From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
March
29, 2002
Assembly of Alcator C-Mod continued this week with
installation of the
TF legs. Work
on the Lower Hybrid MIE Project and RFX DNB continued.
Operations
----------
All
TF vertical legs are now installed. The
TF magnet will be completed
next week as soon as the remaining
springplates are installed. Final
prep
work on the cylinder was completed this week as was a successful
dye
penetrant test of the areas we had machined.
MIT funded
contract work on our control room should be finished next
week. Preparations are being made to bring up
computer, data acquisition,
and control systems as soon as this work in
done. The electrical wiring
for
the new air conditioning units in the C-Mod cell has been completed,
and
water cooling lines are being installed.
Lower Hybrid MIE
Project
------------------------
AC wiring to the equipment
racks was completed this week, and the equipment
rack for Cart #3 was
powered up for the first time. The
fiber-optic cables,
which were recently terminated, were connected at the
HV junction box, the
pump controller, the control computer, and the #3
transmitter Cart.
The PLC rack for Cart #3 was also powered up. Communications were
established
between the control computer and transmitter #3.
The DC supply for
transmitter #3 was turned on and the TPS faults were cleared.
Operation of
the pump enabled fiber optic signal to the pump controller
to be
checked. Fabrication of the fiber
optic interface for transmitter
#3's rack was completed. The RG-220U HV
cable was routed and
terminated between the junction box and cart #3, and
the junction box side
was un-installed to allow HVPS commissioning to
continue.
At PPPL, pins have been added to the prototype LH coupler
to improve the
alignment of the components and reduce reflections. The coupler performance
should now
perform to specification.
ICRF Systems
------------
All
machining and prep work has been completed on the J-Port antenna
straps. They will be copper plated next week. All polishing work has
been completed
on the D and E-Port antenna backplanes which will also
be copper plated next
week. Machining has begun on the new
boron
nitride tiles needed for both antennas.
We continued
testing and calibration of the new phase demodulator
boards. New fault detector PC board prototypes are
in house
and ready to be populated.
DNB and Related
Diagnostics
---------------------------
We continued to operate
the beam throughout the week adding
diagnostics (beam component mix and
pressure measurements), and
continuing the development of the vacuum
system PLC. The beam is
operating
well and comes quickly to full voltage and current after only
a few
shots. We are preparing for the first
regeneration of the cryo
pumps.
Diagnostics
-----------
The
MHD antennas have been re-welded to correct misalignment of support
plates
that occurred during a welding operation by one of our
vendors. Fitups of
both the coils
and the tiles are now acceptable. Work
also continued on the
power supplies and amplifiers required to drive the
antennas.
Work continued this week on new scanners for the TF resistance
and
invessel thermocouple measurements.
Work also continued on the
CXRS telescope and shutter, and the MSE
fibers and optical
components.
Travel and Visits
-----------------
David
Mikkelsen, PPPL, spent the week with the C-Mod group discussing
details
of the experimental measurements, with particular attention to
the
uncertainty in the electron temperature gradient.
Peter Koert spent
the week in Germany reviewing progress on the fast
ferrite tuners and
gathering documentation needed to design the control
circuitry.