From: wolfe@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT

            Alcator C-Mod Weekly Highlights
                  June 25, 2001

Plasma operations continued at Alcator C-Mod last week. Four run days were
scheduled and 3 1/2 were completed. Run time was devoted to ICRF conditioning,
cross-calibration of diagnostics, density limit studies, and imaging of edge
turbulence. A recurrence of the arcing in the phase shifter for ICRF
transmitter #4 resulted in the loss of a half day.

Plasma operations are scheduled to continue this week.

Physics and Operations
----------------------

A half-day run was devoted to study of the density limit. The goal was to
collect data on the changes in turbulence and transport which have been linked
to the density limit.  In the previous experiments it was observed that the
regime of large coherent fluctuations which normally exists in the far
scrape-off, moves inward to the separatrix and intrudes into the closed field
line regions as the density limit is reached. In this experiment, we inserted
the probe more deeply into these plasmas at high densities in order to follow
the evolution of the profiles and fluctuations, to assess how far into the
main plasma this phenomenon reaches.  With the probe inserted about 50 msec
before the density-limit disruption, we observed a break in profiles,
turbulence and autocorrelation function about 1cm inside the LCFS. The
temperature profile was seen to shrink from the plasma edge as the limit was
approached even with Prad << Pinput.  Several shots were identified for
further analysis.

A half-day was dedicated to a cross-calibration of the Thomson scattering
density response based on cut-off of the ECE signal in high density, reduced
field discharges. Corrected calibration factors were obtained, and are being
applied.

Two experiments involving the fast CCD cameras were carried out in the
half-run on Friday. The original camera was used in conjunction with the fast
scanning probes to study edge turbulence (MP#281). On the same shots, the new
million frame/sec PSI camera was used to image the ablation cloud from lithium
pellets.

ICRF Systems
------------

The J-port antenna was tested into vacuum and plasma after repair of the phase
shifter.  It was vacuum conditioned to 32 kV and then was operated into
plasma.  J-port reached 2.5 MW without significant RF-plasma edge interaction
at the antenna corners.  However, some interaction was observed on a couple of
discharges on the K-side of the septum at the midplane.  Comparing the faults
with the optical monitor, we conclude that the system reliability was limited
by arcs in the transmission line, at the phase shifter, Into plasmas, the
voltage reached ~22-24 kV during H-mode which is ~50% higher than during the
last campaign.  Given the continuing problems with the phase shifter, we have
removed the teflon support from the phase shifter (arcing is going across the
teflon surface). Repair of the phase shifter controller was completed on
Saturday. The phase-shifter will be tested during vacuum conditioning on
Monday, and is expected to be available for plasma operation on Tuesday.

E-port was operated upto 1.5 MW into plasmas quite reliably.  D-port
however was less reliable.  It was tested into vacuum and arcing was
detected at relatively low voltage.  It is awaiting inspection and repair.

Diagnostic Neutral Beam Systems
-------------------------------

The DNB did not operate into plasma this week.  A failure in the arc supply
was traced to overheating of a supply.  Repair consisted of replacing a failed
fan and replacing the air filters.  Following repair of the arc, a second
problem appeared with the HV timing.  The testing that we were able to do each
day before the runs, between shots, and on the bench eliminated a number of
possibilities for the problem.  The timing of the suppressor is now working
normally.  Trouble shooting of the HV controls continues. 

BES filter functions as a function of filter rotation angle were completed and
included in the computational model for the BES signal.

Inner Divertor Fabrication Project
----------------------------------

Parts continued to arrive for the new Probe Box assembly. Mock-up building is
moving forward, and a new Stainless Steel Wall was installed. Stud welding
procedures for shooting long studs and welding studs-on-studs were developed
and documented; testing indicates that 5,000 Lbs tensile strength can be
obtained consistently.

The vendor has finalized the manufacturing process for the Rear Girdle plate
and is proceeding with production. Our other vendor has completed all twelve
inconel C-plates; final inspection, including 100% dimensional check is
proceeding.

Lower Hybrid MIE Project
------------------------

The modifications and wiring for the klystron carts are basically complete.
Some additional modifications may be necessary later to facility the
circulator mounting.  Work continues on the equipment rack wiring and PC board
assembly.

Travel and Visitors
-------------------

Stewart Zwebwen (PPPL) spent the week at C-Mod. He brought and helped set up
the Princeton Scientific Instruments PSI-3 million frame/sec camera, got new
Gas Puff Imaging data during the density limit experiment, and worked on data
analysis. He also served as co-session leader for Friday's experiment on edge
turbulence imaging.

Gerd Schilling (PPPL)  was at MIT 6/19-22, working on ICRF antenna conditioning
and
attempting to help with the diagnostic neutral beam (which was down this week
with an electrical problem).

Yi-Jung Yang, one of this years' recipients of the National Undergraduate
Fellowship in Plasma Physics, began her summer internship at C-Mod this
week. She will be here for a total of nine weeks, and will be working with
Brian LaBombard and Sanjay Gangadhara on plume image analysis.

J. Snipes, I. Hutchinson, D. Mossessian, C. S. Pitcher, and J. Rice attended
the EPS meeting in Madeira, Portugal from 18 - 22 June 2001. Four papers on
C-Mod results were presented.