From: wolfe@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT

            Alcator C-Mod Weekly Highlights
                  May 28, 2001

Plasma operations continued on Alcator C-Mod last week. Two run days were
scheduled and completed, with the primary focus being machine clean-up and
conditioning in preparation for physics operation. A total of 20 plasma shots
were produced, most lasting over 1 second; startup reliability was nearly 75%,
which is very high for this early in the campaign.

Operation will continue this week.

Physics
-------

Reflectometry study shows the quasi-coherent (QC) mode associated with EDA
H-modes is usually localized near the center of the density pedestal. The
radial width of the mode is estimated to be in the range of 0.1 cm < W < 0.3
cm, where W is the full-width at the half mode magnitude. W is weakly
dependent on the electron temperature; generally, the higher the temperature,
the narrower the width. The width inferred from the reflectometer is similar
to that observed by a Langmuir probe in several ohmic EDA discharges
(A. Hubbard, et al, Phys. of Plasmas, 8(5), 2033(2001)).  Study of the
reflectometry data also found that the saturated mode level in steady EDA
periods scales with the parameter (\nu^*q_{95}^2)^0.56. This result suggests
that the higher \nu^* and higher q_95, the higher transport effect the QC mode
may have.

Operations
----------

Following the successful plasma startups obtained during the previous week,
ECDC was continued over the weekend and during the first three days of last
week. Plasma runs were scheduled for Thursday and Friday, with the main goals
being to begin the clean-up and conditioning process. Additional goals
included beam-into-gas tests, with toroidal field, for the DNB diagnostics,
and diagnostic checkout. Excellent progress was made in all areas. By Friday,
full length plasma discharges were being routinely produced with currents up
to 800kA. In addition to beam-into-gas shots on Thursday, the DNB was
successfully fired into plasma discharges.  Signal to noise of the MSE system
was good, with signals seen on all channels.  The RF group brought the D- and
E-port antennas up to 1MW reliably delivered into plasma, achieving this
result ahead of schedule.

The H/D ratio was very high (>2), so there was very little chance of seeing
any heating from the RF.  Most of the fueling was from the wall rather than
the D2 puff.  The new Penning gauges are working and some tests of the
divertor BC gauge with the BC flapper in operation were made.  Preliminary
results from these tests indicate rather low gas flow through the flapper.
The rotation measurements were brought back online on Friday.  Some oxygen was
seen by the McPherson UV spectrometer during the rf pulses, but no carbon.

Next week's runs will be aimed at continued machine clean-up, reducing the H/D
ratio, and continued conditioning of the ICRF systems, as well as continuing
the DNB development work and bringing additional diagnostic systems online.

ICRF System
-----------

ICRF system checkout, calibration and vacuum conditioning of the ICRF
antennas continued this week.  All antennas have been tested and are
at various stages in conditioning.  D and E have been conditioned to
~40 kV while J-port has been conditioned to ~25 kV (35 kV will be
sufficient to begin plasma operation).  The progress on J-port antenna
is somewhat slower because there were additional diagnostics to
check out.  The tuning calibration was completed on D and E-port and both
antennas were operated into plasma on Friday, for the first time in
this campaign. Both antennas are performing well, with over 1MW total
power coupled, although the high hydrogen fraction in these targets is
unsuitable for minority heating. At this stage, the main focus is on
conditioning the antennas at high power, and reducing the gas influx
coming from the antenna during operation.


Diagnostic Neutral Beam System
------------------------------

The DNB continued to operate this week.  The main goal was to acquire data for
beam into a gas filled tokamak.  This goal was primarily for MSE calibration
and for assessment of beam excitation.  The beam was fired into plasma for the
first time during this run period.  BES and MSE data were acquired.

Lower Hybrid MIE Project
------------------------

All PC Boards for the transmitter control and protection system, except
optical interface, were ordered.  Bids were solicited from PC board
manufacturers, and a vendor was selected and the purchase requisition
released.  A comprehensive parts list for electronics parts needed to populate
the Lower Hybrid transmitter and coupler PC boards was compiled.  The parts
list was sent out for quotation.  Purchase requisitions were prepared and
released based on price, minimum quantities and lead time.  On Thursday, a
joint internal design workshop was conducted with PPPL.

Inner Divertor Project
-----------------------

All 1300 tiles have been received, checked, and are now in-house; 1000 of
these have been baked and cleaned. All of the tiles screws have been silver
plated, and the plating quality is excellent. All screws have been baked,
cleaned, and stored in the clean room.

Machining of ribs on the Upper Section of the Rear Girdle plates is
proceeding. Ribs on the main body of the two steel plates and 12 Inconel
plates are complete. Delivery of these plates is now projected for the end of
June.

Visitors and Travel
-------------------

Many collaborators from PPPL were at MIT this week to work on LH, RF,
modelling, and diagnostic projects.  Martha Redi (PPPL) came 5/21-22 and
continued her transport modeling, working with Catherine Fiore, Steve Wolfe
and Paul Bonoli on the ohmic H-mode and off axis RF heating TRANSP runs and
EFITs needed for the GS2 analysis.  Stewart Zweben worked on his gas puff
imaging diagnostic 5/21-24 and participated in planning and discussions for a
new high-speed "movie" camera to capture motion of edge turbulence structures.
Chris Brunkhorst was at MIT 5/21-22 to help with the ICRF transmitters. Larry
Guttadora came 5/22-23 to determine layout and cable lengths for the
additional two channels that form the first part of the C-Mod reflectometer
upgrade; relevant rf components were returned to PPPL for hookup to the
remaining circuit elements and for overall system checkout prior to
reinstallation on C-Mod.  Gerrit Kramer came 5/23-25 for the continuation of
the MSE diagnostic startup and calibration in conjunction with startup of the
diagnostic neutral beam.  Stefano Bernabei, Doug Loesser, Joe Rushinsky, and
Randy Wilson came for a status discussion of the Lower Hybrid project on 5/24.
Gerd Schilling helped with all the above at MIT 5/21-24.

While Martin Greenwald was in Fairbanks, AK, attending the TTF workshop and
the associated meeting on edge transport and turbulence, he also discussed
plans for future collaborations with (among other people) Carlos Hidalgo -
density limit studies on JET, Barrett Rogers and Klaus Halatschek - edge
profile simulations, Xue-Qiao Xu - simulations of the quasi-coherent mode,
Gary Staebler - simulations of spontaneous rotation, Bill Dorland -
calculations of edge micro-stability, Bill Nevins - simulation analysis tools
for the fusion collaboratory.