From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
February
5, 2001
We
continued work on the RF antenna redesign last week. Work also
continued on new diagnostics for the antenna and
the new inner
divertor.
Physics
-------
Joe
Snipes participated remotely in a continuation of the JET experiments
attempting
to obtain Enhanced D alpha H-mode on JET on Friday, 2 February.
There were
seven discharge with -pi/2 phasing of the ICRF antennas at 2.8 T,
and 2
MA, to drive current near the q=1 surface, in an attempt to destabilize
sawteeth
and prevent long 'monster' sawteeth.
The first discharges had less
than 2 percent hydrogen concentration
and drove a substantial fast ion tail
that did stabilize the sawteeth such
that large n=2 MHD modes were driven
after the first sawtooth collapse,
which substantially degraded confinement.
Raising the hydrogen
concentration helped to destabilize the sawteeth and
eliminate the large
MHD modes. There were, however,
problems with the ICRF
such that only 5 to 6 MW of RF power was available,
which was insufficient to
get into H-mode. 2.5 MW of NBI was added on top of the available RF power
to
stay in H-mode. Several long ELM-free
H-modes were obtained as the target
density was raised in an attempt to
find a perhaps narrow operating window in
which the EDA H-mode may exist
on JET. However, there was insufficient
time
to complete this density scan. There was no clear evidence of EDA H-mode in
the pulses
obtained, but more analysis of the reflectometer and magnetic
fluctuations
needs to be done to see if there were any modes present that
could be
related to the Quasi-Coherent modes observed in C-Mod EDA H-modes.
ICRF
Systems
------------
The solid model design for the new antenna
components has been completed, and
we have begun fabrication of prototype
parts out of aluminum. The new
design
incorporates better use of magnetic insulation and reduces the
electric field
at critical locations.
Combined with changes already being made to the front
of the
antenna to reduce impurity injection at high power levels, we feel
these
changes will result in better antenna performance. The prototype
components will be checked in our antenna test
fixture for any design
errors after which the inconel stripline components
will be made.
A schedule has been developed to implement the changes
to the antenna.
We expect installation of the antenna with the new
components to be
complete by 3/23.
Following pumpdown, vacuum conditioning, and
plasma startup, plasma
physics operation will begin in early May and continue
through early
June. Please find our short term
schedule at
http://www.psfc.mit.edu/cmod/operations/short_term.pdf
Maintenance
continues on the ICRF transmitters. All
cavities are being
inspected and refurbished where necessary. Mechanical and electrical systems
needed
for tuning the transmitters are being reworked and checked. PLC
connections are being determined
for the new automatic dummy load switching
system.
Lower
Hybrid Project
--------------------
Work continued last week on
development of the control hardware and
software for the lower hybrid
project. Progress was also made
on
the three klystron carts with installation of filament
transformers,
chokes, and high voltage bus. Preparations for the Lower Hybrid
review to be held at MIT
on 2/7 and 2/8 continued.
More information has been supplied by the
vendors bidding for the
lower hybrid system circulators. The selection committee should be
able
to reach a decision soon on what vendor to use.
A great deal of
progress has been made on the Lower Hybrid Active
Controller system. The power supply for the I-Q detector and
vector modulator
characterization tests was completed, and tests on the
sample I/Q detector
were
conducted. Initial results indicate
some unexpected non-linearity.
Testing
of the serial fiber optic link (SFOL) transmitter and receiver is
underway. A synchronization test for a multiple PCI chassis configuration
was
done, indicating that only tens of nanoseconds of jitter is present.
This
jitter is acceptable for our application.
Inner Divertor
--------------
Fabrication
of the inner divertor components is proceeding.
Machining of the C-plates,
which together with the rear plates, form
the major support structure of
the divertor is now well underway.
The rear girdle plate inner and outer
surfaces have been machined using
a wire EDM technique. Fixturing and tooling for cutting the holes
is
now being set up. 350 of the
1300 tiles needed for the project have
been delivered. These tiles are now being delivered at a
rate of about
200 per week. All
bolts for attaching the C-plate to the rear girdle
plate have been
received, age hardening, and will soon be silver plated.
All transition
keys and tile screw keepers are complete and in house.
Visitors and Travel
-------------------
Ben
Carreras from ORNL began a visit at MIT last week. He has been
working with Amanda Hubbard on interpretation of
C-Mod H-mode threshold
data and discussing possible edge instabilities in
the EDA regime.
He has also been working with Brian LaBombard the analysis
of
fluctuation data.
A successful Preliminary Design Review of
the Lower Hybrid launcher
was held at PPPL on 1/31; Ron Parker, Monty Grimes and Paul
Woskov
attended from MIT.
Randy Wilson and Bob Ellis from PPPL
visited last week to participate
in the ICRF antenna rework.
Martin
Greenwald was at UCLA last week as part of the FESAC sub-panel
reviewing
the US fusion science theory and modeling program.