From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
January
22, 2001
We continued
work on the J-port antenna, fixes to invessel diagnostics,
and DNB
development last week.
ICRF
Systems
------------
The PPPL J-Port ICRF antenna was removed
from inside the vacuum vessel last
week for a careful visual inspection
and relatively minor modifications.
However, arc damage found between the
stripline feeds and the support
septum will require a more extensive
cleanup and repair effort than planned.
These problems develop in areas
where we have an along-field (E parallel
to B) path between the stripline
and septum ground. Areas where the
stripline
arc paths are predominantly across the magnetic field showed
little or no
indications of arcing. Therefore we are investigating changes
to the stripline
that will keep the breakdown paths perpendicular to the
magnetic field and
therefore magnetically insulated.
A meeting
was held here at MIT on Friday, 1/19, with our collaborators
from PPPL, to
discuss changes to the antenna.
Another meeting will
be held on Friday, 1/26, to finalize the
design and discuss scheduling.
Lower Hybrid Project
--------------------
The
procurement process for the second largest purchase of the program, the
circulator,
is progressing. Proposals were
received from three vendors at
the end of December. A source selection committee consisting of
Monty Grimes
here at MIT, the head of the RF group at Bates Laboratory,
and an outside
consultant is in the process of reviewing the
proposals. The vendor
selection
process should be complete by the end of the month. The largest
largest item being purchased for the project,
the HV mod/reg supply, is on
schedule for an October 2001 delivery.
A
design review of the Lower Hybrid project is scheduled for February 7th
and
8th. Preparations for this review are
currently underway.
Modifications to the first klystron cart continue. This cart is the first
of three that
will be installed in the cell following the current run
campaign.
Design
of the klystron protection and control circuitry is being finalized.
In
addition, the two channel analog-to-serial fiber-optic transmitter board
was prototyped and some testing has started, the
design of serial-to-digital
analog fiber-optic receiver board is near
completion and a prototype board is
being built, and work on the LH active
controller continues. A test
fixture
and cables for LH vector modulator and I-Q detector tests was
finished
last week.
DNB and Related Diagnostics
---------------------------
The
bake of the DNB continued until Thursday of last week. The results
of the bake will be
assessed this week by generating a beam and
looking at the level of water
components being extracted from the source.
After a prototype test
fit in C-Mod, a hood was designed for the poloidal
CXRS system to retard
the build up of boron coating during C-Mod operation.
The permanent
repairs for the fueling system continued and will be finished
during the
current week. It was decided to repair
the damage to the MSE/BES
mirror by using a combination of epoxy and
straps to hold it in place.
Experiments are being conducted to find an
appropriate epoxy. Two were
tried
last week. Two more will be tried this
week. The one with the
best
combination of holding ability and outgassing will be chosen.
Visitors
and Travel
-------------------
Paul Bonoli and Bob Granetz
co-chaired RF and MHD topical group sessions
at the NSTX Ideas Forum at
PPPL held last week. Paul gave two short
presentations at the forum
titled
"Full-wave simulations of HHFW in NSTX Using Exact MHD
Equilibria"
and
"Future Modelling Plans for
HHFW Heating in NSTX Using TORIC & TRANSP",
while Bob gave
a talk discussing disruptions in spherical tokamaks.
Raffi Nazikian
came to MIT 1/16-18 to attend the Next Step Option PAC
review and work on
the reflectometer upgrade; Gerrit Kramer came to
MIT 1/16-18 to work on
the reflectometer upgrade and MSE optics
repair. Joel Hosea, Randy Wilson, and Gerd Schilling from PPPL were
at
MIT for the antenna meeting. Les Gereg
and Joe Frangipani, also
from PPPL, visited to help with the J-port
antenna.