From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
March
9, 2001
We continued
to maintain transmitters and power systems, develop Lower Hybrid
systems,
and fabricate new J-port antenna components.
Work is proceeding
on improvements to the ICRF control system. A design review was
held on a new CXRS
shutter.
ICRF Systems
------------
Inconel
stripline components for the J-Port antenna modification are being
produced
both in our shop and by two EDM vendors.
We expect to have all
components complete and ready for plating
within the next two weeks.
Modifications to the Faraday shield are
complete, and the shield has been
assembled successfully on the test
stand. Work on the new dB/dt RF
probes
for the antenna also proceeded this week. Four of the six probes are
ready for calibration. Fabrication of the remaining two that will
be
mounted on the antenna septum is nearly complete.
A change to the IPA drive point
location and installation of a
matching transformer greatly reduced the
drive power required for
this stage of the transmitter. Saturation of the IPA stage limited
transmitter
performance somewhat during the last run period. Similar
improvements will be made as needed to the other
transmitters.
We have modified the new demodulator board layout per
manufacturer
recommendations and are awaiting new quotations for these
boards.
The RF components and modules used in our fault detection system
are being
carefully tested and parameterized. These systems currently require very
time consuming
recalibrations for each frequency change.
We are investigating
both programmable modules to make automatic
gain adjustments, and changes
to the electronics and cabling to increase
bandwidth so that manual
recalibration is not required.
A PCI
based data acquisition system has been setup.
This system will provide
very fast data logging of forward and
reflected power and other fault
indication signals. Testing has begun to verify that all
channels are
working. Work has
started on the auto-tune system which links CAMAC analog
outputs with PLC
inputs. Software is in progress and the
associated patch
panel installation and wiring has started.
DNB
---
A
design review was held for shutters to be installed invessel to protect
CXRS
optics. It was strongly suggested by
the DNB Review Committee that this
work be done during the current up to
air. The basic design was
approved.
A number of suggestions for improvement were made during the
review and
are being implemented.
Lower Hybrid MIE
Project
------------------------
We finalized the design of the
anti-alias filters for the D-Traq digitizers
to be used as part of the
lower hybrid data acquisition system.
The SFOL transmitter was completed,
and we have begun testing the SFOL receiver.
The SFOL link must be
operational soon so that closed loop tests of the
active feedback system
can begin. Programming of the active
feedback loop
is proceeding. As we
approach a control program with realistic input, output,
and processing
modules, an assessment of the ultimate control system speed
will be
made. A network problem with the PXI
chassis was resolved this
week.
Data characterizing operation of the vector modulator and I/Q detector
operation
has been taken. Both the vector
modulator and the I/Q detector
are performing as expected. The network analyzer will be used to make
more
accurate measurements for comparison with our test program results.
Representatives
from C-Mod, MIT, and SMMA (the contractor hired by
MIT), met this week to
discuss the electrical work that will be needed
during lower hybrid site
modifications. The proper breakers to
use,
cabling required, and cable runs have been agreed upon.
Electro-Mechanical
design of the transmitter equipment rack is nearing
completion. We have been notified by the vendor that the
contract for the
klystron circulators is in place. Work is proceeding on klystron cart
modifications
and wiring, and work has also begun on modifications to the
equipment
racks. We have ordered the EMI/RFI
protected cabinets for
the transmitter racks.
Power
Systems
-------------
The work on the EF1 commutation switch
capacitor bank continues. The
machining
of the extrand supports is in progress.
Preventative maintenance of
power supply control boards continued.
Inner Divertor
--------------
Over
150 upper transition tiles were received from our vendor this week.
A
successful test fit of these new tiles into our rear and c-plate mockups
was
done shortly after their arrival.
Dimensions of ten tiles will be
computer checked as part of the QA
process developed for the tiles.
The vendors supplying the rear and c
girdle plates are still on
schedule.
A picture of one of the rear backing plates can be seen at:
http://www.psfc.mit.edu/cmod/operations/EngImages/MACHINE/Divertor/Rear_girdle_02.jpg
Note
that none of the ribs that will lock the tiles into position have been
machined
into the plate as yet.
Travel and Visits
-----------------
Phil
Ryan visited from Oak Ridge this week to look at J-port antenna
components
and get drawings and measurements needed to model the
antenna.