From:
wolfe@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator C-Mod
Weekly Highlights
July
16, 2001
Plasma operations continued at Alcator C-Mod last week. Three
run days were
scheduled and completed. A total of 27 plasmas were
produced, with a startup
reliability of about 85%. The primary focus of the week's operation
was
recovery from the previous week's vent, and reconditioning of the
ICRF
antennas.
Physics operation is scheduled to continue this
week.
Operations
----------
Following the
up-to-helium "clean vent" on Friday, July 6, the vessel was
pumped
down and a 120C bake was begun. On
Sunday morning a low current, low
voltage, glow discharge was started in
helium at approximately 25 mTorr.
On
Monday the glow current was increased to 3000 mA at about 300
volts at 10
mTorr. The bake was
dropped to 60C on Monday afternoon.
These conditions
were continued until Tuesday morning when the glow
was stopped for several
hours for antenna conditioning. The glow was resumed overnight at 3500
mA,
270 V, and about 12 mTorr. The
glow was stopped early Wednesday morning and
the vessel temp was dropped
back to 35C and cooldown of the magnets to
operating temp was begun. ECDC
in D2 at 2e-4 Torr was run for about 1 hour
before beginning plasma
operation on Wednesday.
The glow cleaning regimen described above
differs from our usual post-vent
cleanup procedure, which has emphasized
baking and ECDC in deuterium. The
high
quality plasmas produced during recovery shots on Wednesday and Thursday
indicate
that the helium glow, combined with a sustained high temperture bake,
is a
highly effective technique. Good plasmas were readily obtained, and the
initial
H/D ratios were only about 0.3, compared to H/D>1 observed following
our
previous vent. Plasma operations on Wednesday and Thursday were limited
as
the engineering staff investigated and remedied a noise problem which
caused
TF crowbars following several successful shots. However, after only
a
relatively few conditioning discharges the H/D ratio had dropped to the
10-20%
range, adequate to carry out a boronization on Thursday
night.
The vessel was boronized with about 2000 Angstroms of boron,
followed by 2
hours of ECDC in helium at 5e-5 Torr, and 1 hour of ECDC in
D2 at 2e-4 Torr.
Machine operation continued on Friday, with H/D ratios at
the beginning of the
day below the 5% level. The main emphasis of this run
was reconditioning of
the ICRF antennas. Both E-port (80MHz) and J-port
(70MHz) antennas were
brought up to the 1MW level; this is actually the
first time that the J-port
antenna has been operated into plasma at 70MHz
in its four-strap
configuration. The D-port antenna experienced repetitive
fault indications
that may have been due to a faulty demodulator circuit
in the
instrumentation. ICRF conditioning should be completed early this
week,
followed by physics operation.
Physics
-------
This
week we obtained first "movie" images of edge turbulence with the
Gas
Puff Imaging diagnostic using the Princeton Scientific Instruments
PSI-3
camera viewing parallel to B.
This camera can capture 12 frames at up to 1
million frames per
second. Nice images of the motion of
edge turbulence in
the radial vs poloidal plane were taken at 100,000
frames per second and
above.
Diagnostic Neutral Beam
Systems
-------------------------------
The beam was operated
at full voltage and current through the week with no
significant
problems. The sharing of arc current
among the four filaments
(which form one electrode for the plasma arc) was
checked. Arc current is
equally
shared to within trimming adjustments that can be made via filament
current
(same as filament temperature) adjustment.
We further conclude that
it would be useful to measure this sharing
on every shot. We experimented
with
an operating mode in which the arc is run for longer times for
conditioning
while we are also generating beams.
This resulted in the beam
not firing into C-Mod on a couple of
shots and will therefore not be used
again. Arc conditioning will continue before and after regular
operation.
This week we expect to increase the length of time that the arc
can be turned
on during arc conditoning beyond the present 300 ms. An experimental plan for
MSE calibration
was developed and we await the opportunity to do the
calibration which
will also further our understanding of reionization. CXRS
measurements continue to progress with observation of
small signals. BES is
able to
observe fluctuations in ambient D-alpha emission. Data was taken with
beam and will be analyzed and tested for
the effects of parasitic
fluctuations.
ICRF Systems
------------
We
completed the reconfiguration of the coax transmission line and tuning
the
FMIT#3 and #4 to 70 MHz. Before
tuning FMIT#3, we had to repair a broken
mechanical switchgear. The current transmitter tune is not
ideal. The match
between driver
and final is not fully optimized, but should be adequate at the
power
levels required for near-term experiments.
The arc detection system
testing was completed and initial antenna
conditioning was completed for the
J-port antenna at 70 MHz. The decoupling is not as complete as it was
for the
78 MHz configuration; however, it did not limit the operation of
the antenna
into plasma. Antenna
matching calibration factors were obtained in the
initial operation and
about 1 MW was injected into L-mode plasmas
successfully.
The D
and E-port antennas were operated successfully after the up-to-helium.
D-port
was fairly unreliable and a malfunctioning fault detector was found and
thought
to be the cause. The module has now
been replaced in preparation for
this week's runs.
Lower Hybrid
MIE Project
------------------------
Work continued on the
ladder-logic PLC program. A new design has been
developed for the coolant
pump controller interface. This design
has
significant improvements over the initial preliminary design which
eliminate a
PLC, I/O rack, and dedicated optical interface circuit. These changes reduce
the project costs by
over $10,000. Circuit design and PC
board layout for the
Lower Hybrid Timing was completed. This board will provide properly
synchronized
6 and 48 kHz clocks for the LH control and data acquisition
system.
Inner
Divertor Fabrication Project
----------------------------------
An
independent CMM check on one of the C-Plates confirmed the vendor's data
that
all 89 critical dimensions were within the required dimensional
tolerance.
Work on the probe box parts is 90% complete. A design modification
is being
carried out to add new probes for the bottom portion of the C-Plate
and
modify 2 probes at the top in order to remove less material from the
C-Plates. Mock-up building is moving forward. Material (0.020" thick SS
strips)
for "lining" under the BP coils has arrived, and we will complete
the
strips and install them on the mockup wall this week. Manufacture of the Rear
Girdle Plates
has resumed, following a vendor vacation.
There are two more
operations: Milling the bottom of the plates and
wire EDM of the inside radius
removal of the corners. Completion of these milling operations is
promised
for this week.
Travel and Visitors
--------------------
Thawatchai
Onjun, a graduate student from Lehigh University, is visiting the
C-Mod
group for two weeks. He has been
looking at experimental edge pedestal
data, and is comparing this with his
model.
Gerrit Kramer was at MIT 7/9-11, working on the MSE
diagnostic. Stewart
Zweben brought
up the fast camera 7/11 and stayed through 7/13, installing the
camera and
obtaining the new images mentioned above.
Gerd Schilling was at
MIT for the week, mostly helping the with
diagnostic neutral beam
conditioning.
Earl Marmar was at U. of
Wisconsin, Madison, on Tuesday and Wednesday last
week for a meeting of
the Next Step Options Program Advisory Committee.