From: irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject:  Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT


            Alcator C-Mod Weekly Highlights
                  April 5, 2002


Insertion of the outer TF springplates was begun early this week and will
continue into the weekend.  Work on invessel diagnostics and ICRF hardware
is proceeding.  Preparations are being made to continue the commissioning
of the Lower Hybrid MIE Project high voltage power supply. 


Operations
----------

Assembly of the machine early in the week concentrated on verifying
proper alignment of the vertical legs and wedge plates.  These alignments
must be very carefully done to allow proper installation of the cylinder
and taper pins that fix the cylinder to the wedge plates.  Insertion of the
outer TF springplates is progressing with completion expected over the weekend
or early next week.  Other preparations for installation of the cylinder
continued.  Instrumentation on the machine has been checked out, upper TF
cooling tubes installed, and vessel thermal insulation checked and refurbished.


Lower Hybrid MIE Project
------------------------

Only a few cables remain to be run to complete wiring of the LH
transmitters.  Power-up tests of transmitter #3 continue.  The DC power supply,
the 3-phase AC for the supply cabinet, and the filament supplies to all four
tubes were brought into operation.  The fiber-optic signals to enable and
turn on both water-cooling pumps were tested, as were the vac-ion pump
supplies, and the power to the input RF switch.  The redesign of the
Transmitter Protection System (TPS) optical interface board #2 to include the
DFOL circuit is complete.  The printed circuit board layout is complete, and
the board will be sent out for fabrication next week.  The nitrogen
distribution manifold to pressurize the waveguide is nearing completion.

We expect the HVPS vendor's engineering team to return next week to continue
commissioning and acceptance tests of the supply.  A water cooling heat
exchanger on loan to Alcator from our Fusion Engineering and Technology
Division is being installed on the HVPS dummy load so that 10 second
long pulses can be run at rapid repetition rates.


ICRF Systems
------------

The J-Port antenna straps were sent out to be plated and are now back
in house. One D-Port strap was sent out to be brush plated and is also back
in house and being prepared for baking.  The D and E-Port Faraday screens are
at the brush plating vendor for detail masking and plating and are expected
back in house by early next week.  The BN tiles are being manufactured and
will require a high temperature bake (~1250 C) to reduce the hydrogen
content. The E-Port vacuum feedthroughs are being cleaned in preparation
for installation.  The J-Port flange has also been prepared for installation.

The new support for the D and E-port transmission line has been
partially constructed.  Once finished, a more accurate estimate of the
new transmission line components can be made.


RFX DNB
-------

The  final design of the gas control and water cooling systems was completed
this week.  Upgrades to the beam PLC and Paragon software have been made to
aid regeneration of the cryo panels and indicate water flow status.  The
design of a system to automatically fill the cryopanel reservoir from our
main LN2 tank is being developed.


Diagnostics
-----------

The test assembly of the edge CXRS telescope and shutter went well this week.
Minor changes may be required before installation.  The bake and
assembly of the new inner wall scanning probe were also completed this week,
and the probe is ready for installation.

The MSE invessel optics is nearing completion.  All mirrors and lenses
have been installed into their holders.  The new holder design is expected
to handle disruptions loads very effectively. The assembled lens sets
have also been installed into the invessel canister, and the mirrors are
being aligned.  A throughput test and a good deal of spot welding remains to
be done on the outside of the can.  The invessel can should be ready for
installation at the end of next week.  A new vacuum interface window using
low Verdet glass is being designed; the glass for the window should arrive in
about 2 weeks. All of the approximately 175 of the machine side quartz fibers
have been polished, and the ends mating to the PMTs tested successfully.  The
custom ferrules have arrived from PPPL and a successful fitup was performed.
All MSE channels will be upgraded to 16 fibers looking at the center of the
beam.  The new image dissector, which will help prevent damage to the fibers,
is being made at PPPL and should be completed Monday. A retention mechanism
is still being designed.  In house fabrication of the invessel backlighting
and absolute calibration tool is nearly done.  A new technique being
developed for doing remote backlighting for MSE/BES/CXRS looks promising,
and will be taking advantage of the wireless ethernet system which was recently
installed in the cell.

The new Active MHD antennas at GH port are now completed.  The in-vessel
fitup has been performed.  The tiles will be removed and vacuum baked with the
ICRF boron nitride tiles next week.  The antenna hi-pot was successful.
A picture of the antenna without the tiles, showing the 5 turn coil,
can be found at

http://www.psfc.mit.edu/cmod/operations/EngImages/Inspection_2001-2002/Disassembly_Assembly/Machine_assembly_A/DCP_0370.JPG

A picture of the completed antennas with the BN tiles during the invessel
fitup can be seen at

http://www.psfc.mit.edu/cmod/operations/EngImages/Inspection_2001-2002/Disassembly_Assembly/Machine_assembly_A/DCP_0389.JPG


Travel and Visits
-----------------

Approximately twenty Senior Congressional Staffers were on the MIT campus
attending a three day Seminar on Energy Policy, organized by the Sloan
School.   On Thursday evening they were invited to a reception and tour of
the PSFC.  Miklos Porkolab gave a talk to the staffers on fusion, and
tours of Alcator C-Mod, LDX, VTF, PTF, and the Plasmatron were given.

Martin Greenwald, Ian Hutchinson, Amanda Hubbard, and Valerie Censabella,
attended the TTF meeting in Annapolis this week.  Amanda gave an invited
talk on "LH and Pedestal Transport Physics Issues".  Catherine gave
a talk on "Recent Results of Internal Transport Barrier Studies on Alcator
C-Mod", and Martin presented a talk on C-Mod transport plans.

Martha Redi, David Mikkelsen and Stew Zweben, all of PPPL, also attended the
TTF meeting in Annapolis and presented their work on C-Mod related transport
modeling and edge turbulence studies.

On Tuesday, April 2nd, Amanda Hubbard visited the University of Maryland and
gave a seminar on "Edge Transport Barrier Formation and Scalings on
Alcator C-Mod".

Gerd Schilling, PPPL,  was at MIT 4/1-4/4 for discussions and updates on ICRF
hardware, diagnostics and the machine reassembly schedule.