From: irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject:   Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT


            Alcator C-Mod Weekly Highlights
                  February 15, 2002


We continue reassembly of Alcator C-Mod.  Work also continues on the
new DNB installation and the Lower Hybrid MIE Project.


Physics
-------

The PAC presentations are now on the WEB, with links at:

      http://www.psfc.mit.edu/cmod/sciprogram/Cmod_PAC_2002.html

We report here the completion of level 1 Alcator C-Mod program milestone
75. The  experimental work was completed during the Summer 2001 campaign,
which ended on  August 3, 2001. We have also now completed the required
analysis, and a short report is included here.  The milestone
as extracted from the March 2001 Alcator Project Work Proposal is:

      75.0 Evaluate density control (Target date AUG 2001)
      Evaluate potential methods to control wall-gas inventory and
      target plasma density in anticipation of long pulse operation.
      Wall reservoirs for particles will be characterized and potential
      conditioning techniques and fueling options will be evaluated.

Both active and passive density control options have been evaluated in
detail.  In passive density control, the wall is conditioned such that it
acts as a 'pump' during a discharge.   Thus, it is important to establish
the capacity for the wall to pump and methods to condition the wall between
discharges. In active density control,  a cryopump or other activated surface
(e.g., getter) is employed. In order for these systems to work they must have
both sufficient pumping speed and capacity to handle the gas-load during a
discharge. The gas load is set by the plasma/neutral inventory in the chamber
and the capacity of the wall to hold neutral gas (since it may evolve
from the wall during a discharge).

A) Wall Condition and Wall Pumping Capacity Experiments:
Wall condition and wall pumping capacity experiments were performed to assess
helium glow discharge cleaning as a technique to condition the walls for passive
density control (MP273, "Effects of Glow Discharge Cleaning on Boronization
and Wall Conditions"). Helium glow discharge cleaning was performed over a
weekend and between discharges for 1/2 hour intervals. If was found that even
with the most extensive use of helium glow, the wall could only be depleted
by about 30 torr-liters of deuterium gas. A single shot
following helium glow was sufficient to reload the wall. Thus, the idea of
conditioning the wall for pumping in C-Mod is not a viable option. Similar
conclusions were drawn from experiments that assessed the rate of change-over
from deuterium -> hydrogen -> deuterium (MP274,"D/H Changeover").

B) Active Pumping Options:
We have found that the only pumping techniques that have sufficient pumping
speed and capacity for C-Mod are cryo-panels and liquid lithium surfaces.

B.1) Liquid Lithium Surfaces:
On Tuesday April 3, 2001, a 1-day meeting was held to discuss ideas for
using liquid surfaces for pumping hydrogen in Alcator C-Mod. The participants
included: Mike Ulrickson (SNLA), Dennis Whyte (UCSD), Dick Majeski (PPPL),
Jeff Brooks (ANL). It was concluded that liquid lithium surfaces may provide
a large pumping speed and capacity. However, the technology is in the
development stage. The risks associated with the use of liquid lithium
in C-Mod were found to be unacceptable at the present time.

B.2) Cryopump:
A prototype cryopump has been successfully operated in C-Mod, yielding ~1000
liters/second pumping speed for a 1/10 size test unit. This technology is
well established and utilized in many tokamak experiments. It is desirable
to increase the surface area of the cryopump and to simplify its design.
Towards this end, we have investigated the possibility of locating a full
toroidal loop cryopump in the upper divertor region. Recent analysis of
unbalanced double-null experiments shows that the pressures in the upper
divertor can be sufficiently high to enable a pump to be operated there.
Follow-up experiments are planned during the 2002 run campaign to scope the
neutral pressures in the upper divertor for a range of upper x-point locations.

B.3) Long Pulse Experiments:
We have operated C-Mod with pulse lengths extended to 3.4 seconds, in part to
assess gas evolution from the walls (results presented at APS, Long Beach,
2001, www.psfc.mit.edu/cmod/sciprogram/Aps/Aps2001/Wolfe_poster.pdf).
It was found that the wall maintained a moderate level of pumping throughout
the 3 second pulse. Target densities did not exceed the programmed densities.
However, owing to volt-second limitations, these long-pulse discharges were
performed at low to medium densities. Wall saturation & degassing effects,
if they are to be seen at all, might occur in higher density and higher power
discharges. In any case, from the wall capacity experiments as
described above, we have a good estimate on the maximum wall inventory that
could be degassed during a discharge, ~ 30 torr-liters. On this basis, we have
the information we  need to start a conceptual design for a full-scale
cryopump in C-Mod.


