From: irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject:  Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT


            Alcator C-Mod Weekly Highlights
                  March 16, 2001
 

We continued to maintain transmitters and power systems, develop Lower Hybrid
systems, and fabricate new J-port antenna components.  Work is proceeding
on improvements to the ICRF control system.  Work continues on the new
inner divertor.  A design review of changes to the J-Port antenna was held.


ICRF Systems
------------

We expect all inconel components for the J-Port antenna modifications to
be in-house by early next week.  Some machining and finishing in our shop to
the components will be required before they can be welded, plated, and
baked, at which point they will be ready for installation.  E-beam welding
tests are being done to inconel samples, and fixturing is being developed
to support the welding of the actual components.  Our hydraulic press was
used to successfully bend the two long inconel striplines into the proper
shape.  Several fiber views of light from possible plasma discharges around
the striplines are being planned.  We also expect to make a pressure
measurement at this location. Designs for the fiber periscopes, and pressure
sampling tube are being produced.  New holes in the horizontal flange for
these measurements will be drilled over the next few days.  Components for
the diagnostics are being made in-house.

On Wednesday, 3/14, a final J-Port antenna review was held via video
conference.  Steve Wukitch presented details of the problems we had with
the antenna, and the changes we are making to allow full power performance
during the next run period.  Steve's presentation can be found at

www.psfc.mit/people/wukitch/antreview.pdf


Attending the review were:

ORNL  Phil Ryan
      Rick Goulding

PPPL  Gerd Schilling
      Bob Ellis

GA    Bob Pinsker

C-Mod Steve Wukitch
      Rejean Boivin
      Jim Irby
      Peter Titus
      Bruce Lipschultz
      Brian Labombard


UTexas      Perry Phillips


There was general agreement on the antenna modifications.  There was
also strong agreement that phase measurements with fast time response
are essential.  These measurements are being implemented, and
the antenna will not be operated without them.  Since the modifications
require supporting the antenna at the top and bottom from the center of the
antenna, a concern was raised about thermally induced stresses.
FEA analysis of the antenna performed following the review indicates that
these stresses are in fact small.

We continue to perform maintenance and inspections of the transmitters.
FMIT#3 was brought up to full power into a dummy load this week.  However,
during these tests, a new intermediate power amplifier tube failed after
approximately 10 hours of operation.  An older spare tube is being installed
and the new tube is being sent out for evaluation.  Extensive tests of the
IPA protection circuits and cooling systems indicated all were functioning
properly.


Diagnostics
-----------

UT-FRC and U. Idaho personnel are continuing bench measurements to
determine the precise spatial resolution of  the antenna for the High
Resolution ECE heterodyne system.  Based on the initial results, a
new waveguide with improved resolution was designed at UT and is being
fabricated at UT for installation prior to the end of the current
down period.


DNB
---

The detailed shutter design for the CXRS toroidal optics was
completed.  Parts for the shutters and their actuation mechanisms
were ordered with the expectation of delivery next week.   Detailed drawings
have been given to the Alcator machine shop for manufacture.


Lower Hybrid MIE Project
------------------------

We continue to develop the active controller program.  Work this week
involved primarily more work on the input/output routines,
together with another set of routines to set limits for the I/Q detectors.
We continue to prepare the three klystron carts for operation.
Measurements are being made in the cell to verify that columns for
the new mezzanine to support the klystron carts will not interfere with
other equipment in the cell.  A meeting was held on 3/16 to decide
which port the first launcher would occupy.


Power Systems
-------------

The machining of the support structure for the EF1 capacitor bank
has been completed.  Signal cabling for ground current monitoring of the
commutation banks is being installed.  We have begun to setup for testing
and calibration checks of all commutation switch Rogowski coils.


Inner Divertor
--------------

Inner vessel wall tiles and support plates were removed this week to
check stud alignment in preparation for the new inner divertor
installation.  Our rapid prototype plastic divertor components were installed
successfully.  Pictures of the fit-up can be found at

http://www.psfc.mit.edu/cmod/operations/EngImages/CmodImages.asp?ref=/MACHINE/Divertor/

Tiles and other divertor components continue to arrive.


Travel and Visits
-----------------

Earl Marmar, Ron Parker, and Miklos Porkolab attended the DoE
Budget and Planning Meeting March 13 to 15 in Gaithersburg.  Earl and
Ron gave talks on C-Mod and the LH MIE Project.  The viewgraphs from
these talks can be found at

http://www.psfc.mit.edu/cmod/sciprogram/CMod_Budget_Meeting_Presentation.pdf

Amanda Hubbard gave a  talk at California State University of Sacramento
on Thursday, 3/15, as part of the APS/DPP Distinguished Lecturers in Plasma
Physics series,  entitled "Understanding and Improving Energy Transport
in Fusion Plasmas."