From:
WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
August 21, 2000
Operations
----------
Plasma
operation resumed on Alcator C-Mod last week, following the
manned-access
vent in July. Operations were aimed at re-establishing routine
operation,
machine conditioning prior to re-boronization, and diagnostic
alignment
and calibration. Two plasma run days were scheduled and completed,
with a
total of 23 plasmas produced and a startup reliability of over 50%.
The
resumption of operations was carried out about one week earlier than
originally
scheduled.
Power systems tests were completed on Wednesday, and an
initial plasma attempt
resulted in a breakdown but no current rise (a
fizzle). Several full length
plasmas were obtained on Thursday, and the
machine showed signs of cleaning
up, although carbon levels and H/D
remained high. Friday's run was marked by a
substantial improvement in
startup reliability and reduced carbon
levels. Standard 800kA, 5.4T
diverted discharges were run for machine
conditioning. The observed H/D
ratios continued high, with values around 0.7;
this hydrogen concentration
is similar to that observed at this stage of the
conditioning process in
previous campaigns, implying that the use of heavy
water in the initial
backfill at the start of the vent did not effectively
saturate the walls
with deuterium, as had been hoped.
In addition to the standard
conditioning discharges, we also ran plasmas with
ramping toroidal field
to vary the edge q, in support of the turbulence
imaging experiment. We
also produced cases with dynamic scans of the outer gap,
both for the
benefit of the turbulence imaging and to evaluate equilibrium
reconstructions
using an expanded set of magnetic diagnostics.
Plasma operations
are scheduled to continue this week, with three run days
planned.
Physics
-------
The first data were taken with a camera system
designed to visualize edge
turbulence.
The camera has a tangential view (parallel to the field lines) of
a
6x6 cm region with resolution better than 1 mm. The camera was gated for 2
microseconds with images taken
every 16.67 msec. The region of
interest is
illuminated by light from neutral helium which is puffed from
a capillary tube
at the outer limiter radius. Very clear images of turbulent structures were
obtained.
This system was designed and operated by Stewart Zweben as part of
the
PPPL collaboration.
A set of eight poloidal field loops located on
the outboard limiter were
incorporated into the equilibrium reconstruction
(EFIT) for the first
time. These loops, which were formerly dedicated to
study of magnetic
fluctuations, are 10 to 15 cm closer to the plasma than
the original loops
mounted on the outboard wall of the vessel, and are
expected to improve the
accuracy of the reconstruction of the outer
separatrix location. A series
of shots in which the plasma was moved into
contact with the outboard limiter
was carried out to help test the new
reconstructions. Detailed analysis of
these data is in progress.
RF Systems
------------
We
began vacuum conditioning D and E-port antennas and completed the J-port
transmission
lines preparations. We also repaired
the screen crowbar unit for
the FMIT#2 transmitter, and also repaired the
one of our spare crowbar units.
The Lower Hybrid launcher Conceptual
Design Review was held on 8/17 at MIT.
The PPPL participtants were Joel
Hosea, Stefano Bernabei, Gerd Schilling, Doug
Loesser and Joe
Rushinsky. From MIT, Miklos Porkolab,
Ian Hutchinson, Ron
Parker, Jim Irby, Monty Grimes, Dave Gwinn, Dave
Terry, Bill Beck, Bob Childs,
Rui Viera, and Steve Wukitch were in
attendance.
Engineering
-----------
Tests of the
upgraded glow/boronization system on our vacuum test stand were
completed
last week, and the system was reinstalled in the cell. A full
checkout of the boronization
system using helium rather than diborane will
occur early this week
followed by installation of the diborane bottle in the
cell. Tests of the glow discharge system are also
planned.
The installation of new instrumentation for long pulse
operation is
proceeding. We will
complete installation of the new conduit this week and
begin running the
cabling. A new CAMAC crate for the new
instrumentation is
also being prepared.
The DNB mod/reg stopped
producing pulses during our last week of plasma
operation in June. This problem has been tracked down and
fixed. The DNB
beamline is now
being leakchecked and prepared for operation.
Travel and
Visitors
-------------------
Stuart Zweben was at C-Mod from
8/15-18, working on the completion of the new
edge turbulence imaging
diagnostic. First images of edge
turbulence structure
were observed on 8/17, and are now being optimized. Norton Bretz was at C-Mod
8/16-18,
continuing the Motional Stark Effect diagnostic calibration and
resolving
possible interference issues with the Beam Emission Spectroscopy
diagnostic. MSE is again ready for the Diagnostic
Neutral Beam to resume
operation.