From:
wolfe@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
May
21, 2001
Plasma operation resumed at Alcator C-Mod this week. Run days
were scheduled
Tuesday and Wednesday for the purpose of full operations
systems testing and
commencement of plasma conditioning. These runs were
completed successfully,
with short plasma shots being produced each day.
The facility was then
returned to standby status for the remainder of the
week, to permit work on
auxiliary systems, particularly the RF, DNB, and
diagnostics, to proceed.
Work also continued on the lower hybrid and
divertor upgrade projects.
Operations
----------
The
Electron Cyclotron Discharge Cleaning (ECDC) conditioning campaign begun
the
previous week continued through the weekend, with the vessel held at
60C.
On Monday the magnet systems were cooled down to -125C in preparation for
operation.
Also on Monday, the alternator, which provides 13.8KV power for the
experiment,
was run up to full speed for the first time this year.
On Tuesday
all magnet power systems were tested under PLC control. All systems
performed
nominally, except for a spurious fault indication in one of the OH2
supplies
which was traced to a defective solid-state relay, which was
replaced. The
power testing took most of the day. The final shot was a plasma
attempt,
which was successful in producing a short (170msec) 500kA plasma at
our
standard field of 5.3 tesla. The discharge was quite resistive and
dominated
by wall-influx and impurities, as is typical for first operation
following a
major vent. Several weeks of tokamak operation and continued
ECDC are normally
required to produce high-quality discharges for physics
studies.
Following overnight ECDC, we began operation on Wednesday
with a repeat of the
plasma shot from Tuesday, with quite similar results.
The next three plasma
attempts resulted in fizzles. This behavior is also
typical of initial plasma
operation, as each full plasma evolves dirt from
the walls which must be
cleaned away before another successful current
rise can be produced. During
this sequence it was noted that the
resistance of the coaxial joint connection
to the OH2L coil was increasing
from a fraction of a uOhm to the 2uOhm
level. We have observed this
behavior, attributed to reseating of the joint
connection, at the start of
all recent campaigns; after additional machine
cycles and thermal cycling
the resistance returns to its nominal value. A
check of the resistance on
Thursday morning indicated it was indeed back below
1 uOhm. The last part of the run day Tuesday was
devoted to a series of
beam-into-gas shots, with 5 tesla toroidal fields,
in support of testing and
calibration of the diagnostic neutral beam
diagnostics.
Plasma operation will resume next week, with the
primary goal of machine
clean-up and conditioning. Additional diagnostic
systems will also be brought
back on-line during this period.
ICRF
Systems
----------
Work continued this week to bring the ICRF
system back online after the
shutdown. XMTR 1 and 2 (D and E antennas)
were successfully tested in vacuum.
Their instrumentation is fully
functional and tested. These systems were
vacuum conditioned up to 30 kV
each. Further conditioning is still required.
XMTR 3 and 4 are ready for
operation (J antenna,4 strap). The
additional
instrumentation for J-port, which includes additional
directional couplers,
voltage probes, B dot probes and faster phase
measurements, is being brought
online and calibrated. Upon completion of
the instrumentation checkout, the
J-port system will be ready for vacuum
conditioning as well.
The J-Port MKS pressure gauge operated
properly during plasma discharges with
a very low noise level. This gauge will be used to monitor the
pressure
behind the J-Port antenna.
DNB Diagnostics
---------------
Beam
conditioning continued this week. Early
in the week, a low
voltage control system power supply was repaired: Its overvoltage
protection latched up
during a HV supply crowbar. Some time
was lost
due to problems with a CAMAC digitizer: The software driver was
modified and
caused a digitizer malfunction.
On
the beam into gas shots, some BES data was acquired. First data was
acquired with the h-alpha duct monitors. An MSE calibration was also
attempted. Although some signal was observed, the MSE
S/N was not adequate
for the gas pressures available, which were limited
by concerns regarding DNB
duct damage.
The calibrations were deferred until later in the campaign.
By
noon on Friday, the beam had operated to 49 kV and 5 A.
Power
Systems
--------------
Additional capacitors have been received
and are being stored in the power
room.
This gives us a total of four spare capacitors for the commutation
banks.
Testing
and conditioning of the reworked commutation capacitor banks was
completed
during the power systems tests on Tuesday. The new cabling
connections
show little or no movement as viewed from the monitoring camera
during
operations.
A calibration error on the recently installed 4160v
experimental power camac
signal was traced to the tolerance value of the
voltage divider resistors,
which are now being replaced. Work continues on
calibration checks of the 4160
three phase current signals.
Lower
Hybrid MIE Project
--------------------
Design activities for
the Lower Hybrid waveguide layout are proceeding. Design
of all printed circuit boards for the transmitter
equipment rack and coupler
protection system was completed. These will be sent out to multiple PC
board
manufacturers for quotation.
