From: IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject:   Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT


                Alcator C-Mod Weekly Highlights
                        July 31, 2000


Invessel work on Alcator C-Mod was completed the middle of last week.  After
final cleanup, documentation, and diagnostic alignments the vacuum vessel was
closed up and pumped down on Friday.  Also on Friday, the vessel heaters were
turned back on and a GN2 purge was begun of the cryostat and bus tunnel.
A leak on a newly installed flange was found and fixed on Saturday, and more
sensitive leakchecks were performed today. No additional leaks have been
found.  We plan to begin LN2 cooling of the machine structure and a 120C bake
of the vessel later this week.


Invessel Work
-------------

The J-Port antenna is now rf shielded top and bottom, and rf currents are
bypassed through ceramic capacitor arrays on the left and right sides.  These
changes should considerably reduce or eliminate the parasitic power losses
to plasma surface waves, which we think have been responsible for the
previously observed low heating efficiency.  Both the J-Port antenna and the
two older antennas at D- and E-Port have also had their molybdenum protective
tiles replaced by boron nitride to reduce metallic impurity influx to
the plasma.

Alignment of the tangential two-color interferometer and new charge
exchange analyzer, replacement of mirrors boronized during the last run
period, extensive documentation using digital and 35mm cameras, vacuuming
and wipedown, and final inspections were also completed last week.

Pictures documenting the invessel status at pumpdown can be found at

http://www.psfc.mit.edu/cmod/operations/EngImages/CmodImages.asp?ref=/INVESSEL/2000/Close_Up_Survey/


Other Engineering Activity
--------------------------

Nine klystrons needed for our lower hybrid experiments which had been on loan
to PPPL were returned to MIT last week.  All 16 tubes from the Alcator
C Lower Hybrid experiment are now back on site at the PSFC.  The first of the
nine returned tubes is now being prepared for installation into our klystron
test stand.  The first of two delrin insulators needed for repair of two other
klystrons is now ready for installation.

The J-Port external resonant loop, coupling the antenna  to the transmitters,
has been reassembled and checked for resonance in the two 80 MHz phasing
configurations: (0,180,180,0) and (0,180,0,180).  It has also been
tested for operation at 70 MHz.  Operation of the  D- and E-Port antennas at
their nominal 80 MHz combined with J-Port at 70 MHz will allow us to form
the highly peaked discharges discovered in June by ICRF heating off-axis,
while simultaneously using the lower frequency power for on-axis heating near
the density peak.

Chris Brunkhorst (PPPL) came to MIT 7/24-27 and worked on optimizing the
tuning of the  #3 and #4 ICRF transmitters that are coupled to the J-Port
antenna for operation at 70 and 60 MHz.  70 MHz operation is needed
for the off+on-axis heating scenario described above, while 60 MHz is
intended for current drive experiments.

Work continued last week on the DNB and associated diagnostics.  The
alignment of the beam was measured and adjusted.  The field generated by
the DNB dump magnets was measured.  The transmission of the F-Top CXRS
window before and after cleaning was measured.  The tangential CXRS optics
were backlighted to assure that no mis-alignments had occurred during the
several months since installation.

The upgrade to the glow discharge and boronization system is moving very
quickly and should be ready for operation within two to three weeks.
Upgrades to the power system instrumentation in preparation for long
pulse operation are also progressing well.


Physics
-------

Very low density H-modes produced in June as part of an exploration of the low
density H-mode limit have recently been analysed.  Most of these discharges
were  ELM-free, with high pedestal temperatures and modest density rises.  The
edge collisionality was correspondingly lower than in most EDA H-modes.  It is
possible that this prevented access to the EDA regime.  However, the
discharges had q95 ~ 3.5-3.7,  which is on the low side for EDA access, so this
result is not conclusive.  Several discharges showed isolated ELMS, which
occurred at fairly high edge pressure and temperature, unlike our usual
Type III ELMs.  These may have been Type I ELMs, which are seen regularly on
other machines but not normally on C-Mod.  Further experiments to clarify the
ELM type and the effect of density on the EDA/ELM-free boundary are
proposed for September.



Travel and Visits
-----------------

Rejean Boivin travelled to INRS-Energie et Materiaux, located in Varennes
Quebec, for the thesis defense of Irina Condrea, who did research on rotation
measurements in L and H modes.  He also attended, along with Martin
Greenwald, the APS program committee meeting in Washington for the upcoming
APS-DPP meeting in Quebec.

Chris Brunkhorst visited from PPPL to work on improved tuning procedures for
the #3 and #4 transmitters.

Tom Fredian visited PPPL to analyze the use of the MDSplus data
system on the NSTX experiment and make suggestions for improved performance
and functionality. The system is installed and working well. A few fine
tuning suggestions were made.

Gabriele Manduchi from Padova (one of the original authors of MDSplus)
visited Tom Fredian, Josh Stillerman and Stuart Sherman to discuss new
MDSplus features and future development plans.

David Winslow (UT-FRC) visited the PSFC during the vent to remove the Texas
probe and get an absolute position calibration. After modifications and
prior to beginning of the next campaign, the probe will be reinstalled to
take data during the remainder of the campaign.

Pablo Acedo (Carlos III University, Madrid) has returned to MIT for
6 weeks to continue our collaboration on interferometry.

John White, Juergen Alex, and Walter Kaufmann from Thomcast Radio Systems,
Inc. visited last week for two days of discussion on the high voltage
power supply/modulator Thomcast will supply for our Lower Hybrid experiment.
Items covered included contractual clarification, and technical issues such
as electrical interfaces, testing procedures, protection circuits, and PLC
software.