From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
April
19, 2002
Re-assembly of Alcator C-Mod continued this
week. On Thursday a DoE Quarterly
Review
of the Alcator C-Mod program was held.
We continue to work on
the Lower Hybrid MIE project, ICRF upgrades,
and diagnostic fabrications
and installations.
Physics
_______
The
Alcator C-Mod DoE Quarterly Review was held via remote conferencing on
Thursday,
4/18. The agenda consisted of:
Welcome/Agenda Earl Marmar
Facility and Operations Jim
Irby
DNB and Diagnostics Bob Granetz
Linux
migration Josh Stillerman
ICRF Steve Wukitch
Lower Hybrid MIE Greg
Pitonak, Joel Hosea, Ron Parker
Progress on LHCD
modeling Paul Bonoli
Attending at DoE were Anne Davies,
Rostom Dagazian, TV George, Esther Ku,
Warren Marton, and John
Willis.
Attending at PPPL were Stefano Bernabei, Remi Dumont, Joel
Hosea, Dale Meade,
Greg Pitonak, Gerd Schilling, and Skip Schoen.
Attending
at MIT were Paul Bonoli, Jim Irby, Bob Granetz, Martin Greenwald,
Amanda
Hubbard, Ian Hutchinson, Earl Marmar, Miklos Porkolab,
Bill Rowan (UTexas),
Josh Stillerman, Steve Wolfe, Steve Wukitch,
and Howard Yuh.
Discussion
primarily concentrated on the status of the LH MIE project, and
progress
on machine re-assembly and the return to plasma operations.
Links to
the presentation viewgraphs can be found at
http://www.psfc.mit.edu/cmod/sciprogram/Q_rev_apr02/
Dr.
Marco Valisa, from Consortio RFX, visited this week to discuss
collaboration
plans for the next year. This
collaboration includes the
loan of their diagnostic neutral beam, which is
now operating on Alcator
C-Mod.
RFX spectroscopists are very interested in trying out a new
spectrometer
design with their beam on C-Mod, but they will need some
initial spectra
of a non-intrisic low-Z element, such as neon, fluorine, or
nitrogen, in
order to optimize their instrument for a particular
wavelength. The first multi-week visit of an RFX
physicist will start
after plasma operation begins for the summer
campaign, and the spectrometer
could be here during the latter part of the
summer. We have a number of
fiber
views that we could provide for them to get started.
Dr. H. Kubo of
JT-60U visited the PSFC from April 17th through April
19th. Dr. Kubo is
an experimentalist interested in edge and divertor
physics as well as
impurity spectroscopy. During his visit he had
discussions with many of
the C-Mod staff and presented a lecture
"Atomic and Molecular
Processes for Heat and Particle Control in
Tokamaks"
Operations
----------
Re-assembly
of Alcator C-Mod this week concentrated on installation of the
LN2 cooling
lines, the ef and oh coax extensions, and the horizontal ports.
Installation
of 4 out of 10 horizontal ports has now allowed invessel work
involving
antenna and diagnostic installations to continue. Installation of
the coax
extensions allows preparations to be made for hi-pot and ringing
tests
that will qualify C-Mod assembly at the "tokamak complete"
stage.
Work continued on magnet bus work refurbishment. Also, all upper vertical
flange
surfaces have been polished and the tear-drop adapters installed
in
preparation for installation of the vacuum crosses and tees that provide
interfaces
for instrumentation and diagnostic cabling.
ICRF Systems
------------
The
bake of the J-Port straps was completed early in the week and these
components
are now ready for installation. Prep
work on the D and
E-Port Faraday screens was completed and these
components are now
undergoing a bake.
Installation, followed by a successful leakcheck, of the
J-Port
horizontal flange has prepared the way for invessel antenna assembly.
Boron
nitride tile fabrication in our machine shop is complete and the
tiles are
being prepared for a 1200 C bake. These
tiles, along with the MHD
antenna tiles, will be baked for approximately
48 hours to reduce the level
of trapped hydrogen in the tiles.
RFX DNB
-------
The
beam is now being positioned with respect to the newly installed F-Port
horizontal
flange. Diagnostic components are being
installed on the flange
and components of the DNB beamline are being
attached. Plans are being made
for
installation of an LN2 feedline for the beam cryopanels from our main
tank.
This fill line will also provide service for the planned invessel
cryopump.
Diagnostics
-----------
Now that the
entry way port extension has been installed, we have resumed
invessel
work. The outer divertor is now
re-torqued, the current shunts
resurfaced, the Thomson scattering viewing
dump installed, the new
inner wall scanning probe and associated wall
tiles also installed, and
preparations are being made to install the new
F-Hor periscope, VB
viewing dump, and MSE/BES optics.