From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
March
1, 2002
We continued invessel work on the new inner divertor
this week. Machining
of the
cylinder continued. Work on the new DNB
installation and Lower Hybrid
MIE Project showed good progress.
Operations
----------
Two
of the three port modifications to the retaining cylinder have been
completed. These changes will allow better tangential
access to the
plasma. The OH2U and
OH1 coaxes were installed this week.
Resistance,
hi-pot, and ring tests were all to specification. Following first-to-last
turn hi-pots
early next week, we will begin installation of the wedge
plate and
remaining TF horizontal arms and vertical legs.
Lower Hybrid
MIE Project
------------------------
The last equipment rack
has been installed in the Cell (control & protection
cabinet for
transmitter #1). Wiring of transmitter
#3 is nearly complete,
and we have begun wiring transmitter #2. We have also begun populating the
regulator
and filter board for the input RF switch and solid-state preamp.
We have
begun work on the output waveguide assembly.
Testing of the
prototype Lower Hybrid waveguide has started at PPPL.
PPPL is requesting a
Fin Plan change to allow a more timely procurement of
remaining
long-lead-time components this fiscal year.
The PPPL LH
engineering group is preparing the background and
paperwork for
these procurements.
ICRF Systems
------------
We
have checked crowbars and protection circuits, tuned, and brought up both
transmitter
#3 and #4 to approximately 1.8 MW into a dummy load. We are
now working to bring up #1 and #2. This work is in preparation for the
Spring
run campaign. We continued to procure
the parts needed for
approximately 50 new demodulator boards.
Inner
Divertor
--------------
All inner divertor tiles have been
installed and we are in the process of
doing final torque checks. Spot welding of the tile keeper
hardware,
scheduled to be done next week, will complete installation of
the
inner divertor.
DNB and Related Diagnostics
---------------------------
A
great deal of progress was made on the new DNB installation this week
with
an enormous amount of work provided by nine engineers from the
Budker
Institute. The vacuum
chamber was assembled and leak checked successfully.
The chamber was then
moved onto its supports on the cell diagnostics stand.
A picture of the
vacuum chamber installation in the C-Mod Cell can
be found at
http://www.psfc.mit.edu/cmod/operations/EngImages/Inspection_2001-2002/Disassembly_Assembly/Machine_assembly_A/DCP_0230.JPG
Four
power electronics racks were installed in the cell at floor level, and
three
more racks are ready to be installed.
The transformer tank is leak
tested and filled with SF6.
Ron
Bravenec, U Texas, was at C-Mod to set up the CAMAC crate for the DNB
(with
guidance from Don Patterson at Texas).
It will be tested once it can
be hooked up to a data highway. He also consulted with Rui Vieira and
Dexter
Beals about the schedule of the F-Port flange (currently being welded
and
expected to be finished next week), and prepared a schedule for UT-FRC's
diagnostics
work and installations at F-Port. He
also discussed hardware
issues with Howard Yuh and Russ Feder (of PPPL)
concerning the MSE/BES
optics system.
Travel and
Visits
-----------------
Miklos Porkolab attended the FESAC
meeting on Feb. 27,28. Dmitri
Mossessian
was at GA for the ITPA Pedestal meeting last week. Bruce Lipschultz was
also at GA, for an
edge/divertor ITPA meeting.