Operations and Power Systems
----------------------------

Reassembly of Alcator C-Mod continued this week with the installation of
nearly all the lower TF springplates.  Following completion of the
springplate installation, we expect the machine to be craned back into
position on the lower dome mid next week.  Extensive measurements of the
TF joint resistances must also be made before the machine is moved.
A picture of the machine in the Southeast corner of the cell can be found
at:

http://www.psfc.mit.edu/cmod/operations/EngImages/Inspection_2001-2002/Disassembly_Assembly/Machine_assembly_A/DCP_0143.JPG

Machining of the cylinder to provide better tangential access for
diagnostics began this week.  Estimates of time-to-completion for this
process are being made.

A careful inspection of the Alcator C-Mod TF magnet, OH coax,
and most other machine components was carried out between Aug
2001 and Jan 2002.  The TF magnet horizontal arms and vertical legs
were found to be in excellent condition.  After the TF fault in 1998,
changes to the springplates and springplate pressure, plating of the
sliding joint surfaces, and the addition of a graphite coating
to the feltmetal, have resulted in very much improved performance
of the TF magnet.  Several feltmetal pad locations
indicated that more graphite would be useful, and we are therefore
increasing the coating thickness at all joint locations during
reassembly.  These locations showed a somewhat frosted appearance
indicating more interaction with the opposing TF finger than expected.

Inspection of the OH coax connections indicated a reduction in the
preload on several of the bolts; by in one case as much as 33%.
Damage to the bolt threads was also found as well as to the helicoil
inserts into which they engage.  After re-analysis and simulation
of the coax foot behaviour, and extensive testing and measurements
of the coax components, several changes were made to the
coax connection.  High strength bolts are now being used and
the engagement of the bolts with the inserts was increased up to a
factor of two.  The Belleville stacks that maintain the preload have
been changed to provide more compliance, and wedges have been added
to restrain movement of the top of the coax foot.  These changes will
improve the reliability of these crucial components.

More generally, heater and thermocouple leads, TF instrumentation
cabling, LN2 cooling lines, and bus components are all being
refurbished as part of the the inspection/reassembly effort.

       
Lower Hybrid MIE Project
------------------------

PPPL continues to direct fabrication by outside vendors of LHCD launcher
components.  Shop visits are being made as needed to resolve issues or
check status.  A second three-waveguide launcher prototype has been
fabricated, and an integrated splitter-coupler system test is being
assembled.  This test will check out the E-taper, 3 dB divider,
H-taper, phase compensation, reflected power probes, possible RF
leakage from the bolted plates, and performance of the gold seal at
the coupler nose under vacuum.  The same setup will be used to test a
preliminary design of the reflected power water load presently under
construction.  The setup will then be tested at high power at MIT.

All twelve klystrons needed for Phase 1 of the LH MIE Project are now
installed in the Cell.  A photo of one of the carts installed in the
cell can be found at:

http://www.psfc.mit.edu/cmod/operations/EngImages/RF/lower_hybrid/DCP_0142.JPG

Wiring continues for the transmitters in the Cell. Transmitter #3 wiring
is approximately 75% complete.  HVPS commissioning continues.
A full voltage (50kV) pulse lasting nearly 5 seconds was applied
to the dummy load.  Preparations are underway for the HVPS wire tests.
A Ross relay is being prepared to short the supply with a short piece of
small diameter wire.  This process will, among other things, test the fault
protection of the supply.  Design of the input RF switch assembly was
completed this week. The parts to assemble this switch assembly were ordered.
Cabling for the transmitter fiber-optic connections was ordered.

ICRF Systems
------------

Machining of the D and E-Port Faraday shields continued this week, and is
nearing completion.  Work on the J-Port antenna current straps also continued.

 
DNB and Related Diagnostics
---------------------------

The RFX beam components (29 crates of equipment) were received this week and
were stored in anticipation of arrival of the installation and commissioning
team from Novosibirsk.  Visa problems have delayed their arrival by a few days
from the original date of February 17.  Testing of PLC software for
the vacuum system continued.  Output signals from the PLC were tested.
Progress was made on the fueling system hardware.  Matt Sampsell of UT-FRC
visited for several days to work on mirror calibration for the toroidal CXRS.


Travel and Visits
-----------------

Cynthia Phillips attended the ITPA meeting in Naka, Japan, February
6-8. At the meeting, she presented results from the C-Mod 2-frequency
ITB experiments and plans for the LHCD program.

Miklos Porkolab was in San Diego this week where he served on the Program
Advisory Committee for the Virtual Technology Lab.