From:
WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
Oct
23, 2000
Plasma operations continued at Alcator C-Mod last week. Three
run days were
scheduled and completed. A total of 52 plasma shots were
obtained, with a
start-up reliability of over 80%. Experiments included
testing of the J-port
antenna in the four-strap configuration, high
performance operation with all
three ICRF antennas operational, and SOL
transport measurements in ohmic
L-mode plasmas.
Fresh
boronizations were carried out on Monday, and again on Thursday
night.
Average boron layer thicknesses of 1460 and 2050A were deposited in the
two
sessions. The second round of boronization was done in an attempt to
further
reduce the H/D ratio, which was still in the .05 to .1 range on
Wednesday.
However, H/D was not much reduced on Friday, indicating the source
of the
hydrogen is not being effectively covered by the boron layer. The
hydrogen
levels have been somewhat elevated since the partial up-to-air
incident in
late September. Startup reliability was
relatively poor (under
60%) on the first run following the first
boronization, which was followed by
extensive ECDC in Helium, but startup
on Friday, with only 90 minutes of
post-boronization ECDC, exhibited high
reliability.
No plasma operations are scheduled for this week, as
most of the physics staff
is participating in the APS Division of Plasma
Physics Meeting in
Quebec. Operations are planned to continue next week.
Physics
-------
One run day was devoted to
completion of MP#267, to explore the dependence of
SOL fluctuation
characteristics and attendant cross-field particle transport
on the
collisionality of the SOL. This run consisted of a partial repetition
of
an earlier experiment, during which the Lyman-alpha array was not
operating.
The goal was to complete a density, current and B-field scan with
ASP and
FSP probes reaching the separatrix and with the Lyman-alpha array
working.
The run was quite successful, completing four density scans with four
combinations
of current/field: (Ip=1.04, Bt=5.3), (Ip=0.53, Bt=5.3), (Ip=0.8,
Bt=4) and
(Ip=0.8, Bt=6). In addition, CII and CIII plume images from the
'burping'
FSP probe were obtained. From these results, we hope to infer the
magnitude
of Er and perhaps its variation across the SOL under a variety of
collisionalities. Analysis of data from this set of discharges
should allow
us to compute Deff profiles across the SOL for a variety of
collisionalities
and to relate changes in particle transport to
fluctuation characteristics.
One run day this week was devoted to
exploitation of the J-port ICRF antenna
in the four-strap configuration,
in combination with the D- and E-port dipole
antennas, to produce
high-performance EDA H-mode discharges. Maximum RF power
was ~4.5 MW, but
there were problems with keeping all the transmitters on for
the entire
flattop. Density, triangularity, RF
power, and
plasma current were varied.
ICRF Systems:
-------------
A
separate day was devoted to investigating the power limits of the 4-strap
antenna. The antenna coupled power was brought up to
2.8 MW; however, the
upper corner adjacent to K-port developed a glow and
injected impurities into
the plasma.
Typically, the plasma would transition into H-mode, some time
later
injections would begin, and the plasma would then revert to L-mode, with
most
shots ending in an early disruption.
The threshold for this phenomenon
was about 2 MW early in the
run. In an attempt to eliminate these
injections,
variations in outer gap (from 0.5 to 1.5 cm), a change in
plasma current, and
a change in target plasma density were made. None of these changes eliminated
the
glow or injections, and it appears that the effect is not strongly
dependent
on the target plasma parameters. The j-port external feedline and
resonant
loop has now been disassembled and arc damage and tracking has been
found
in an elbow in the decoupler section.
An arc at this location could
affect the relative phases of the
straps and conceivably result in the effects
seen.
Review
--------
The
Fall Alcator C-Mod Quarterly Review was held via video-conference on
Wednesday,
October 18. The main topics presented were Machine Status and
plans;
Engineering Activities; ICRF Results, focussing on the J-port antenna;
Lower
Hybrid Project Status; and the DNB Status and plans. Participants
included:
>From DoE OFES site: R.
Dagazian and C. Finfgeld
>From MIT PSFC site: S. Wolfe, J. Irby, S. Wukitch, R. Parker, E.
Eisner,
M. Porkolab, and I. Hutchinson;
>From Univ. of Texas
FRC site: R. Bravenec and W. Rowan
>From PPPL site: N. Bretz and
N. Sauthoff