From: IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT


            Alcator C-Mod Weekly Highlights
                  Jan 2, 2001
 

Alcator C-Mod was warmed up last week in preparation for in-vessel
work scheduled to begin this week.  Work on ICRF and Lower Hybrid equipment,
the glow discharge system, and new tiles and septum for the J-port
antenna also continued.

 
Physics
--------

Data obtained from the fast scanning magnetic and Langmuir probes during
EDA discharges have been carefully analyzed over the past few weeks.
A strong (~ 5 G at LCFS) magnetic component of the Quasi-Coherent (QC) mode
in the 100 - 150 kHz frequency range was found in EDA H-mode together with
local density fluctuations of (delta n)/n ~ 30% that were sufficiently in
phase with the electric field fluctuations to drive substantial particle
transport. Thus, the QC mode appears to be responsible for the increased
edge particle transport found in EDA H-mode.  A letter is being prepared for
submission to Plasma Physics and Controlled Fusion entitled "Quasi-Coherent
Signature of Enhanced D alpha H-modes in Alcator C-Mod", by J. Snipes,
B. LaBombard, M. Greenwald, I.H. Hutchinson, J. Irby, Y. Lin, A. Mazurenko,
and M. Porkolab. 


General Engineering
-------------------

Alcator C-Mod has been warming up since 12/22 and is now warm enough to
shut down the GN2 vaporizer and vessel heaters, both necessary operations
required before in-vessel work can begin.  Glow discharge cleaning
in helium will be run overnight to break down any remaining heavy boron
hydrides and will, along with multiple backfills with moist room air, make
the vessel safe for entry.

Work continued on a new board layout and upgraded design for our ratiomatic
vacuum gauge controllers.  A prototype controller was tested successfully
during the last week of the run campaign.  These controllers provide an analog
output proportional to the log of the pressure over the several decade
pressure range needed during C-Mod operation.

A modification to the glow discharge system has been made to allow
arc detection trip points to float with a programmed offset relative
to the electrode voltages.  As adjustments to electrode current are made,
or electrode voltages change during conditioning, the trip points now
automatically adjust to these changing conditions.
 

ICRF System
-----------

Preparations for the invessel work on the J-port antenna continues.  The new
boron nitride tiles, septum, and RF probes are in various stages of
detailed design or fabrication.  An internal review of proposed changes to
the antenna was held on 12/22/00, and a decision was made to proceed with the
up-to-air to implement them.

Work continued on the new demodulator design.  The design incorporates
modern, more easily obtainable limiter and mixer components, that
will provide more operational reliability and range.  Prototype testing
of the design is progressing.  The new demodulator is part of an ongoing
upgrade of the ICRF control system.

Repairs have been made to the phase shifter that limited the J-port antenna
power level during 70 MHz operation. 
 
Lower Hybrid System
-------------------

The first Lower Hybrid control chassis from National Instruments
arrived last week.  We have begun to set up the hardware and bring up
networking capability so that testing can begin.  This system will be used
for fast control of the lower hybrid RF phase and amplitude.  It will control
the power reaching the launcher from the twelve klystron sources.  Work is
also progressing on new analog fiber optic link circuitry.  Breadboarding of
some Lower Hybrid protection circuits was also started last week.


DNB System
----------

A small change to the DNB beamline vacuum system is being made so that
DNB testing can continue during the up-to-air.
 
Visitors and Travel
-------------------

Tom Fredian visited NIFS in Toki, Japan to install MDSplus on the CHS
experiment. Tom together with Jeff Schachter from General Atomics
installed MDSplus and MDSplus related utilities such as ReviewPlus and
provided training on the use of the software.

Several people from PPPL visited MIT over the last couple of weeks as part of our
collaboration.  Joel Hosea visited on 12/18-19 to join in the ICRF group
discussions on modifications to the PPPL J-port antenna.  Stewart
Zweben came 12/19-21 to participate in the experiments and obtain
additional edge turbulence images under different plasma
conditions.  The weekly diagnostic neutral beam meeting  was held on
12/18, with Norton Bretz and Gerrit Kramer attending via videoconference
and Gerd Schilling attending in person.

Yuri Rokhman and David Terry attended Labview software programming courses
from 12/18/00 to 12/22/00 at National Instruments in Woburn, MA.