From:
wolfe@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
August
27, 2001
The Maintenance, Upgrade and Inspection period continued at
Alcator C-Mod last
week. Partial
disassembly of the machine is proceeding, and preparation for
the planned
upgrade installations is progressing on schedule.
Operations
----------
The
cryostat has been disassembled and moved away from the machine. The
machine connections, cooling tubes,
and electrical insulation are in very
good condition. The status of these systems has been
documented, and we
are continuing with disassembly. A view of the machine can be found at
http://www.psfc.mit.edu/cmod/operations/EngImages/Inspection_2001-2002/Disassembl
y_Assembly/P0001863.JPG
The
k-port horizontal flange is being prepared for removal in this picture.
The
in-vessel railing to support divertor modification activities has been
installed,
and inner divertor work is proceeding. The LED in-vessel lighting
system
has been installed and is operational. Additional LED spot lights have
been
purchased and installed. New tent racks to facilitate vessel access
are in
place.
The Power Systems Group has completed plans for the
installation of cooling
fans in the TMX supplies, including both the
mechanical and electrical aspects
of the job. The parts and tooling for the job have been ordered. The
construction
of the prototype duct box for cooling of the Interphase
transformers at
the TF supplies is in progress.
The cell is now ready for outside
contractors to begin their work on the
new mezzanine needed to support the
lower hybrid klystons.
Transformers
located on the east wall of the cell have been
relocated on the north side,
freeing up space for the mezzanine. RF transmission lines have also been
moved
out of the way, and diagnostic systems have been removed from the cell.
ICRF
Systems
------------
All three ICRF antennas and their
associated vacuum feed thrus have been
removed from the machine. This includes the Faraday screens from D and
E-port
antennas that have not been removed in over 5 years. To summarize the
observations from the
inspection thus far, the feedthrus for J and D-port
antennas are in
excellent condition. Two of E-port's
feedthrus will require
some work to repair arc damage on the vacuum
side. There is evidence of
arcing
between the D and E-port antenna straps and their respective Faraday
screen. The BN tile fasteners show some damage from excessive
heat. The
J-port Faraday screen is
in good condition, and the straps have arc damage at
the ground
bridge. As on D and E, the J-port BN
fasteners show damage
associated with overheating.
Diagnostic
Neutral Beam Systems
--------------------------------
The DNB
duct was completely detached from C-Mod to make way for
continued
disassembly of C-Mod. The duct was
removed, inspected and
stored.
The in-vessel MSE optics were detached from the F-port
flange to
allow removal of the flange. These optics
were also
detached from the in-vessel supports in preparation for removal
from
the vacuum vessel along with F-port early next week.
Lower
Hybrid MIE Project
------------------------
The concrete pad to
support the HVPS has been poured.
Several meetings
between contractors, and MIT and C-Mod personnel
were held throughout the
week to make sure the pad will conform to
spec.
One of the new CPCI data acquisition crates has been installed
in the Lower
Hybrid control room for use during power supply and active
controller testing
and eventually for data acquisition in that area.
Inner
Divertor
--------------
The vendor continues to make good
progress on the remaining girdle
plates.
We continue to make fitups and test new diagnostics that will
be installed
in and behind the divertor.
Removal of the old inner divertor
modules is 95% complete. The survey of the
inner wall has been completed.
Preliminary installation trials with the stud
welding fixture are
complete.
Visitors and Travel
-------------------
David
Mikkelsen (PPPL) visited MIT and ran EFIT, with help from Steve
Wolfe. He
has now demonstrated that the 'q' and magnetic shear at the
mid-radius of
C-Mod plasmas are not strongly constrained by the available data
(including
the sawtooth inversion radius at a/3). He also discussed with Earl
Marmar
the prospects for improving the constraints on q and shear, using the
Lithium
pellet ablation cloud internal magnetic field measurements, which
could
make possible more definitive predictions of turbulent transport.
Rex
Gandy from University of Idaho visited PSFC from Monday, August 20 to
Tuesday,
August 21. He and Yongkyoon In
discussed the electron temperature
fluctuations using radiometry.