From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups:
sci.physics.plasma
Organization: MIT
Alcator C-Mod Weekly
Highlights
July 17, 2000
The scheduled maintenance period continued at
Alcator C-Mod last week.
On Sunday, July 9, the machine was
backfilled with hydrogen for calibration of
the Thomson scattering
diagnostic. The Raman scattering calibration was
carried out on Monday and
Tuesday.
After completion of the Thomson scattering calibration, the
vacuum vessel was
opened for manned access. The first survey indicated
very low diborane
levels and no measurable radioactivity, allowing work
inside the tokamak to
proceed without delay.
A general
invessel survey was carried out on Wednesday, with video
documentation.
The status of invessel components was generally good.
A few systems
suffered light damage. Some ground glass has been found near
the MSE/BES
optics, indicating damage to the lenses or mirrors. Some
internal optics such as the J antenna-view mirror, the
DNB poloidal view,
and CXRS optical systems have been covered with boron,
and plans are to clean
them in situ. Five molybdenum tiles (out of 8000)
suffered damage from heat
flux and disruptions, and are being replaced.
Additional work planned for
this opening includes some minor calibrations,
alignment work for
diagnostics, and installation of the PPPL invessel
telescope that will be
used for 2d imaging of edge fluctuations. The fiber optic bundle, bellows,
window,
and miniconflat seals have been installed for this new diagnostic.
Imaging
checks of the telescope system indicate that 1 mm spots will be
easily
resolved.
This vacuum opening is scheduled to be completed within a
week, followed by
leak checks, a 120C bake and ECDC in order to resume
basic operations
at the end of August.
ICRF System
-----------
An
inspection of the antennas was performed as soon as general invessel
access
was possible. The J-port antenna was in
very good condition compared
to the previous campaign. The protection tiles had little arc or melt
damage,
indicating the new shorting strap between the tiles is functioning
as
designed. The new insulating
washer assemblies are in excellent condition,
as are stainless cups inserted
to protect them. There are some
vertical arc
tracks on the vacuum wall that suggest the antenna is at a
different potential
with the toroidal field present. These arc tracks are consistent with the
most
likely cause of our parasitic loading being the generation of plasma
waves
between the back of the antenna and the vessel wall. We have already
completed grounding of
the J-port conductor covers. Machining
for the
remaining pieces has been completed and we have begun
reassembling
the antenna. The remaining
major item is the side plate installation, and
this should be finished by
the end of the week.
An inspection of the D-port antenna revealed
minor pitting and tracking on the
top left strap (looking out along the
major radius). Video images
during
plasma operation had already indicated a problem at this location
that when
correlated with phase balance and reflected power measurements
lead us to
suspect a transmission line or feedthrough. Inspection of the
feedthrough indicated
tracking had indeed taken place at this location.
Clean up of of the
feedthrough is progressing well, and reassembly will begin
this
week.
The E-port Faraday screen shows indications of arcing near the
BN tiles.
The mechanism for this problem is not as yet understood, but is certainly
under
investigation.
The Mo side tiles have been removed from D and E-port
antennas in preparation
for installation of the BN tiles. The BN tiles have been fitted and
await
the fasteners for installation.
Travel and Visitors
-------------------
Stewart
Zweben visited from PPPL all last week working with Jim Terry
to install
the 2d telescope.