From: irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT


            Alcator C-Mod Weekly Highlights
                  March 1, 2002


Work continued on reassembly of Alcator this week.  The installation of the
inner divertor, milestone 78,  was completed.  Work also continued on
ICRF, DNB, and Lower Hybrid MIE Project systems.


Physics
-------

Dmitri Mossessian  made a presentation at the ITPA pedestal group meeting at
GA, February 26 - 28, on "Recent results of pedestal studies at
Alcator C-Mod".  He showed scaling studies of pedestal parameters with
plasma parameters, talked about the operational region of EDA H-mode, and the
conditions for obtaining small ELMs on C-Mod. He also presented the results
of ideal MHD stability analysis for both EDA and ELMing discharges and
showed that the small ELMs can be associated with medium n coupled
peeling/ballooning modes that are  unstable in the pedestal region.

David Mikkelsen, PPPL,  visited GA this week to gain experience with the GYRO
turbulence  simulation code and the vuGYRO analysis tool. These codes will
be applied to simulations of transport in C-Mod plasmas.

The Alcator C-Mod FY2004 work proposal has been submitted to DoE OFES.
It can be found online at

www.psfc.mit.edu/people/censabella/C_Mod_Work_Proposal.pdf


Inner Divertor
--------------

Milestone 78 was completed on Friday, March 8th.  This milestone
states that:

  All components of the inner wall modifications will be installed
  and made ready for operation.  These modifications will strengthen
  the inner divertor and wall, allowing for operation at higher plasma
  currents, while simultaneously increasing plasma shaping flexibility
  for our standard lower single-null divertor configurations.

All twenty interlocking inner wall girdle plates have been installed along
with the over 1000 moly tiles, tile support plates, and tile keeper
hardware.  The number of inner wall studs was tripled to better hold these
new components.  New eddy and halo Rogowski coils, thermocouples, and
retro-reflectors have also been installed behind the divertor.
Simulations indicate that not only will the new divertor easily survive high
current, high field disruptions, but it will also add strength to the inner
wall and provide a substantial increase in the heat load capacity of the
inner divertor during long pulse AT discharges. A picture of the
completed inner divertor installation can be seen at

http://www.psfc.mit.edu/cmod/operations/EngImages/Inspection_2001-2002/Disassembly_Assembly/Machine_assembly_A/DCP_0254.JPG


Operations
----------

The last port on the cylinder needing modification will be completed
by Tuesday of next week.   Final cleanup and testing will then be done,
followed by installation of the cylinder on the machine.  The upper wedge
plate was installed and carefully aligned this week, and the installation of
the top TF arms was begun.  Each arm goes through a process of cleaning,
hi-potting, and coating of the feltmetal with graphite before installation.


Lower Hybrid MIE Project
------------------------

Fiber-optic cables from the transmitter to the pump controller and HV junction
box are installed and ready for termination.  Wiring on the TPS systems
continues.  The electrical panel for the transmitter racks is installed.
More components were machined for the LH low power microwave rack, including
the master oscillator chassis.

PPPL continued to focus on launcher prototype testing and the
preparation of drawing packages and specifications for early procurement
of long-lead components.


ICRF Systems
------------

We have checked crowbars and protection circuits, tuned, and brought up both
transmitter #1 and #2 to approximately 1.8 MW into a dummy load.  We have
also run the #1 and 2 transmitters at 200 kW into a dummy load with a 4 second
pulse length.  With this test we have begun to qualify the rf system for
long pulse operation. Control, fault, and data system hardware performed
properly on this initial test.

The final version of the new phase demodulator board has been tested and
has now been put into production.  This board uses a programmable
local oscillator and PIC controller to mix signals from 40 to 85 MHz into
a 10 MHz IF band.  Standard operating frequencies can be loaded into and
easily selected from a lookup table.  Besides providing very accurate
measurements of signal phase and amplitude, over a broad power input range,
the board also generates fault signals to protect the transmitters.  The
response time of the fault circuitry is approximately 1 us.  A picture of
the board can be found at

http://www.psfc.mit.edu/cmod/operations/EngImages/Inspection_2001-2002/Disassembly_Assembly/Machine_assembly_A/DCP_0257.JPG


DNB and Related Diagnostics
---------------------------

The RFX beam is now installed in the cell along with the new power supplies
and the pulse transformer.  Utilities and control systems are being
hooked up.  Some redesign of the DNB duct was necessitated by last
minute changes in the beam location.  We expect to pump down the beamline
early next week.

Ron Bravenec, UT-FRC, visited MIT to work on noise reduction in the BES data
acquisition electronics and to work on the final design of the
MSE/BES fiber-holder.


Diagnostics:
------------

Perry Phillips, UT-FRC, is currently visiting MIT and will be here through
next week. He met with Josh Stillerman to get the PC data acquisition system
for FRC ECE system up and running. He also met with Robert Childs to work out
any possible conflicts on the modified ECE mirror system on F-port.  He plans
to test fit the ECE mirror to the F-port flange.  Matt Sampsell, UT-FRC, is
visiting MIT this week to repair any damaged  BES optical fibers.


Travel and Visits
-----------------

John Rice and Catherine Fiore were in San Diego last week to participate in
the ITPA ITB/T session, which reviewed ITB results in an attempt to develop
a definition of what an ITB is, and discussed implementation of an ITB
database.