From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator C-Mod
Weekly Highlights
March
30, 2001
Work
continued on modifications to the J-Port antenna and ICRF control
system.
The DNB, inner divertor, and Lower Hybrid MIE projects all moved
forward
this week.
ICRF Systems
------------
All ebeam
welding of the striplines has been completed.
Final machining
operations are now being done on the components. An 0.0005" layer of
copper will be
plated on the striplines early next week followed by a
vacuum bake. A picture of one of the long stripline can
be seen at
http://www.psfc.mit.edu/cmod/operations/EngImages/RF/ICRF/P0001408.JPG
The
last of five diagnostic access holes in the J-Port flange has been
completed. Invessel cleanup inside the port can now
begin in preparation
for installation of the antenna. We expect reassembly of the antenna to
begin
within the next 10 days as scheduled.
All six of the B-dot probes
for the J-Port antenna have been fabricated.
An absolute calibration of
the probes will be done over the next few days.
Invessel cabling and cable
clamps are being installed for the probes.
Small adjustments to the
auto-tuning PLC program were completed this week.
This system is now operational. Changes to the ICRF tuning
components can be made from the
VAX workstations with a direct link
from the tuning program.
The
prototype phase demodulator board has been sent out for fabrication.
However,
improvements are also being made to the PPPL demodulator modules to
improve
their phase response during fault conditions over the next run period.
We
continue maintenance and upgrades to the #1 and #2 transmitters.
DNB
---
The
automatic mode for the DNB was brought into operation this week and the
time
between pulses decreased from 150 to 120 s.
Data for the arc current
overshoot was taken. An anticipated strong dependence on the time
between
the prepulse and the main pulse did not materialize. The overshoot does
change with the
time between pulses, but is not eliminated.
We will continue
investigation of the overshoot by making
correlations with spectral
measurements of the arc plasma and by
monitoring it as a function of
conditioning time.
Lower
Hybrid MIE Project
------------------------
More testing of the
active controller was done this week. A
loop
test summing amplifier was built so that we could add an error
voltage to
the closed loop to test the PID program calculations. We did some tests
with both square wave and sine wave
perturbations and were able to show
that the program is working
correctly.
The high yard protection systems are being reviewed and
work is underway to
verify that the existing cabling and breakers are acceptable for supporting
the
new LH systems, and that we will be able to set the protective relays for
proper coordination.
A meeting was held with MIT this week to
finalize the schedule for the
MIT funded LH site modifications. Details of the Hi-Yard changes and
work
to be performed in the cell were discussed.
Work continues on the klystron carts.
Inner
Divertor
--------------
Tiles continue to arrive and proceed
through QA. We now have all the
upper
and lower transition tiles.
The vendor is on schedule fabricating the rear
girdle plates. They
have stress relieved all plates to prevent movement after
machining. Another vendor has nearly completed
machining of the ribs
on all the C plates. This process is the most difficult of the machining
operations
and provides the keys to limit motion of the tiles. High
strength bolts and nuts continue to arrive and undergo
testing.
Power Systems
-------------
Modifications to the EF1U-L
commutation bank have begun. The other
banks
are now complete except for installation of a few recently repaired
capacitors.
Diagnostics
-----------
A laser
will be loaned to MIT from UT-FRC for cold pulse experiments during
the continuation of the current run
campaign. This laser was used
on
TEXT for the same type of experiments.
It was taken out of
storage and tested recently at UT-FRC. The laser is now packed for
shipping
and should arrive for installation and commissioning prior
to the
resumption of experimental work.
The first of the CXRS shutter parts
was delivered by the MIT Central
Machine Shop. Other parts are being fabricated in the Alcator and UTex
shops
as we press to get the shutters installed invessel.
Travel
and Visits
-----------------
Stewart Zweben visited this week
from PPPL to discuss upgrades to his
fast imaging fluctuation
diagnostic.
Jim Irby visited PPPL last week for discussions with
Douglas Loesser,
Randy Wilson, Stefano Bernabei, and Gerd Schilling on the
Lower Hybrid
Launcher. He also met
with Raffi Nazikian and attended a PPPL/MIT proposal
review of the
reflectometry collaboration.