From:
WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
Sep
5, 2000
Operations
----------
Plasma operations
continued at Alcator C-Mod last week. Four run days were
scheduled and
completed. The first boronization since the July vent was
carried out on
Monday night. Approx. 140 psi of
diborane gas was used
corresponding to about 2000 Angstroms of boron on
the walls. The boronization
was
followed up with 2.5 hours of ECDC in helium at 5.e-5 Torr.
C-Mod
operation was run on the usual Tuesday through Friday schedule. A total
of
94 plasma shots were produced, with a startup reliability of 90%. Two run
days
were devoted to experiments by the pedestal/H-mode physics research
group,
and two to ICRF conditioning and development.
Plasma operation will
continue this week.
Physics
--------
With its
good energy confinement, moderate particle confinement and lack of
large
ELMs, the EDA H-mode could be a highly favorable regime for a tokamak
reactor
- if we can understand the underlying physics sufficiently to
extrapolate
into new regimes. The key to understanding EDA seems to be in the
quasi-coherent
fluctuations which have been observed by the reflectometer,
PCI, and
probes. These fluctuations seem always
to accompany EDA and have
been shown to drive significant particle
flux. An experiment carried out
this
week employed the A-side fast scanning probe with a magnetic coil
embedded in
the probe head along with two Langmuir probes, and the fast
framing tangential
camera, which was set up with an Halpha filter and a
hydrogen puff to observe
the quasi-coherent (Q-C) fluctuations in ohmic
H-mode EDA plasmas. Ohmic EDA's
are chosen for these experiments to limit
the incident heat flux on the
scanning probe, permitting deeper
penetration. A principal goal was to look
for magnetic components of the
quasi-coherent mode with the scanning probe.
Q-C fluctuations were clearly seen on the reflectometer,
electrostatic probes
and on the magnetic probes, with frequency between
100 and 150kHz. Although
the
magnetic sensor itself never got closer than 1 cm to the separatrix, the
amplitude
of the signal reached 400 T/sec peak to peak.
Accounting for the
mode frequency, this corresponds to about .4mT
or about 20 A/cm^2, which is of
the same order as the total calculated
edge current density. The
electrostatic
probes, which are part of the same probe head, saw the modes
quite clearly
- with similar time histories. The main
distinction is that
they only see the mode when they are immersed in it
(deep penetration) while
the magnetic probe needs only to be close to the
separatrix. The conclusion is
that the Q-C mode has a very significant
magnetic component.
On one
shot the probe also observed some ELM precursors from type III ELMs.
These
had a longer decay length as seen on the probe scan, and were also seen
with
the wall magnetics, suggesting that they have a lower m number. These
fluctuations were not seen on the
floating potential, strengthening this
conclusion. Thus we would conclude that the Q-C mode is
distinct from ELM
precursors.
We also obtained D-alpha images
with the gated tangentially-viewing camera for
most shots. Clear differences among L-mode, ELMfree
H-mode, and EDA were
seen.
Emission from L-modes is quite broad, extending 5-6 cm outside the
separatrix. In ELMfree H-mode, the region of emission is
much narrower and
hugs the separatrix.
During EDA, clear fluctuations are seen well outside the
separatrix.
These images suggest additional transport in the far scrape-off
(consistent
with profile measurements). They do not appear to be a visualization
of
the Q-C fluctuation itself.
Thursday's
run was devoted to documentation of pedestal parameters in
ELM-free, i.e.
non-EDA, H-modes with ICRF heating. Data were obtained at 1.0 and
1.2 MA,
at a toroidal field of 5.4 tesla. RF power was <2MW, and the H/D ratio
increased
to >10% over the course of the day, resulting in less than optimum
heating
efficiency. On Friday's run it was found that between-shot ECDC in D2
resulted
in stable H/D fractions of ~5%, which is preferred for efficient
minority
heating.
A set of eight
BP-loops mounted on the outboard limiter located between G- and
H-ports
were incorporated into the EFIT flux reconstructions, in an effort to
improve
the reliability of the inferred location of the last closed flux
surface.
Discrepancies between the EFIT reconstructions and other diagnostics
of
order 5mm, particularly at the outboard midplane have been previously
noted.