Brackets for mounting the current transformers
on the klystron
carts were redesigned for additional high-voltage clearance.
Fabrication
of these brackets is proceeding. One of
the klystron cart current
transformers came supplied with a steel
insert. This insert was determined
to
be unacceptable due to sharp edges which would cause field
enhancement. The
modification or
redesign of these inserts is being evaluated.
Modification
and installation of new sub-chassis on the transmitter
equipment racks is
underway.
Measurements are being carried out
on the vector monitor attentuation and
phase characteristics, using
locally-developed software to set the monitor and
a network analyzer for
the measurements. Work continued on the arc detector
system.
A
LH project design review with PPPL is scheduled for next week.
Inner
Divertor Project
-----------------------
135 more tiles arrived
from the vendor this week, and passed fit-up and gage
tests. We now have
1157 tiles in-house. Aluminum prototypes of the probe box
tiles were made
for fit-up testing. Molybdenum pins for the probe assembly
were fabricated
and fit-up successfully. Machining of the Rear Girdle Plates
is
proceeding. Machining of the upper section of the C-plates is also
proceeding;
some re-work is required in order to bring the transition portion
of the
C-plates into compliance with the spec, which is necessary to insure
good
thermal contact with the inner wall.
We are proceeding to build a
Mock-up of the New Inner Divertor. This will
require welding long studs,
and studs-on-studs on the new Inner Vessel Wall
simulation. The goal is to
use the same equipment/fixtures that will be used
to install real
parts. We are also simulating in-vessel
space constraints
while doing this work.
Then all hardware will be mounted on the wall to check
the
fit. The technicians will develop the
final assembly procedures based on
their experience with the
mock-up.
Finite Element Analysis was carried out to evaluate the
proposed modification
to one C-plate (at F-port) to accommodate the probe
box insertion. Removal of
material from the lower portion of the plate was
deemed acceptable, because
that region will still be relatively thick. The
top section of the C-plate is
sloped, and thinner than the bottom section.
The FEA shows that removal of
material in the vicinity of the probe box
did not have much effect on the
stresses, which are highest in the ears of
the Rear Girdle plate. However,
because the model did not include all the
fine detail of the drilled holes,
counter-bores, etc., a design
modification to further reduce the amount of
material removed from the
C-plate is being considered.
Visitors and Travel
-------------------
Ed Cecil
from the Colorado School of Mines visited the PSFC on Monday and
Tuesday
(May 13 and 14) as part of an ongoing collaboration with Rejean Boivin
and
Earl Marmar directed at the possible installation of a "Faraday
foil"-based
lost ion diagnostic on Alcator C-Mod sometime during the coming
year. As
part of this visit he presented a summary of results from comparable
instruments
on JET and NSTX. In addition he examined data from a Faraday foil
device
which had been installed outside of Alcator last year as a measure of
the
response of this type of detector to soft x-rays and as a measure of the
electro-mechanical
noise which might be expected for a device on the machine
interior. By
subtracting signals from adjacent foils, a noise level of a few
nA/cm2 was
found. By comparison, a worst case scenario in which all the fast
ions
during 3He ICRH minority heating were lost during a typical slowing down
time
of ~100 ms would result in a current of ~40microamps/cm2. The fact that
this projected current is
well in excess of the few nA/cm2 noise measured
outside the machine
suggests the viability of the proposed diagnostic.
Evaluations taking into
account more realistic lost ion fractions are ongoing.
Joydeep Ghosh
from the University of Maryland arrived last week for an
extended stay, as
part of the on-going U. Md collaboration on C-Mod.
Miklos Porkolab
attended the FESAC meeting in Germantown, MD, on May 15,16.
During the
Public Comment session he gave a brief presentation on the
status of
graduate students at the PSFC. He emphasized the healthy status
of
graduate student enrollment at MIT, and the strong job market for recent
Ph.D's
graduating in plasma and fusion sciences.
Spencer Pitcher was also
at the FESAC meeting. He discussed his "open letter to
FESAC"
advocating a burning plasma tokamak experiment, during the public
comment
session.
Jim Terry, Brian LaBombard, John Rice, Martin Greenwald,
Catherine Fiore,
Jerry Hughes, and Valerie Censabella attended the 14th
Transport Task Force
(TTF) meeting in Fairbanks, Alaska, May 16-19.
LaBombard, Greenwald and Terry
also participated in a Meeting on Plasma
Turbulence and Transport in Edge/SOL
regions, also held in Fairbanks on
May 14-15, prior to the TTF meeting.
Larry Guttadora (PPPL)was at IF
Engineering in Dudley, Massachusetts, on 5/8
for acceptance tests of part
of the PPPL upgrade to the C-Mod reflectometer.
The remaining rf parts
will be brought from MIT to PPPL for integrated system
tests prior to
installation on C-Mod.