From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups:
sci.physics.plasma
Organization: MIT
Alcator C-Mod Weekly
Highlights
December
28, 2001
Over
the last week we have made progress on the inspection, the Lower Hybrid
MIE
Project, the new inner divertor, and ICRF systems.
Inspection
----------
Measurements
and tests of the OH2 Lower coax continued this week. These
last measurements were required so that fine
adjustments to the
OH hardware could be made before final assembly. We now expect
reassembly of C-Mod to
begin next week. The support ring for
the TF
spring plate hydraulic insertion tool is nearly ready to be
tested.
A procedure for testing the tool is being developed.
Operations
----------
We
continue to work on the new TF and thermocouple scanners. Work
continues on improvements to the
MOV protection system for the magnet
power supply bus. New boots that seal the cryostat to the
machine are being
fabricated in preparation for reassembly. New milling equipment needed to
modify
the cylinder arrived this week. Our
vendor is making progress
on the modifications to the cryostat.
Lower Hybrid MIE Project
------------------------
Cable
routing between the equipment racks, the carts, and other Lower Hybrid
components
is proceeding. Wiring between the water
instrumentation and the
junction boxes is also being installed. We have finished wiring the second
transmitter
control and protection cabinet. The
water hoses needed to
connect the klystrons to the water system are now
in-house. These hoses
are also
needed to perform some initial tests on the water system.
The pump
controller for the cooling system is being installed. The 480 VAC
connection
to the pumps and breakers is in progress.
The pump
rotation test is scheduled for next Friday. The mechanical drawings of the
master
oscillator distribution chassis and related brackets and supports
have
been completed. A request has been
generated to fabricate these parts.
Work on the phase and amplitude
control system continued.
ICRF Systems
------------
The
PC board for the new demodulator is now in house. Work populating the
first board with components has
begun.
DNB and Related Diagnostics
---------------------------
The
F-port flange design has been approved by all interested parties
with the
stipulation that a small change in the location of one
tangential port is
made to increase the clearance around a flange mounting
bolt. The design for the modification to the
diagnostic stand to
accommodate the Budker DNB was completed. Camac and
PLC rack reconfiguration
and addition of supports for the transformer tank
are underway.
Inner Divertor
--------------
All
halo and eddy current Rogowskis have been tested successfully and
cable
runs for these coils are now in progress.
We will begin torquing
all the divertor plates to spec next
week. This process will take
several
days.