From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Organization: MIT
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
October
05, 2001
The inspection of Alcator C-Mod continues. The Lower Hybrid High Voltage
Power
Supply has been delivered to MIT and work continues on ICRF systems.
Inspection
----------
Both
upper OH coaxes have been removed from the machine after careful
measurements
of the torque settings of all six bolts securing each coax
in place. Analysis of this data is proceeding. The condition of the
feltmetal used in
the coax connections is in an as installed
condition. A small number of silver plated TF joint
fingers show a
frosted appearance that we are investigating. These surfaces had a
polished
appearance before the last assembly.
The frosting indicates
some wear of the plated surface. We will continue disassembly
next week
to reach the lower horizontal arm connections to the TF core and
the OH2L
coax. Disassembly will be complete at
this point.
Lower Hybrid MIE Project
------------------------
The
Lower Hybrid High Voltage Power Supply arrived at the shipping company
yard
on Wednesday morning. Hans Kalt, an
engineer working for the supply
vendor
, Monty Grimes, and Dave Terry went there to inspect the shipment,
supervise
the unloading and reloading of the containers on the
trucks, and supervise
the uncrating of the transformers and switchgear.
The power supply arrived
at MIT on Friday. The switchgear and transformers
were the first to be
setup. The lower container was set in place next and
finally the upper
container. The outside stairway to the
upper container was
also installed.
Wiring of the components inside the containers will begin
next
week. Pictures showing the switchgear
enclosure and the high voltage
transformers after they were craned into
position can be found at
http://www.psfc.mit.edu/cmod/operations/EngImages/RF/lower_hybrid/P0002154.JPG
Pictures
of the upper enclosure being lowered into position and the final
assembly
with the stairway can be found at
http://www.psfc.mit.edu/cmod/operations/EngImages/RF/lower_hybrid/P0002167.JPG
and
http://www.psfc.mit.edu/cmod/operations/EngImages/RF/lower_hybrid/P0002172.JPG
Installation
of cable trays, interface boxes, and water cooling piping
for the lower
hybrid project continued this week.
Wiring on the transmitter
equipment racks is proceeding. A wiring
harness to
test the control system with the carts is being
fabricated. Tests of the TPS
RF
boards were begun. Assembly of the HV
Junction Box Optical Interface and
Relay Driver Boards was
completed.
A temporary breaker control panel for the HVPS tests has
been fabricated.
A conduit has been run from the HV control panel in the
power room into the
LH development lab to allow power supply tests to be
conducted from there.
The control cable has arrived and we will pull and
connect it early next week.
Error checking and handling programs for
the active controllers are being
developed.
C-Mod engineers met
with contractors working on the Lower Hybrid water system.
Much progress
was made finalizing the transmitter water manifold interface.
ICRF
Systems
------------
We continue development of the new phase
detector boards. A choice between
a
down-conversion technique and application of an extremely fast XOR chip
will
be made in the next few days. Work also
continues on models of the
antennas, transmission system, and
cavities.
Inner Divertor
--------------
The
invessel fitup of the new inner divertor has been completed successfully.
All
measurements have been made needed to complete final machining of the
components
and to have the inner surfaces silver plated to enhance thermal
contact to
the inner wall. All components have
been delivered to the
vendors and are all expected back by the end of the
month. Work at
MIT will now
concentrate on the installation of the studs.
Before being
shipped out, the inner divertor was assembled in our
machine shop as one
last assembly test.
A picture of the assembly may be seen at
http://www.psfc.mit.edu/cmod/operations/EngImages/MACHINE/Divertor/P0002145.jpg
Mike
Demaria on the left, our design engineer, and Jim Zaks, divertor project
lead
engineer, are shown standing over the divertor. Measurements indicated
a variation in the inner ring
diameter of less than 0.005", well within
the tolerance required to
maintain efficient heat conduction into the inner
wall.
Diagnostics
-----------
We
are considering modifications of the CXRS views to emphasize more
accessible
and possibly more interesting regions near the plasma periphery.
We
continued to identify improved spectrometers (for higher throughput) and
detectors
(for sensitivity and readout speed) for CXRS, and to optimize the use
of
one or two spectrometer/detector instruments to record spectral
information
from a number of plasma regions. The
BES team continued with
redesign of the BES/MSE optics including optical
simulations and significant
mechanical changes for the internal optics to
simplify installation and
improve measurement
At PPPL, work
continued on extending the reflectometer wave propagation
calculations to
include the effect of poloidal field shear.
DNB
---
We
continue to evaluate the RFX beam and its effects on beam related
diagnostics. A first meeting was held this week at MIT to
discuss site
preparations for the beam.
An extensive email dialog is ongoing between
C-Mod and the INP team
in Novosibirsk. A new engineer will
begin work on
the beam project next week (UTexas employee to be stationed
full time at
MIT).
Trips and Visits
----------------
On
Tuesday, Hans Kalt, an engineer working for the vendor providing the LH
High
Voltage Power Supply, arrived to
prepare for the power supply
installation. He will be here until the end of the month supervising
installation
of the supply.