From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
August
10, 2001
Alcator C-Mod is now up-to-air, and invessel
inspections, documentation,
and calibrations have begun. Following the run on Friday, August 3rd,
the
LN2 cooling system for the machine was shut down and secured. Two
days of helium glow discharge
cleaning were run over the weekend to reduce
heavy boron compounds to safe
levels. The vessel was brought
up-to-air
on Monday, and manned entry began on Wednesday.
Operations
----------
Preparations
for the machine inspection began Monday as the process of
removing
equipment and diagnostics from around the machine was begun.
Work was
concentrated on the top of the machine, so that we can begin
removal of
the igloo blocks, and the east side of the cell where LH
site
modifications will take place.
Invessel work began with careful
documentation of the vessel with both digital
pictures and video
tape. The calibrations of several
diagnostic systems were
completed by Friday. Following more measurements and documentation next week,
removal
of invessel components will begin in preparation for installation
of the
new inner divertor.
Physics
-------
Robert
Granetz, Bruce Lipschultz, and Bill Rowan presented some of the DNB
CXRS
measurements from the recent run campaign at this week's Physics
Meeting. Spectral lines from hydrogen-like species of
helium, boron, and
carbon have been observed. Background line emission
from recombination and
excitation dominates the emission from beam charge
exchange, which makes it
very difficult to extract spatially-resolved ion
temperature and velocity
profiles.
The strongest CXRS signals came from the B+4 7->6 transition
(494.5
nm), which shows a doubling of intensity when the DNB turns on.
This
particular line appears to have significant Zeeman broadening, and
detailed
spectral analysis is in progress.
Experiments were performed with a
two-coil fast magnetic scanning probe at
A-side to measure the poloidal
phase difference of the two coils during the
Quasi-Coherent Mode (QCM) in
EDA H-mode. The magnetic probe shows
that
QCM ktheta varies from at most 2 cm^-1 to 1.1 cm^-1, typically about 1.4
cm^-1
measured 10 cm above the outboard midplane. Radial decay magnetic
measurements of
kr agree reasonably well with direct ktheta measurements from
the double
magnetic probe so that kr ~ ktheta. PCI
kr measured simultaneously
was typically 5 cm^-1. Much of this discrepancy can be explained by
flux
expansion in the divertor and by the angle that PCI makes with
respect to
the field lines.
Sometimes ktheta varies early in EDA H-mode, sometimes
remains
constant. Small ELMs on top of EDA have
a broadband spectrum that
interrupts the QCM.
Lower Hybrid MIE Project
------------------------
Work
has begun on installing and configuring the modules needed for the link
to
the PLC controlling the Klystron High Voltage Power Supply. Some
components of the PLC software
have been completed and downloaded to the
controller.
Work
continues on installation of TPS components.
The SFOL transmitter
prototype pc board will be sent out to the manufacturer
on Monday. The receiver board will lag by about 2
weeks.
ICRF Systems
------------
Work
continues on upgrades to the ICRF control system. PC boards for the
new demodulator scaling and phase
detection circuits have arrived and have
been populated with parts. Some testing has started. Verification of the
"as built"
drawings of the current control system is underway.
Inner
Divertor
--------------
Work resumed on stud welding tests this
week. The stud-on-stud welding
required
at some inner wall locations is working well with full strength
welds
being obtained routinely. All fixturing
for the Rear Girdle plates
has been completed by our vendor. We hope to have these final girdle
components
in house by early September. Work also
continues on the new
magnetics and divertor probes that will be installed
with the divertor.
DNB
---
Some disassembly of
the beam was completed to facilitate the main
C-Mod disassembly. The invessel portion of the BES and
CXRS
calibrations, backlighting, and documentation were completed. This work
included absolute intensity
calibration of the optical systems at the
principal wavelengths used for
measurements and backlighting for
measurement of the plasma volume that
was viewed. The beam duct
monitors
were calibrated. The remaining
calibration work consists of
transfer fiber transmission measurements and
spectrometer instrument
function measurements which will be completed next
week.
Travel and Visits
-----------------
Doug
Loesser from PPPL visited on Wednesday to discuss the action
items
generated by the Lower Hybrid Final Design Review held July 31
at
PPPL. All seventeen items were gone
over in detail and PPPL and MIT
responsibilities were defined.
Martha
Redi visited CMOD at MIT this week, 8/6/01-8/10/01, to work on
gyrokinetic
simulations of off-axis RF heated experiments and have
collaborative
discussions with MIT scientists Catherine Fiore and
Paul Bonoli.