From:
IRBY@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator C-Mod Weekly
Highlights
January
29, 2001
We continued
last week with design work on upgrades to the J-port
antenna
striplines. Work also continued on the
Lower Hybrid and DNB
systems.
Physics
-------
Joe Snipes spent the
week of 22 - 26 January 2001 at JET to take part in
experiments attempting
to obtain Enhanced D alpha H-mode on JET.
The
experiment took place on 24 January. While long ELM-free H-modes were
obtained, there was
insufficient time to complete the experiment due to
maintenance
problems. In the final shot of the
experiment, gas puffing into
an ELM-free H-mode did produce a mode that
was visible on the 92 GHz edge
reflectometer channel at about 40 kHz
during the ELM-free phase. The
mode
numbers have not yet been determined. However, since the density and radiated
power continued to
rise in the ELM-free phase, it was clear that the mode did
not
significantly reduce edge particle confinement. Contingency time was
approved for the experiment, and an
additional six shots will be performed
on 2 February in an attempt to
complete the experiment.
ICRF Systems
------------
Work
continued on the redesign of the striplines feeding the PPPL
ICRF
antenna. A first review of the proposed
modification was held
via videoconference on 1/26, with Randy Wilson, Bob
Ellis and Gerd Schilling
representing PPPL. We have decided to proceed with the detailed design
following
agreement on the conceptual design during the meeting. The
striplines will be rotated
approximately 90 degrees relative to their current
orientation to take
advantage of magnetic insulation. The
separation between
the stripline and the ground plane will be increased by
50% to reduce the
electric fields.
The conceptual design solid model can be viewed at
http://www.psfc.mit.edu/people/irby/jport_antenna_stripline3a.jpg
Digital
panel meters and associated modified circuit boards were
installed for
the tuning indicator upgrade to FMIT3 and 4.
Problems
were found with the limit switches during tests. These are now being
debugged.
The
dummy load remote switch upgrade for FMIT1 and 2 is waiting for
documentation
to be completed before the PLC connections can be made.
Design is
proceeding on an upgrade to the phase shifter and stub tuner control
system
which will allow for more automated control.
This change will require
some hardware installation in the CAMAC
system and a small amount of wiring
to the PLC in addition to new PLC
programming.
Lower Hybrid Project
--------------------
The
Lower Hybrid group is preparing for a design review to be held at
MIT on
2/7 and 2/8.
The circulator source selection committee met at MIT Bates
Accelerator Lab
last week. In
attendance were Monty Grimes (C-Mod), Abbi Zolfaghari (Bates),
and Bill
North (a consultant). It was determined
that more information from
the suppliers will be needed before a selection
can be made.
Two more of the three lower hybrid carts, have been
stripped, cleaned, and
repainted.
Each cart will support four klystrons.
The first of the carts is
now well along with installation of the
klystron support hardware.
Work continues on the fast hardware and
software needed to
control the klystron power levels and relative phases.
Tests were done
to verify hardware timing operation for
synchronization of multiple
controller
chassis. Using the asynchronous
internal 20MHz
clocks on two chassis running identical programs we
determined that time to
start sampling after the common start pulses
varied only a few tens of
nanoseconds from chassis to chassis with many
repeated tests. This is more
than
adequate for the application.
Progress was also made in program
development for the active controller.
A test program was written to allow
characterization of the vector modulator
and i-q detector operation. The i-q detector arrived last Friday and
we
are now making plans to
characterize its operation. Also, a
test
program for communicating between the host computer and two embedded
processors was started and some testing was done.
The Serial
fiber optic line (SFOL) receiver prototype board was built
and is ready
to be tested with the SFOL transmitter prototype board built
last
week.
DNB and Related Diagnostics
---------------------------
Work
continued on remounting one of the mirrors in the MSE/BES
in-vessel optics
enclosure on to its backing plate. Tests of several
epoxies having
advertised low outgassing rates were carried out
using a spare mirror and
a sheet of stainless steel. So far, the
epoxied mirrors are resistant to
shearing shocks. A final decision
on
the best means of securing the mirror will await some additional
tests
with epoxies and may include a supplementary means of securing
the mirror
to the plate.
The planned repairs to the process gas system for the
DNB were completed
last week and the beam was operated for two days. High voltage operation
at 48 kV was
easily achieved. The full energy
component is significantly
increased over December operation, but still
remains below 30%. We will
continue
our attempts to improve it this week.
Water was still present
in the beam, but at a reduced level which
appears to be decreasing with
operation, although more data is needed to
confirm this observation.
Power Systems
-------------
Our
power engineers met with representatives from NWL to discuss the failure
of
two capacitors used in our commutation bank.
The capacitors will be
sent back to the company for analysis and
possible repair. These capacitors
have
already been replaced with spare ones, and the commutation banks are
ready
for operation.
Visitors and Travel
-------------------
Dr.
Parvez Guzdar, from the University of Maryland, visited last Thursday.
He
presented his recent theory of LH transitions and we had useful
discussions
regarding possible comparisons with C-Mod threshold data.
Jean
Jacquinot, director of the Tore-Supra program at the CEA in Cadarache,
France,
visited the PSFC last week. During his one-day visit, in addition to
presenting
an IAP lecture on the Highlights and Plans of the European Fusion
Program,
he also toured C-Mod and held discussions with various Alcator
scientists.
Among the topics covered were possible collaborations with the
Tore-Supra
group on ICRF, lower hybrid and diagnostics. He was also consulted
with
regard to our proposed J-Port ICRF antenna modifications.
Eric Melby
traveled to Los Alamos National Laboratory last week (Jan 23-25) and
gave
a talk entitled "Phase Contrast Imaging Observations of Ion
Bernstein
Waves in the Alcator C-Mod Tokamak."