From: irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT


            Alcator C-Mod Weekly Highlights
                  March 15, 2002


Machining of the retaining cylinder was completed this week.  Installation
of the upper TF horizontal arms is also complete.  The new RFX diagnostic
neutral beam is operational.


Physics
-------

Pedestal comparison experiments continued on Thursday and Friday at
ASDEX-Upgrade.  This series of discharges aimed to match the dimensionless
parameters of some 1 MA EDA H-modes on C-Mod; previous experiments were at
lower current.  Despite fairly good matches to the shape and plasma
parameters, the  AUG H-modes were either ELMy or ELM-free.  Detailed analysis
of profiles and fluctuations will be carried out during the upcoming
AUG maintenance period.


Operations
----------

All machining of the retaining cylinder is complete.  It is now
being prepared for installation.  All upper TF horizontal arms have
been installed and the springplates inserted.  Modifications to the
cryostat have been completed by our vendor.  We expect the cryostat to
be back on-site by early next week in time for fitups of the new boots
needed to seal the cryostat to the vessel ports.

Preps to the horizontal vacuum flanges continue as we prepare them
for installation with the new boot configuration.  The new F-Port flange
welding is nearly complete.

The upgrade to the alternator varistor bank has been completed.   

The MIT funded work on the control room is making good progress.  The old
control room wall has been removed, new doors installed, new AC units
hung, and the support hardware for the new ceiling tiles is in place.


Lower Hybrid MIE Project
------------------------

The fabrication of components for the lower hybrid launcher is on schedule.
The vacuum shroud and interface flange have been completed by the vendor
and are being shipped to PPPL.  The 5 final couplers are EDM'd  and ready for
brazing to commence on site pending delivery of the ceramic windows.  Testing
on the prototype waveguide is proceeding;  some adjustment may be necessary
to optimize the splitting configuration.  Drawing packages are continuing to
be collected for RFQ packages in anticipation of accelerated funding.

High voltage wiring and connections to the klystrons has begun and
transmitter control wiring continued.


ICRF Systems
------------

The stub tuner and phase control box fabrication was completed this
week. Work has begun on changes to the PLC software to control these
new systems.  We continued to work on improvements to the rf control
and fault systems.

All machining and polishing operations on the J-Port antenna straps
have been completed and we are preparing to send them out for
re-plating.  We have begun final grinding operations on the D and
E-Port antenna Faraday screens.


DNB and Related Diagnostics
---------------------------

The RFX Beam was operated this week at 50 kV and 4A, with 50 ms pulses.
A very large effort by the Russian visitors, and Texas and MIT personnel
was required to bring on line in such a short time the power, vacuum, and
control systems needed to operate the beam.  The DNB camac crate and highway
have been brought back into operation in preparation for synchronization
tests and for measurement of the component mix next week.

Polishing of the BES fibers was completed this week.  New ferrules for the BES
optical fibers have also been completed.   Ferrules for the MSE fibers are
still being fabricated.


Diagnostics:
------------

The 132 GHz channel of the upgrade to the reflectometer is operational at PPPL,
and bench tests are continuing.  The Gunn diode frequency can be varied between
128 and 136 GHz.  The 140 GHz channel, originally intended to be another
swept channel, has been converted  into a fixed frequency channel until its
Gunn diode can be repaired.

All components are in-house for the MHD antenna and assembly is in
progress.  We continue to develop a prototype amplifier to drive the
antenna.


Travel and Visits
-----------------

Miklos Porkolab, Ian Hutchinson, Earl Marmar, and Ron Parker  attended the
FY2004 Budget Planning Meeting in Gaithersburg, MD, on March 12,13. The
Alcator C-Mod presentation for this meeting may be found at

http://www.psfc.mit.edu/people/censabella/bpm_2002_presentation.pdf

Earl Marmar also attended the FFCC meeting on March 14 at Gaithersburg.

Martin Greenwald travelled to Oberlin College this week to give a talk on
"Turbulence and transport in magnetic confinement experiments" as part of the
APS distinguished lecture program.  Martin also travelled to PPPL to attend
the ITPA meeting on global confinement and modelling.   Plans for migrating
the profile databases to MDSplus were discussed.

Tom Fredian presented MDSplus tutorials at three ITPA workshops held at GA
and PPPL over the last three weeks. The tutorials focused on the MDSplus
remote access to the ITER Profile Database now being stored in MDSplus
format in Culham, England.