From: irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT


            Alcator C-Mod Weekly Highlights
                  April 6, 2001
 

Installation of the J-Port antenna began this week.  Work continued on the
RF control system, DNB, inner divertor, and Lower Hybrid MIE project.


Physics
-------

Analysis of neutral particle transport in the main-chamber scrape-off layer
(SOL) at the outer midplane has been performed for a small set of discharges
using a newly developed neutral transport code, KN1D. This new
code is a 1-D space, 2-D velocity kinetic code that treats atomic and
molecular transport including molecular dissociation, charge exchange, and
elastic collisions between neutral and plasma species. The code takes as input
the measured plasma density and temperature profiles in the main-chamber
scrape-off layer and the measured molecular neutral pressure near the wall at
the midplane. A unity recycling condition on main-chamber limiter and wall
surfaces is imposed, consistent with that expected in experiment.
In most cases, neutrals contribute to an inward-going heat flux 'pinch' across
the separatrix. A comparison with the magnitude of cross-field plasma heat
convection in the near and far SOL shows that neutrals play only a minor
role in the total heat transported across the scrape-off layer.

A meeting was held at MIT on April 3 to investigate the possibility of
using Li as a divertor material in Alcator C-Mod. Mike Ulrickson
(SNLA), Dennis Whyte (UCSD), Dick Majeski (PPPL) and Jeff Brooks
(ANL) all came to participate in this meeting. Participants from
C-Mod included Bruce Lipschultz, Brian LaBombard, Jim Terry, Spencer
Pitcher, Jim Irby, Earl Marmar and Bob Granetz.

Dennis Whyte spent an additional day at C-Mod discussing
wall-recycling data taken at DIII-D as part of a joint mini-proposal
in which Bruce Lipschultz participated. Progress was made on
issues of how to present data from C-Mod and DIII-D jointly and in what
format. Discussions with Brian LaBombard included observations and
computations of particle and energy fluxes in the SOL of C-Mod and
a comparison of fluctuations phenomena observed in the SOL of DIII-D
and C-Mod.


ICRF Systems
------------

Machining and polishing of all stripline components were completed this
week, and copper plating of these components will be completed early
next week.  Following a vacuum bake, they will then be ready for installation
invessel.  A picture of one of the long striplines ready for plating
can be found at

http://www.psfc.mit.edu/cmod/operations/EngImages/RF/ICRF/P0001428.JPG

A fitup invessel of the new antenna support plates has been completed
and studs have been installed to support the plates.  The new J-Port windows
and pressure port have been installed on the flange and are ready to be
leakchecked.  The flange support plate has been taken invessel and punched
for drilling at the new diagnostic port locations.  The Faraday screen has
been aligned on the test stand and will be ready for installation following
laser welding of the new gap cover plates.  The vessel wall in and around
J-Port has been ground and polished to a near mirror finish in preparation for
the antenna installation.

Testing and calibration was begun this week of the six phase demodulator
modules to be used for phase fault detection on the D, E, and J-Port
antennas.  The new prototype demodulator board is back in house from the
vendor and will soon undergo testing.


DNB
---

The beam was operated in automatic mode for two days this week as we
continue the conditioning process.

The optical sections of the edge and core CXRS in-vessel optics were
cleaned, calibrated, and reassembled.  In-vessel backlighting tests
demonstrated that the alignment is adequate for the experiments.  The
shutter assemblies for the two systems are under construction and
delivery is expected on Monday.  Installation of the shutter
actuation cables has begun.


Lower Hybrid MIE Project
------------------------

Work continued on the serial fiber optic link.  The prototype is working
and undergoing tests.  Digital I/O definitions are being finalized for the
LH phase and amplitude control system.  Some hardware/software issues that
have caused program crashes are being worked out with the
vendor.

A 3 kW, 2.45 GHz source is being setup in the LH lab and will be used to
test arc detection concepts and electronics.

Further progress is being made at PPPL on the design of details of
the Lower Hybrid launcher.  Advantages are becoming apparent in
replacing the original geared chain-driven launcher drive with a
hydraulic version.

Over the last two weeks, Ron Parker and Montgomery Grimes visited Tore-Supra,
JET, and our LH high voltage power supply vendor.  At Tore Supra, they
discussed recent lower hybrid current drive results and plans for the next
campaign including the design of the new launching antenna.

At JET, recent progress in the JET lower hybrid experiments was discussed.
These experiments had been plagued by coupling problems, especially during
high-power auxiliary heating. Recently the coupling has been substantially
improved due to a number of factors including better congruence between the
coupler and plasma shapes,  puffing of CD4 near the launcher to increase
the plasma density near the multijunction grill, and four days of dedicated
run time during which optimization of the coupling could occur.  A
"trophy shot" with 3 MW of lower hybrid power and ~ 20 MW of NBI and ICRF
power that maintained a reversed shear discharge for ~ 8 s was obtained.
Both electron and ion ITB's were formed and the non-inductive current drive
has been calculated to be > 80%.  The possibility of expanding the
collaborative relationship between C-MOD and JET was also discussed.

The Lower Hybrid high voltage power supply is progressing on schedule.
Preparations for installation and the required acceptance tests were
discussed.
                                         

Inner Divertor
--------------

Tiles continue to arrive and machining continues to be done on the
new inner divertor.  A picture of one of the C-Plates being machined
can be found at

http://www.psfc.mit.edu/cmod/operations/EngImages/MACHINE/Divertor/Mar30_05.jpg

Note the keyways for holding the tiles in place.


Power Systems
-------------

Work on the EF1U-L Capacitor bank modifications was completed this
week.   

We have started installation of new Hi-Yard instrumentation to better
monitor power delivered to the LH, ICRF, and Alternator systems this week.


Travel and Visits
-----------------

Steve Wukitch attended the US-Japan RF physics workshop in Japan March 22-24.

Miklos Porkolab attended the Annual Sherwood Fusion Theory Conference in Santa
Fe, NM, on April 2-4. Paul Bonoli also attended the conference.

Bob Childs was in Brooklyn, NY supervising copper plating of the stripline
components.

Martin Greenwald was in Lausanne for an International Database meeting.

David Mikkelsen (PPPL) presented a talk on "Turbulent Transport Simulations
of C-Mod" at the Confinement Database and Modelling Workshop at CRPP
in Lausanne - 2-6 April, 2001.