hold down
hardware
for the BN tiles, capacitor layout and soldering techniques, and
plasma
shields were all discussed.
As time allows, small invessel tasks,
such as light calibrations for BES, MSE,
and camera views, will be
completed in parallel with the antenna work.
Flux loops will be examined,
connections on the second Lyman alpha detector
will be checked, as well as
for a emissive probe, and a flux probe. Finally
we will try to install the
new fluctuation imaging system built
by S. Zweben (PPPL).
Preparations
for our first period of long pulse operation continues.
Simulation of coil
temperature rises during the planned 3.5 second flattops
indicate a large
safety margin. Calculations of power
supply component
junction temperatures are proceeding and have indicated
which components will
need to be monitored. The design and procurement of instrumentation needed to
monitor
these critical components is proceeding.
Upgrades to the C-Mod glow
discharge system are underway. Fast
IGBT switches
are being installed to allow for current rollback control
during arcs. This
change will
eliminate damage to invessel components during glow discharge
campaigns. In addition, improvements to the gas control
system will allow
more automatic operation of the glow system, and the
addition of RF chokes to
the leads to the invessel glow paddles will
eliminate RF pickup by diagnostics
near the glow system electronics
rack.
Progess is also being made in the upgrades to the cryostat and
igloo we plan
to make during the machine inspection late next Fall. Preliminary designs
have been completed. These changes will allow for the easy
removal and
installation of the horizontal ports to fix leaks, much better
thermal
insulation of the ports from liquid nitrogen, and new
instrumentation ports
through which to bring cabling out of the
igloo.
ICRF
System:
------------
We began an inspection of D-port coax for
evidence of arcing. This antenna
did
not condition well this past campaign and would trip consistently on a
specific
pair of faults (DC0 arc detect and phase balance). The resonant
loops and a portion of the 9" coax have
been inspected without finding any
significantly damaged component. The inspection will continue this
week.
The J-port antenna modifications were reviewed last week. The plan is to RF
ground the antenna
structure, ground the end front tile and the side plate,
and replace the
Mo protection tiles with BN. We will
begin with an inspection
of the antennas at first invessel
opportunity. Analysis of heating
experiments
with the J-port antenna configured as a dipole (center strap pair)
show
heating efficiencies ~70-75% (similar to D and E-port antennas). This
suggests that proper RF grounding
of the antenna should improve its 4-strap
performance.
DNB
System:
-----------
The DNB was operating most of the last week
of plasma runs. However,
a minor
fault in the HV system led to an early shutdown in beam operation.
Initial
measurements of the magnetic field near the beam were completed and
will
be used to verify the effectiveness of the magnetic shielding of the
beam. Preparations are now underway for
realignment of the beam, improvement
in monitoring of the beam plasma
source, improvements in vacuum gauging,
recalibration of the thermocouple
system that monitors beam profile and
energy, tests of the CXRS window
transmission at F-top, and tests of CXRS
fiber transmission. These tasks
will be completed prior to restart of C-Mod
operations.
The BES
diagnostic measured good signal levels from the hydrogen DNB during
the
week of 6/12. The signals were up to
factors of 2-3 over background.
The
absolute intensities of the beam signals were compared with our
model and
agree within a factor of two.
Matt Sampsell (UT-FRC) was at MIT that week to
coordinate the BES
measurements. A poster was delivered at
the HTPD
Conference in Tucson describing the BES model used to interpret
the data.
Lower Hybrid System
-------------------
Testing
of the first seven klystrons (all those presently in-house) has been
completed.
Four are in nominal operating condition; two (S/N 112 and 115)
experienced
high voltage breakdown in the vicinity of the flying leads; and
one has a
shorted filament. Physical inspection of tube 115 revealed that the
cathode
and heater leads showed signs of cracking, which could lead to the
observed
breakdowns. A plan has been devised to repair these klystrons, and
parts
for the repair hve been ordered. We are coordinating with Princeton for
the
shipment of the remaining nine klystrons, which are presently at PPPL.
Diagnostics
-----------
David
Winslow (UT-FRC) completed installation of the Texas Scanning probe.
It
has now been successfully reciprocated both during ECDC and tokamak
discharges.
Mechanical limitations in the probe drive system prevented
measurements
near the separatrix. These will be corrected during the
current break and
it will be ready for the next section of the campaign in
September.
The
UT-FRC ECE system was returned to operation.
As noted in previous
reports, repairs were required mainly due to
blockages of the waveguide and
faulty regulation in a power supply. These
repairs have now been completed.
By the end of C-Mod operation in June, 30
of 32 channels were back in
operation and measuring electron
temperature. Malfunctioning components
in
the remaining two channels have now been replaced.
With the recent
installation of the Diagnostic Neutral Beam, the Neutral
Particle Analyzer
had to be temporarily removed from the tokamak.
It has now been
reinstalled in its new position on B-port. It is an
E||B type analyzer,
with 39 channels for each species (H and D). Its
new view will look at the
center of the discharge, from slightly above the
midplane, nearly
perpendicular to the magnetic field. It
will be used for
characterization of the tail population, and help us
determine the
hydrogen concentration during ICRF heating.
The
Tangential Two Color Interferometer (TTCI) began operation near the end
of
the run period. This single
chord diagnostic monitors the plasma edge density
at 0.88 m and uses a
diode pumped frequency doubled laser to provide the two
colors for
vibration subtraction. The transitions
into and out of H-mode are
clearly seen, are of the expected magnitude,
and correlate well with other
edge diagnostics such as the edge diode
bolometer array and visible
bremsstralung. The cause of a low frequency drift in the phase measurement
must
still be determined and fixed. Typical
C-Mod pedestal densities result
in peak phase shifts of 0.03 to 0.05
fringes, depending on pedestal location
and width, so vibration
subtraction requirements are quite severe.
Travel and
Visitors
-----------------
Cynthia Phillips was at MIT last
week (July 5-7, 2000) working with Paul
Bonoli as part of the C-Mod/PPPL
collaboration. We are carrying out TRANSP
modelling of the 4.5 T density
barrier discharges that were achieved on C-Mod
(with emphasis on shots
1000607007 and 1000607008). We are
using the new
upgraded FPPRF ICRF package in TRANSP, which now includes
the TORIC ICRF
code. The results of this transport analysis will be
reported as part of an
IAEA poster presentation in Sorrento Italy in
October, 2000.
Ricky Maqueda (LANL) was onsite working with the LANL
fast camera during the
last week of operation.
Stewart Zweben
(PPPL) was at C-Mod during the last week of operation making
preliminary
measurements in preparation for his fluctuation imaging
diagnostic.