From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Organization: MIT
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
February
22, 2002
Alcator C-Mod was moved from the assembly area to the
center of the
Cell this week. Work
also continues on the new DNB installation, ICRF
systems, and the Lower
Hybrid MIE Project.
Physics
-------
At the
Physics meeting, Catherine Fiore presented preliminary calculations of
the
electrostatic potential and radial electric fields in CMOD ITB shots,
generated
by the input of central toroidal rotation measurements into TRANSP.
The
highest value of the resulting EXB shearing rate peaked at 8e4/s in the
ITB
region after the ITB was fully developed.
Further work is needed to
compare this result with the ITG growth
rates.
Joe Snipes presented a preview of the talk he will give at
the ITPA Confinement
and Threshold Database meeting in Princeton 11 - 14
March on the Latest H-mode
Threshold Results and Future Plans. The talk covered the inner gap scan
experiments
that were presented by C. S. Pitcher at the APS meeting in Long
Beach. There does not appear to be an increase in
threshold down to a 3 mm
inner gap within the measurement errors. Closing the gap still further to
produce
inner wall limited plasmas, however, increased the threshold
dramatically
to the point where 2.7 MW of launched ICRF power was
insufficient to get
into H-mode. More experiments on this
topic are planned
during the next run campaign when more ICRF power will
be available.
Operations
and Power Systems
----------------------------
All lower TF
springplates were installed and carefully documented for proper
operation
this week. TF joint resistances were
measured and turn-to-turn
hi-pots were conducted. All measurements indicated successful
completion of
the lower TF arm installation, and the machine was moved
from the assembly
stand to the lower dome at the center of the Cell on
Friday. A picture of
the "big
lift" can be found at
http://www.psfc.mit.edu/cmod/operations/EngImages/Inspection_2001-2002/Disassembly_Assembly/Machine_assembly_A/DCP_0196.JPG
We
continued maintenance work on the alternator this week in preparation for
the
next run campaign. Cooling water pumps
are being refurbished as is the
varistor bank that protects the rotor from
over-voltage.
Lower Hybrid MIE Project
------------------------
We
have stopped the commissioning activity on the HVPS until several issues
with
the control system can be addressed by the vendor. We expect to resume
the commissioning process late March to
early April. Though the supply
has
reached current, voltage, and pulse length specifications, the control
system
as it currently programmed will not allow safe operation of the
supply with
our klystrons. We
continued installing the cabling between the klystron
carts and the
various control and protection cabinets this week. Waveguide
is being prepared for installation on the
klystrons.
ICRF
Systems
------------
Chris Brunkhorst (PPPL) visited this week
to participate in
commissioning of FMIT#3 and #4 in preparation for the
upcoming campaign.
Transmitter and screen crowbars were tested. FMIT#3 was successfully tested
to 1.8
MW into a dummy load. FMIT#4 was
limited by a low power problem that
will be addressed next week.
DNB and Related Diagnostics
---------------------------
The
first contingent of Russian engineers from the Budker Institute arrived
this
week to begin assembling the diagnostic neutral beam, which has been
loaned
to us by Consortium RFX in Italy. Over
the next four weeks, a total
of eleven Russian scientists and engineers
will assemble, install, and
commission the DNB. Completion is scheduled for 24 March, in time for the
beginning
of tokamak conditioning operations.
The new spectrometer for the
CXRS is being ordered this week. A
design
review for the new high-resolution edge CXRS in-vessel optical
system was
held this week. No
significant problems were found, and final drawings for
construction will
be ready next week.
Russel Feder, PPPL, continued to work on the new ferrules and ferrule
holder for
the MSE/BES Image Dissector with Ron Bravenec, U. of Texas, and
Howard
Yuh, MIT. The ferrules for MSE have
been merged into larger
rectangular ferrules, and the new design should be
generally easier
to work with.
Other Diagnostics
-----------------
Work
at PPPL continued on the 130/140 GHz TFTR reflectometer upgrade
for C-Mod.
Power supplies have been built and tested.
During microwave
circuitry checkout two of the Gunn oscillators
were found not to be
in proper working condition, and have been returned
to the
manufacturer for further testing.
Travel and
Visits
-----------------
Martha Redi, PPPL, was here this week,
doing further exploration of the
stability of dual frequency heated ITBs
on CMOD.
David Mikkelsen gathered information relevant to
transport
simulations at MIT February 18-22, and began to use the MIT
Beowulf
cluster. He also spoke with Joe Snipes about the possibility of
using
PPPL codes to analyze Alcator C-Mod plasmas with locked modes.
Miklos
Porkolab gave a talk at the AAAS meeting in Boston last Sunday,
Feb. 17,
as part of a panel discussion on the future of Nuclear Energy
entitled
"Recent Progress in Fusion Research and Future Prospects."
The
lecture was well attended and covered by the news media.