From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
February
1, 2002
Reassembly continued
on Alcator C-Mod this week. Work on the
LH MIE
Project, preparations for the new RFX beam, and work on ICRF
systems
also continued.
Physics
-------
Data
was presented at the Physics Meeting this week showing the time history
of
the Balmer H-to-D ratio over several C-Mod campaigns. An increase in
this ratio was seen to be well correlated
with installation of boron
nitride tiles on the ICRF antennas. Maintaining a low H-to-D ratio is
important
on C-Mod where ICRF fast wave minority heating is the primary heating
scenario. We are now investigating the best way to
reduce the level of
hydrogen generated by the tiles, so that better
control of this parameter
can be obtained during the next run
campaign.
Operations
----------
All twenty
lower TF arms have now been installed.
Installation of the
springplates using the new hydraulic insertion
tool is expected to begin
next week.
The MIT funded upgrade to the cell air conditioning continued
this
week with installation of the mounting hardware for the new cooling
unit,
and rework of the ventilation system. Work
continued on preparations
for cylinder machining.
Lower Hybrid MIE Project
------------------------
Initial
tests were completed on transmitter #3 protection, control, and
supply
cabinets. The cabinets were installed
in the cell underneath cart #3.
Testing was begun on the protection and
control cabinet for transmitter #2,
and the control and supply cabinets
for transmitter #1. Cart #2 has been
installed in the cell on the upper
mezzanine. Two of the three carts
required
for LH Phase I are now in the cell. Pre-installation testing was completed
on transmitter cart
#3. This cart will be installed in the
cell once all
other equipment racks have completed testing.
The
high-voltage junction box for the HVPS was hi-potted along with the
triaxial
cable and the dummy load. Both the
high-voltage enable and trigger
gates
(fiber-optic to the HVPS) are now operational. Wiring between
transmitter cart #3 and its associated
equipment racks was begun.
PLC Operator console display screens were
designed or modified for,
transmitters #1 and #2, the coolant system, and
the HVPS.
ICRF Systems
------------
We
continued in-house machining of the D and E-Port Faraday screens, and
the
J-Port current straps. Work also
continued on phase detection and
fault electronics.
DNB
and Related Diagnostics
---------------------------
Modifications
to the DNB support stand so that it will interface properly
with the new
RFX beam are nearly complete. The
transformer tank
supports on the upper level stand are complete. The
chamber supports on the
mezzanine level have been installed.
Modifications
to the PLC rack are near completion. Testing of
the control power and
signals began this week. Testing through the PLC
will begin next
week.
The new F-Port flange design has been sent to a vendor for
fabrication.
We expect the Russian team to arrive in Boston on the
17th of February to
begin installation of the RFX beam.
Travel
and Visits
-----------------
Martha Redi was here this week
from PPPL working with Catherine Fiore
on GS2 analysis of dual frequency
ITBs on CMOD.