From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
October
19, 2001
All lower TF arms have been removed from the machine
and are being
carefully inspected.
Work continued on the Lower Hybrid Project, with
a large amount of
activity focused on the HVPS installation.
We also
continue to work on the ICRF systems and prepare for the
new DNB.
Physics
-------
The addition of a taper
to the waveguide transition pieces has improved the
Gaussian beam pattern
significantly in the ECE radiometer at
F-port. This change allowed for the shift of the Gaussian beam waist
from
R=0.9 m (near separatrix) to R=0.75 m (r/a=0.3) with smaller poloidal
width
(~8 mm). With these improvements, the cross power correlation studies
of
electron temperature fluctuations have made progress. At r/a=0.7, a pair
of channels showed coherent thermal
fluctuations in the frequency range of
550 - 680 kHz, which started to
appear within 2 % error and became
conspicuous at 1.5 % error (increased
number of shots in the average).
The data were numerically simulated (Te
fluctuation = 1 % of the standard
deviation of random background noise)
successfully. However, the cross
phase
information in the coherent region obtained from the experiments may
not be
reliable yet in that there were non-random cross phases even in
non-coherent
frequency ranges.
A great deal of work is now
going into preparations for the APS meeting.
Dry runs of the oral talks
and poster sessions which began on Thursday of
this week will continue
until mid next week.
Inspection
----------
All
lower TF horizontal arms have been removed from the machine and access
has
been gained to the OH2 lower coax. A
detailed inspection of the TF
arm and core fingers will begin next
week. We expect to remove the OH2
lower
coax next week at which point the disassembly of Alcator C-Mod
will
be complete.
Lower Hybrid MIE Project
------------------------
We
continue to install lights, receptacles, switchgear, panels, and blowers
in
the HVPS. Outside conduit runs for 208
volt AC service to the HVPS are
complete and wiring is pulled and
terminated. Fiber optic cables between
the
HVPS and power room are pulled and ready for termination on
Monday. Control
cables between the
HVPS and power room are pulled and terminated at the power
supply and
junction box ends. The ground to the HV
Junction Box in the power
room is being run. Work has started on mounting the snubber and electronics
in
HV Distribution box in the power room.
Wiring of the transmitter
control and protection cabinets is
progressing with the first cabinet
complete, and the second one started.
Wiring of the transmitter test setup
was completed this week. A
systems
test of the control, protection, and supply control circuits will
begin
soon. Drawings for the water
system instrumentation interfaces are complete
as are the design and PCB
layout of the pump controller optical interface
boards.
Brackets
and panels for the LH Low Power Microwave Rack booster amplifiers
have
been fabricated.
The date for circulator design review to be held at
the vendor's location
in Backnang, Germany has been set for December 3 and
4.
Contractors continue work on the klystron water cooling system
and the cell
mezzanine.
ICRF Systems
------------
Work
continued on the phase demodulator system.
Selection of the proper
local oscillator to use is underway. Drawings are being developed for the
new
layout of the rf racks in the cell and power room. Development of a
transmission line model using simulation
results from the antenna code
continues.
Design of new boron nitride tiles for the J-Port antenna is
well
underway. The changes to the tiles will
reduce plasma interaction with
the plasma facing surfaces.
DNB
---
Dexter
Beals (UT-FRC) is now permanently on-site at the PSFC as DNB Engineer.
The
requirements for the Padova beam are being compared to the present DNB
resources
to determine the extent of required changes, and the equipment that
can be
recycled into a new system. Thus far,
it is evident that we can
recycle vacuum equipment, PLCs, and some beam
diagnostics. New support
systems
will be required to provide liquid helium for the cryopumps
and SF6
handling and recovery for the step-up transformer.
Diagnostics
-----------
Joe
Snipes presented a proposal for a new magnetic probe array at the weekly
Physics
Meeting. It would consist of a closely
spaced (4 mm) array of five
poloidal magnetic field pick-up coils to be
mounted on the inner wall at the
midplane to measure the quasi-coherent
mode (QCM). The array would
measure
the mode amplitude and k_theta at the inner wall for comparison
with
similar outboard measurements to determine if the QCM has a strong ballooning
character
or not, and to verify the expected strong dependence of k_theta on
poloidal
position.
Visitors
--------
Richardo Maqueda,
our LANL collaborator, was on-site all this week
to help with data
analysis of divertor surface temperatures from the long
pulse discharges,
and to ship the IR camera back to LANL.