From:
WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Organization: sci.physics.plasma
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
Oct.
10, 2000
Plasma operations continued at Alcator C-Mod last week.
Three run days were
scheduled, but only one was completed. A total of 22
plasmas were obtained,
with a startup reliability of over 90%. Operation
was curtailed in order to
locate and correct a ground fault in the OH2L
circuit, which was ultimately
determined to be due to a failing capacitor
in the commutation bank. The bad
capacitor was identified and removed from
the circuit on Friday. Experiments
to evaluate the performance of the
four-strap J-port antenna with the newly
corrected phasing continued.
Plasma operations are scheduled to continue this week.
Physics
-------
ICRF
experiments were carried out with upper null, inboard limiter, and
(normal)
lower null target plasmas. The upper null and inner limiter targets
were
employed in order to obtain good comparison discharges in L-mode, without
the
complication of H-mode transitions. On one upper null discharge with 2MW
of
RF power an EDA H-mode was observed. The threshold power for this L-H
transition
was somewhat lower than expected, though higher than required to
obtain
H-modes with the standard lower null geometry later in the day. The
edge
electron temperature at the transition was observed to be significantly
higher
for the upper null than for lower null discharges; this result is
consistent
with previous experiments with reversed toroidal field and lower
null
targets, which also have the ion grad-B drift direction away from the
X-point.
Last
week, we obtained the first results from the neutral particle analyzer
since
it was reinstalled in B port. The diagnostic, which looks at passive
charge-exchange,
is a E||B-type analyzer and produces a 39 channel energy
spectrum of both
the hydrogen and deuterium neutrals.
Looking perpendicular
to the toroidal direction, the analyzer is
located slightly above the
midplane, and looks 5 cm above the magnetic
axis. First results indicate that
the new 4 strap RF antenna couples
differently to the edge versus the two 2
straps. The measured H/D ratio is
similar to the one obtained
spectroscopically but temporal differences
seem to exist; a complete
comparison awaits further experiments and
analysis.
ICRF Systems
------------
In L-mode, we
obtained good comparison discharges for
evaluating the heating
efficiency of the four-strap J-port antenna
relative to the dipole antennas at
D- and E-port; loading data were also
obtained. High power operation up to 2MW
was obtained from J-port; total
power with all three antennas operating
simultaneously reached 4.5MW into
an H-mode plasma. Operation of the J-port
antenna above 2MW was hampered
by arcing in either the transmission line or
the antenna. This problem is
under investigation; additional conditioning may
be required to increase
the power handling capability of the antenna.
The FMIT#3 (one of the
two transmitters feeding J-port) screen crowbar has
been firing on RF
trips. Installing a 480T5E (4800V, 5A)
fuse (150 msec at 20
amps) in place of the screen crowbar unit allowed us
to observe the screen
current spikes associated with antenna arcs. It appears that the screen
crowbar
response is faster than the arc protection (both have ~5-10 usec
response
time), and the crowbar is firing before the arc protection removes
the RF
drive. The screen crowbar in FMIT#2
(E-port) will be instrumented in
the same manner to investigate whether it
suffers from a similar problem.
It is clear from last week's
operation that if one transmitter faults on J the
other needs to fault as
well, so that monopole operation of the antenna, which
leads to impurity
injections, does not occur. This change
in the fault logic
has now been implemented, and will be tested in
operation this week.
DNB Systems
-----------
A
meeting was held to discuss the recent damage to the DNB drift duct
and
the low signal levels detected by the diagnostics. The damage to
the duct appears to be due to a combination
of factors: reionization
of the
beam and failure of the diverting magnet.
Repairs to the
drift duct are underway. Experiments to look more closely at the
reduction of signal
levels due to reionization and due to stray
fields were recommended, and
plans for these are underway. Spectra
from the plasma source were acquired under typical conditions of
current
and voltage in the source, but without extraction or
acceleration of a
beam. They appear to be absent of
impurities, but
this work is not yet complete.
Engineering
-----------
Final
drawing of the inner divertor "girdle" rear plate was reviewed with
the
manufacturer, and a final quote was obtained. 100% inspection of all
14
critical dimensions is included in the price. Delivery of the first
plate for
MIT approval is scheduled for November 27, 2000, with the last
of 12 pieces,
including two spares, to be delivered by Jan 17, 2001.
Travel and Visitors
-------------------
Ian
Hutchinson, Earl Marmar, Bruce Lipschultz, John Rice, Miklos Porkolab,
Jim
Hastie, and Bob Granetz are presenting papers based on Alcator C-Mod
research
at the 18th IAEA Fusion Energy Conference in Sorrento, Italy.
Also attending
the conference are Joe Snipes and Ron Parker. Earl Marmar
also presented a
seminar on Alcator C-Mod results to the Tore Supra group
in Caderache, France.
Montgomery Grimes, Ron Parker, and Dave Terry
visited Thomcast AG in Turgi,
Switzerland for a design review of the Lower
Hybrid power supply/modulator.