From:
WOLFE@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Approved: plasma@cs.uml.edu
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
Jan
16, 2001
Work
continued at Alcator C-Mod last week on modifications to the J-port
ICRF
antenna, repairs and refurbishment to
the DNB diagnostics,
and continued maintenance of engineering
systems.
General Engineering
-------------------
The
LN2 sump was opened up last week and the LN2 pump filters were removed
and
cleaned. The filter for the TF
first-to-last turn leg was also
inspected and found free of any
debris.
Some components for the inner divertor upgrade are arriving
from our
vendors. Inconel 718
bolts needed for the upgrade are now in house as
are some of the
molybdenum tiles. A small quantity of
tiles from one vendor
did not meet spec and have already been returned to
the vendor to be reworked.
Major components such as backing plates and
C-plates that make up the girdle
are on schedule.
Modifications
are nearly complete of the OH commutation bank that will allow
for much
easier inspection and component replacement.
A failed capacitor
in one of these banks took several days to find
and replace during the
last run period.
ICRF
Systems
------------
The fabrication of the new boron nitride
tiles for the J-port antenna
was completed last week. The tiles were cleaned and then baked at
500C over
the weekend to prepare them for invessel installation. Fit up of the new
antenna septum
indicated that modifications to the stainless steel spline that
holds the
BN tiles would be required. These
changes will be completed
this week.
Mockups of the new dB/dt probes were also fit up on the antenna,
and
exact lengths for the coax signal leads were determined. We have decided
to delay the pumpdown
somewhat so that a better inspection and cleanup of,
and possible
modification to the antenna feedlines could be undertaken.
Tracking and
arcing marks discovered between the strip lines and septum need
careful
evaluation. These components have not
been inspected since the
beginning of the 2000 run campaign (Jan
00).
DNB and Related Diagnostics
---------------------------
The
DNB optical diagnostics have been carefully inspected. The CXRS optics
were still in alignment,
but had been coated during vessel boronizations.
They were removed from
the vessel and cleaned. Hoods will be
added to slow
the boron deposition rate.
The MSE/BES optical alignment was found to be
shifted by
approximately 1 cm since the last calibration due to disruption
damage to
one of the mirrors. That mirror and its
support were removed from
the vessel for repair. An inspection of the
inner wall of the vacuum vessel
opposite the DNB duct showed no beam
damage. Also, there was no further
beam-induced damage to the DNB
duct. Baking of the beam line has begun
in
preparation for offline operation of the beam which will continue
during
the up-to-air period.
Visitors and Travel
-------------------
Gary
Taylor spent the week at C-Mod working on the electron cyclotron
emission
diagnostics. A PPPL microwave source was used to optimize GPC2
signals and
to carry out tests of the instrument functions of both
GPC and GPC2.
Steve
Wolfe and Ron Parker participated in the DIII-D Advisory Committee
Meeting
at General Atomics in San Diego last week. Wolfe also presented
a talk on
recent C-Mod results to the DIII-D group.