From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Organization: MIT
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
March
23, 2001
Fabrication
of the J-port antenna stripline components is nearly complete.
We
continued work on the ICRF control system, the DNB, inner divertor,
and
the Lower Hybrid MIE Project.
Physics
-------
Double
transport barrier plasmas have been observed by operating at 4.5 T so
that
the 78 MHz ICRF resonance is located near r/a = -0.5. These plasmas have
a
strong gradient in the electron density profile, and the core density is
seen
to increase continuously in time until radiative collapse. The barrier
is
also seen in the ion temperature profile, indicating that this is a true
energy
barrier. Application of additional ICRF power at 70 MHz to these
plasmas
is seen to arrest the increase of the electron density, to heat the
ions
at the plasma center, and to hold the double barrier in steady state
for
nearly 10 energy confinement times. The bootstrap current is estimated
to
be of the order of 100 A/cm^2 at r/a = 0.5 for these plasmas.
ICRF
Systems
------------
All inconel components arrived in-house
this week and are undergoing final
machining, polishing, and fitup procedures. Test inconel pieces have been
successfully
e-beam welded, and welding of the stripline components is now
planned for
early next week. Copper plating of the
antenna backplates
has been completed, and the backplates are back on the
antenna test stand
to aid fitup tests of the striplines. Machining of the
J-port flange
for installation of the new diagnostics has begun. Four windows and
a port for a pressure
measurement will to added to the flange.
A
dB/dt probe has been tested on the antenna mockup and shown to
have
a more than adequate rejection of electrostatically coupled signal.
Six
of these probes will be installed on the antenna.
Following
replacement of the intermediate power amplifier tube, FMIT#3
was brought
up successfully to full power into a dummy load. Both
FMIT#3 and FMIT#4 are now ready for operation. A matching transformer
similar to the
one installed in FMIT#4 was installed in FMIT#3 this week
to improve the
drive to the IPA stage. Similar
improvements in the standing
wave ratio and drive efficiency were
found. We continue to work on the
rf
control system.
DNB
---
Resumption
of arc conditioning was delayed by a failure of the arc and
snubber power
supplies. The failure was traced to two
15V, 2A supplies
which failed when the house power was cycled. The 15 V supplies
have been replaced
and work on the arc and snubber supplies was resumed
on Friday. Machining of the new CXRS shutter components
has begun.
At the weekly videoconference meeting on the C-Mod
diagnostic neutral
beam, Paul LaMarche (PPPL) presented his redesign of
the MSE lens mounts.
This upgrade is planned to be installed during
C-Mod's upcoming long opening,
and should prevent any further lens and
mirror damage from disruption shocks.
Lower Hybrid MIE Project
------------------------
All
modifications to, and new wiring for, the klystron carts will be
completed
in the next few days. The design of the
klystron equipment rack
component layout is also nearly complete. Wiring tasks for these racks have
have
been released. The klystron equipment
racks will primarily contain the
tube protection boards and associated
fault logic. Work continues on
the
klystron phase and amplitude control system. A complete feedback loop has
been tested and results
indicate a very good response time. A
test of a
new arc detection technique that relies on the detection of the
rf produced
by the arc well above the 4.6 GHz drive frequency looked very
promising.
This technique may allow arcs on the plasma side of the vacuum
windows to be
seen in sections of waveguide well before the
launcher.
Work on the launcher continued at PPPL this week. PPPL is finalizing
the design of a
fixture for testing the water loads designed here at
MIT that are needed
to dump the reflected power from the launcher.
Four water pipes installed
in the waveguide will conduct away the power.
Another fixture for
calibrating the alumina windows is being fabricated.
The alumina bricks
for the launcher's air/vacuum interface have been ordered.
Preparations for
the Lower Hybrid final design review are also underway
at PPPL.
Inner
Divertor
--------------
Machining continues on the divertor
backing and C plates. Vendors
continue
to produce tiles. All tiles for the
divertor are expected
to be in-house within the next 3 to 4 weeks.
Travel
and Visits
-----------------
Martha Redi from PPPL visited on
Tuesday, 3/20 to discuss plans and early
results of gs2 simulations of
particle transport in ITB regimes.
She
had discussions with Catherine Fiore and Martin Greenwald about
the
experimental measurements and accessing C-Mod data.