From:
wolfe@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
January
4, 2002
Over the
last week we have continued to make progress on the inspection, the
Lower
Hybrid MIE Project, the new DNB, and the new inner divertor.
Inspection
----------
A
final test assembly of the OH2 Lower coax was made on Friday and left
over
the weekend with pressure indicating film between the terminal
pocket,
feltmetal, and coax. If resistance
measurements and the film
results are positive, we will be ready to begin
C-Mod reassembly early
next week.
Operations
----------
We
continued work on C-Mod Cryo, Heat, TC scanners, and some diagnostic
systems
this week. A vendor for ceramic coating
of components for the
new MHD antennas is being selected. We also continue work on the
wideband
rf amplifier needed to drive the antenna.
Updates to our PLC
engineering drawings continued. Work on the new
TF and thermocouple
scanners continued.
Lower Hybrid MIE Project
------------------------
The
water cooling pumps for the klystrons have been powered up successfully.
Some
debugging of the controller relay box may be required. We continue
work on protection and
control circuitry. The first klystron
cart has
been moved into position on the new mezzanine in the cell.
Each
cart supports four klystrons.
Representatives from the HVPS vendor
will be here next week to help with
commissioning of the power supply. This process is expected to take
several
weeks.
ICRF
Systems
------------
Component procurement has been completed
for the control system upgrade
to the stub tuners and phase shifters. We
are now ready to implement this
new upgrade. A transmitter model including the drivers is nearly
complete.
A plasma model for simulating the loading and coupling
is also being
developed.
DNB and Related Diagnostics
---------------------------
The
support modification design was completed for the Budker beam.
The fueling
system design can now be completed with the recent
responses from Budker
Institute. The control system
implementation
for the beam is underway.
Specifically, PLC software modification,
C-Mod shot synchronization
software, and PC acquisition for local
control are all underway. The primary power transformer has been
installed
and AC power is to be run to it. The
support design for
the pulse transformer are complete and ready for work
to begin.
Inner
Divertor
--------------
We continued to install invessel cable
runs for the new inner divertor
diagnostics. All 240 silver-plated nuts holding the Rear Girdle plates
on
the inner wall studs have been torqued up to 21 ft-lbs. The high-strength
bolts
which hold the C-Plates to the Rear Plates have been hand-tightened, and
will
be torqued up this week.