From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups:
sci.physics.plasma
Organization: MIT
Alcator C-Mod Weekly
Highlights
April
12, 2002
Reassembly of Alcator C-Mod proceeded this week with
installation of the
retaining cylinder and dome. Work continues on Lower Hybrid, ICRF, and
RFX DNB
systems. We continue to refurbish and
test power system components
for the next run period.
Physics
_______
Robert
Granetz presented further analysis on the possibility of obtaining
information
about the internal q-profile from the elongation of x-ray
emissivity
contours. Tomographic reconstructions
were done throughout the
evolution of large sawteeth in highly-peaked ITB
discharges. The
elongation of
emission contours located near the sawtooth inversion radius
consistently
showed a gradual decrease during the sawtooth ramps, implying
a slow
decrease in q by 0.01-0.03, which is quite plausible. However, the
x-ray contours very close to the magnetic axis
did not behave as expected.
Analysis is continuing.
Operations
----------
Installation
of the remaining springplates was completed early this week.
Following
successful hi-pot and resistance checks on the TF magnet, and
a complete
checkout of thermocouples, heaters, and diagnostic instrumentation,
we
installed the retaining cylinder.
Pictures of this operation can be
found at
http://www.psfc.mit.edu/cmod/operations/EngImages/Inspection_2001-2002/Disassembly_Assembly/Machine_assembly_A/DCP_0436.JPG
and
http://www.psfc.mit.edu/cmod/operations/EngImages/Inspection_2001-2002/Disassembly_Assembly/Machine_assembly_A/DCP_0441.JPG
On
Friday we installed the retaining dome, approximately 65,000 lbs of
stainless
steel. A picture of the machine during
this last major machine
component installation can be found at
http://www.psfc.mit.edu/cmod/operations/EngImages/Inspection_2001-2002/Disassembly_Assembly/Machine_assembly_A/DCP_0454.JPG
Installation
of cooling lines and horizontal ports has
begun.
Preparations for operations continued on the
alternator this week with
work on the water cooling systems, while the
inspection of all magnet bus
work was begun in the power room. Some bus work joints near the
transitions
from aluminum to copper bus are being re-plated.
Lower
Hybrid MIE Project
------------------------
At PPPL, Lower
Hybrid launcher drawing packages are being assembled for rear
waveguide
components to be procured. An RFQ will
go out in within two
months. The
remainder of antenna detailing and RFQ packages will be
sent in
August. We are awaiting samples of the
ceramic window billet
to re-measure and verify its electrical properties
prior to final
window machining.
The following LH launcher hardware items have been
delivered to
PPPL: couplers, coupler flanges, vacuum shroud,
interface flange, and flange heaters. The remaining "Phase 1
Components"
have received RFQ responses, and purchase orders have
been awarded.
At
MIT, Wiring of transmitter #3 is now very close to complete. The following
power-up tests of
transmitter #3 were performed this week.
A closed-loop
communication between the operator interface
computer, the HVPS, and the
transmitter
#3 PLC was established. This closed
loop communication
allowed for remote control of the HVPS. An enabling of the HV,
which includes
raising the HV relays on cart #3, raising the HV relay in the
HV junction
box, and enabling the HVPS was performed.
Now that the flow
meters and other water-related instrumentation
are operating on transmitter
#3, testing of the PLC ladder-logic software
was able to proceed. Many of
the
scaling and fault logic routines were updated and pre-tested. Design and
layout of the TPS optical
interface board #2 was completed this week.
The PCB layout was sent out
for bids. The requisition for these
boards will
be placed soon. Parts
to populate this board have been ordered.
Commissioning of the LH
HVPS was stopped late in the week by the vendor when
timing problems
appeared in the new controller software.
Commissioning
is expected to resume again in two to three
weeks.
ICRF Systems
------------
The current
straps for the ICRF antenna have been re-plated with copper
and are
currently being baked. The Faraday
screens are being prepared
for baking early next week. New boron nitride tiles for the antennas
will
also be ready for an extended high temperature bake early next
week.
Work continues on the new diagnostic, fault, and control
system electronics.
Printed circuit boards are being populated, new racks
fabricated, and
power supplies installed.
RFX DNB
-------
To
verify proper operation of the DNB controls, we operated the beam
remotely
this week. With the exception of the
initial power
supply turn-on, the beam was operated from outside the
cell, and the
data describing the beam pulse was also displayed at the
remote site.
The beam was operated from Austin in these tests, though
during
C-Mod operation the beam will be operated from the C-Mod
control
room.
The assembly of F-port was completed this week. The final assembly
consisted of
installing the cleaned and baked components of the ECE
High Resolution
mirror, as well as installation of various periscopes
that are attached
on the radial port. It is ready for
installation
at the first opportunity.
Diagnostics
-----------
The
new low Verdet constant glass (SFL6) windows for the MSE
diagnostic were
received by PPPL from Schott and were forwarded to MIT
for installation
on C-Mod. These components are now at
MIT and the
window port design is being finalized.
Work
continued on the CXRS edge system, MHD antenna components and
power
supplies and amplifiers, and new periscopes.
Horizontal ports
and the components associated with them are being prepared for installation.
Travel
and Visits
-----------------
David Mikkelsen, PPPL, gave an
invited talk on his transport simulations of
C-Mod plasmas at the IAEA
Technical Meeting on Theory of Plasma
Instabilities at Kloster Seeon,
April 10-12.
Stefano Bernabei and Remi Dumont, PPPL, were at C-Mod
on 4/10 for discussions
on the future Lower Hybrid experiments on C-Mod
and the associated
modeling effort.
They communicated with Paul Bonoli, Amanda Hubbard,
John Liptac,
Ron Parker, Miklos Porkolab, and John Wright.