From: IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT


                Alcator C-Mod Weekly Highlights
                        July 24, 2000


The last full week of invessel activity has been completed.  Alcator
C-Mod will be pumped back down early this week.   Modifications to all the
antennas will be completed by 7/25 as will numerous cleanup and repair
activities associated with invessel diagnostics.  Maintenance and calibration
activities continued on power and cryo systems.


Invessel Work
-------------

Work continued this week on rf shielding of the perimeter of the PPPL
ICRF antenna.  The last measurements performed  at the end of June supported
the idea that the low heating efficiency was due to rf power leaking around
the back of the antenna  and coupling to plasma surface waves.  The top and
bottom of the  antenna have now been enclosed with stainless steel shim stock
and spot welded to the antenna frame and vacuum vessel wall.  The left and
right sides of the antenna frame could not be directly grounded to the
vessel wall because eddy currents generated during disruptions would have been
too large.  Instead, rf bypass capacitors have been installed between the
antenna and the wall.  These capacitors are essentially shorts at rf
frequencies, but appear as a relatively high impedance to disruption currents.
All molybdenum protective tiles on all antennas have been replaced with
boron nitride tiles.  In addition, a new set of boron nitride tiles has
been installed between the D and E antennas to better protect their
Faraday screens.

The viewing telescope, optics, and coherent fiber bundle for the new
PPPL 2-D turbulence imaging diagnostic have been installed inside the
vacuum vessel.  A test target at the position of the gas puff was
clearly imaged onto an external video camera.

Invessel calibration and alignment of the F-top and F-side optical systems
used for viewing "plumes" generated by gas injection from the F-bottom
scanning probe took place during the recent C-Mod opening. Both a relative
pixel calibration and an absolute brightness calibration were obtained, the
latter using the Labsphere. A back-illuminated aluminum plate with holes
drilled on a precise grid pattern was used to determine pin-cushioning and
other distortion effects. Absolute alignment was performed by viewing a small
light bulb placed at various known locations in the vessel, e.g. in grooves
between divertor tiles and at the tip of the scanning probe when inserted to a
known vertical position. The system is now ready for operation during the
upcoming run campaign.


Other Engineering Activity
--------------------------

Work continued last week on an upgrade to our glow discharge system.
Besides a general cleanup of the layout and improvements to the PLC control
electronics, we are also adding fast solid state controllers to the current
going to the glow paddles.  These controllers will be able to rollback
the current to the electrodes in a few microseconds and limit the energy
dumped into arcs to a few mJ.  This energy will be insufficient to sputter
material from the vessel walls.

Our 13.8 kV current and pulse transformers have been re-calibrated.  Results
indicate both current and voltage measurements were accurate to within
+-2%.  Fuses and breakers associated with C-Mod power systems
have been inspected.  A fuse for the A-phase of the FMIT#1 transmitter
had clearly been arcing at some point since the last inspection.  This
condition may explain some of the transient fault conditions experienced
over the last few weeks of operation.

Preventative maintenance to the CRYO system proportional valves continued
last week.  Work on the new cryostat exhaust valve also made progress.
All CYRO system filters have been cleaned or replaced.  The LN2 pump has
been removed from the sump and is undergoing an inspection.


Quarterly Review
----------------

A C-Mod Quarterly Review was held on July 20th.  Rostom Dagazian and
Warren Marton from DoE were at MIT for the review.  Presentations by MIT,
University of Texas at Austin, and PPPL personnel were given.  The agenda and
the presentations can be viewed in PDF format at

      http://www.psfc.mit.edu/cmod/sciprogram/q_rev_jul00/


Travel and Visitors
-------------------

Stewart Zweben from PPPL was at C-Mod for the week, working with Jim
Terry on the turbulence imaging installation and presenting a talk at
the Quarterly Review.

Miklos Porkolab attended the Fusion Power Associates Meeting on July 17
in San Diego and made the following presentation: Alcator C-Mod Program and
Recent Results. The following 2 days he attended the FESAC meeting at General
Atomics where the recent draft of the Integrated Program Planning Activity
document was discussed.  Earl Marmar also attended the FESAC meeting,
as well as the first meeting of the Next Step Options Program Advisory
Committee.