From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups:
sci.physics.plasma
Organization: sci.physics.plasma
Alcator C-Mod Weekly
Highlights
August 7, 2000
After a several day long GN2 purge
of the cryostat and magnets to remove air
and water vapor, a cooldown of
the C-Mod retaining cylinder and domes was
started on Tuesday of last
week. Cooldown of the magnets to
approximately
-25 C was completed on Wednesday, and the vacuum bake of the
vessel was then
brought up to 120 C.
Work also continued last week on RF and
Power systems, and the
divertor upgrade.
Engineering
-----------
The
two klystrons that had exhibited high voltage breakdowns have now
been
successfully tested with new insulators installed. Testing of the
klystrons just returned from PPPL has already
begun. We now have ten
klystrons
qualified for service. Twelve will be
needed for the first
lower hybrid experiments.
The gas fill
and pressure indicator system for the ICRF transmission lines
is being
modified to accept 1/4'' npt fittings.
The D-port phase
shifter has been repaired and installed. The 9'' coax reassembly is
progressing
for D, E, and J-port. We have
recalibrated the voltage
probes and directional couplers (EDC2, EDC3 and
EDC4, and DDC3 and
DDC4).
A water leak in the FMIT#4 anode
cooling lines was apparently caused by low
resistivity water has been
diagnosed and repaired. The water
system was
recently modified to be closed loop to increase the water flow
while reducing
the head pressure from the main C-Mod loop. A clogged filter in this new
system
eventually resulted in an erroneous resistivity measurement and in a
large
current flow through the cooling lines when the transmitter was in
operation. Small pumps are being added to all the
cooling systems to
continuously replace the cooling water with high
resistivity main loop
water every 20 hours.
We continue to add
new diagnostic signals to the power systems in preparation
for long pulse
operation. Cabling and conduit are
being run, and the
CAMAC equipment required to record the new data
installed. Simulations
of the
solid state power system components are complete and indicate
all
components will operate in a safe range during 10 second long
pulses. Simulations of the main fuses in the system
are now underway.
Aluminum prototypes of the new divertor upgrade
tiles have been made to
verify the design and drawings. We are now ready to go out for final
bids
for the approximately 1000 tiles needed. We are also in the process of
producing a test piece for the
tile support structure (girdle).
Heat
conductivity tests used to model the heat transfer from the
girdle to
the vessel wall indicated a 30% improvement in conductivity when
silver
plating was added to the girdle components. We have also successfully tested
a
mockup of the tile keeper components.
Completion of these inner
wall/divertor modifications is scheduled
for the winter maintenance period,
and these changes will allow for full
plasma current operation (> 2 ma)
in the 2001 campaign.
Work continued last week on the upgrade
to the glow discharge and diborane
systems. The Diborane/Glow discharge rack equipment wiring cleanup
was
completed. A new glow
discharge HV chassis was installed in the rack and
bench testing has been
started. High power resistor rack
wiring was
completed. Interconnect
cables from the new glow discharge rack to the
Diborane/Glow discharge PLC
rack were completed. Multipin connector
panels
for the Diborane/Glow discharge PLC rack were wired. The glow discharge switch
control
chassis is built and wiring is underway.
All design work is complete.
Spare glow paddles are being installed
in our vacuum test stand so that the
new system can be checked offline
before installation on C-Mod.
Travel and Visits
-----------------
Gary
Taylor spent the week at C-Mod working on the GPC2 electron
cyclotron
emission diagnostic.