From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
April
13, 2001
Work
continued this week on the J-Port antenna modifications, LH
MIE Project,
and several diagnostic systems.
Installation of the
J-Port antenna will begin early next
week.
ICRF Systems
------------
All stripline
components for the J-Port antenna upgrade are back in-house
following
copper plating. Final machining
operations have been completed
and the components have been fitup on the
antenna test stand. A picture
of
the fitup can be seen at
http://www.psfc.mit.edu/cmod/operations/EngImages/RF/ICRF/P0001488.JPG
Note
that the surfaces conducting rf currents have been copper plated while
the
rest of the surfaces have been left bare inconel. This design
detail reduces disruption forces by a factor of
two.
The components are now undergoing a vacuum bake after which
installation
invessel will begin early next week.
The windows,
pressure monitoring tube, electric break, bellows, and gauge
have all been
successfully leakchecked on the J-Port flange.
The fibers
have been installed in the windows, back illuminated,
and aligned to view
the striplines.
Components for supporting the gauge, magnetic shielding,
and
pressure tube have been machined and are undergoing fitup. The
PMT amplifiers needed for the fiber
views have been modified for the faster
response time needed for fault
detection and are ready to be re-installed
in the cell.
The rf
vacuum feedthroughs are being installed and leakchecked.
Sixteen of
approximately twenty phase demodulator modules have been upgraded,
checked
for proper operation, and re-installed.
The primary focus for work
on the rf instrumentation has now
shifted to maintenance of interconnecting
wiring and cabling.
Diagnostics
-----------
The
CXRS F-Top periscope has been reinstalled.
Transmission measurements
were completed and show that the
transmission increases from more
than 70% at 2500 A to more than 80% at
7500 A. Measurements
following
removal at the beginning of the current vacuum break
indicated no
transmission at the lower wavelenghts due to
plasma-induced coating. The coating was removed by polishing.
The
machining of the core and edge shutters for the invessel CXRS optics
is
complete. Both systems have been
re-installed invessel and tested
for proper operation. The only remaining task is spot welding the
control
cable runs into position.
Adding shutters to these systems was a strong
recommendation of the
DNB review committee. The
high-resolution edge CXRS
system has also been re-installed. A new window and grounding grid have
been
added to this systems to protect its mirror from glow discharge
cleaning
and boronization.
The modified waveguides for the
heterodyne ECE system were brazed, cleaned
and baked, and the optics were
re-installed at F-port. The
modifications to
the in-vessel quasioptical focussing system are now
complete. The transition
waveguides
were modified to improve the imaging of the ECE system and
increase the
maximum k that can be observed by the system.
Work continued on the
design of the driver electronics for the MHD
antenna.
Lower
Hybrid MIE Project
------------------------
At PPPL, two
three-window prototype couplers have been successfully
brazed and passed
leakchecks. A process for repairing
leaking
window seals was also developed and tested successfully.
Windows
with larger corner radii, which would have reduced stress levels
compared
to the current windows, are also being prepared. These tests
are very encouraging, and indicate we can expect
good results as we go
to the 24 waveguide coupler modules needed for the
lower hybrid launcher.
MIT and PPPL are discussing plans for high power
component testing to
be done when the high voltage power supply and
klystron installations
are complete in approximately seven to eight
months. The list includes
3db
couplers, water loads, DC breaks, phaseshifters, and tapers.
Limiter
shape and field ripple data have been given by MIT to PPPL to be
used in
designing the coupler plasma facing surface.
The prototype digital serial fiber optic link is now
running at its
design speed of 50 Ksamples/s. The prototype will be linked to the
I/Q vector modulator as
a primary test of the link. Work on the
LH
phase and amplitude control system continues. Digital i/o definitions
and descriptions have been
completed.
The
walk-through for prospective contractors for the LH site modifications
was
held this week.
Work proceeds on the klystron cart modifications
and wiring. A new
safety interlock
key/lock was test fitted. This lock is
manufactured by
the same company used by our high voltage power supply
vendor, and will
use their key interlock system. This system will provide seamless
compatability with the
safety key interlock system in the power supply
container used to provide
access to high-voltage areas associated with the
Lower Hybrid
transmitter.
The electrical design of the transmitter control electronics
is nearly
complete. Work this
week concentrated on the interconnection wiring;
specifically, the EMI/RFI
interface.
Inner Divertor
--------------
Components
continue to arrive and be checked. The
vendors for the
backing- and C-plates continue to make progress. Pictures of
tile fitups on one of the
plates can be found at
http://www.psfc.mit.edu/cmod/operations/EngImages/MACHINE/Divertor/Apr12_09.jpg
The
fish scale design of the tiles can be seen as well as the ribs
machined
into the plate to restrain tile motion.
Power Systems
-------------
All
work on the commutation capacitor banks has been completed,
including
calibration of the Rogowski coils.
Travel and Visits
-----------------
Les
Gereg and Joe Frangipani from PPPL visited this week to help with
the
fitup of antenna components and the installation of the rf
feedthroughs.
Pat
Diamond visited Thursday and Friday and gave two informal talks and
the
PSFC seminar. He talked with several
C-Mod physicists.
Martin Greenwald travelled to Lausanne Switzerland
to participate
in the international database meeting held April 2-5. He took
the opportunity to meet with Jo
Lister, Basil Duval, Richard Pitts
and Yves Martin to discuss plans for
joint experiments with the TCV
group.
Last Friday, 4/6, Amanda
Hubbard gave the Plasma Physics Colloquium at
Columbia University, NYC, entitled "Edge transport barrier
and
fluctuations in Alcator C-Mod".
John Rice was at the Univ. of Wisconsin on Monday, Apr. 9,
and gave
a seminar on the latest C-Mod results.
Rejean Boivin
was at GA this week and gave a talk on neutrals.
Paul Bonoli
participated in the NTCC PAC meeting.