Inclusion of the limiter BP-loops, which are much closer to the plasma
than
the original magnetics diagnostics mounted on the outboard wall, did
result
in reconstructions which placed the separatrix further in by about 5mm,
in
better agreement with independent diagnostics. However, the results, and
subsequent
testing, indicated a discrepancy between the new and old loops at
the
level of ~2%; this discrepancy, which is well outside the nominal
accuracy
of 0.5%, was later determined to be due to a systematic
difference in the
calibration techniques used for the two coilsets. An
independent check of the
absolute calibrations is now in preparation.
Dynamic outer gap scans carried out during the previous week give
some
independent indication of the correct location of the last closed
flux surface
by comparing magnetic fluctuations with the EFIT calculations
of the outer
gap. The amplitude of
the outboard midplane magnetic fluctuations increases
as the gap is
reduced, then remains constant. We speculate that the
fluctuations remain
constant when the gap is in fact zero and the mode cannot
get any closer
to the coil. The time history of the RMS of the magnetic
fluctuations was
compared with the EFIT calculations using either just the
original
poloidal field pick-up coil set alone or including the integrated
outboard
limiter coils, as discussed above. The
comparison indicates that the
fluctuation amplitude is constant when the
outer gap is zero for the EFIT
calculation including the outboard limiter
coils, suggesting that these
reconstructions give a better estimate of the
outer gap. However, questions
about
the coil calibrations must be resolved before a definitive conclusions
can
be drawn.
ICRF Systems
-------------
ICRF
antenna conditioning resumed this week following overnight boronization
on
Monday. Hydrogen/deuterium ratios in
the plasma were now reduced to the 5%
level, allowing ICRF hydrogen
minority heating experiments to be initiated on
Wednesday. Inner-wall limited discharges were run in
order to avoid L-H mode
transitions, which complicate antenna matching and
power balance analysis. D-
and
E-Port antennas conditioned up to 1.35 MW each relatively easily. The
J-Port antenna began to fault above
0.8 MW, with accompanying impurity
injections. A series of low power ramps at different plasma outer gap
settings
produced loading resistance measurements from the J-Port antenna that
indicate
similar values and power behavior to those obtained before the July
modification,
and different from the other two antennas.
A further series of
discharges with different outer gap settings
and a constant power level of 0.8
MW from each antenna in sequence allowed
a heating efficiency comparison of
the antennas to be made. The J-Port heating efficiency, as indicated
by
central electron temperature increase, stored energy increase, and
neutron
rate, was lower than the other two antennas (roughly half). A phase change of
the J-Port antenna
from (0,pi,0,pi) to (0,pi,pi,0) resulted in severe faulting
with ejections
from many different points on the antenna.
Further conditioning and
a repeat of the antenna comparisons were carried out
on Friday. The J-port
antenna conditioned better compared to the Wednesday
run, in the sense
that the number of faults were greatly reduced. However,
there was still quite a bit of glowing on the
antenna and many impurity
injections.
Power ramps were used to try and get around this condition and
these
were successful in getting to higher launched powers (up to 1.2MW) but
resulted
in disruptions due to the injections.
During this conditioning at a
plasma current of 1 MA the
disruptions started to occur at lower and lower
powers. Eventually it was necessary to lower the
power to 400kW (200kW each
pair) to get the antenna to run cleanly. The
current was then changed to 0.8MA
and conditioning was repeated. The total
achievable power was raised to ~1.2MW
during this set of conditioning
shots just as at 1MA.
On Friday, performance of the J-port antenna
was significantly better than
that on Wednesday. The central temperature increase, stored energy increase,
and
the neutron rate were only slightly lower (~15%) for the J-port antenna
compared
to the other two antennas.
DNB Systems
------------
The
Diagnostic Neutral Beam was brought up during the last week. The modreg
problems that caused DNB
operation to cease a few days before the end of C-Mod
operation in June
were traced to relatively minor problems with power for the
control system
and with fuses for the main beamline power.
An intermittent
problem early in the week with one of the beam cryo
pumps was associated with
high ambient cell temperature. This did not limit operation and has
not
recurred. Apparent modreg
cooling problems were traced to a faulty interlock
and resolved. The beam plasma source was conditioned early
in the week. The
accelerator was
then vacuum conditioned to approximately 47 kV. In the course
of the run on Friday, the beam was operated
into the plasma.
Travel and Visitors:
----------------------
Stew
Zweben (PPPL) came to C-Mod 8/31-9/1 to continue to work with the C-Mod
physicists
and computer engineers on optimizing and automating data
acquisition for
the new 2-D edge turbulence imaging diagnostic.