From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Organization: MIT
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
May 3, 2002
We are
moving forward with the assembly of Alcator C-Mod and invessel work.
Work
on ICRF, LH MIE, and DNB systems continued.
Physics
_______
J.
Snipes gave a preview, at the C-Mod Weekly Physics meeting, of the talk
he
will present in Garching on May 7 to the W7-AS and ASDEX-Upgrade groups
on EDA
H-mode. It was an overview
of C-Mod results focusing on the Quasi-Coherent
Mode and EDA. The talk is intended to give the W7-AS
scientists an idea of
what we have found experimentally in EDA H-mode to
compare with their own
results on Improved Confinement (IC) mode with
their new divertor
configuration.
Operations
----------
All
horizontal ports are now installed and diagnostics and instrumentation
are
being installed where possible. The rf
feedthroughs for the J-Port
antenna have been installed and are ready to
be leak checked. Installation
of
the antenna will proceed as soon as the feeds are proved to be leaktight.
All
curved bus has been installed on the cylinder and nearly all connections
from
the bus to the ef/oh coax extensions are complete. All cooling lines
have been installed. Following a series of inspections next week,
we will
begin installation of the cryostat.
ICRF Systems
------------
We
continued to test and calibrate new rf instrumentation. All the new
fault detection boards have
been tested. The response time for
these
boards is less than 200 ns.
We continue to build up the instrumentation
racks with the new
diagnostic, control, and fault electronics.
Work on the PLC control of the phaseshifters and stub tuners
continued.
Lower Hybrid MIE Project
------------------------
We
continued work on the TPS Optical Interface boards. Components are being
specified and ordered for the diode
detectors that we have just received from
PPPL.
RFX DNB
-------
A layout
design and a vendor have been chosen for the new LN2 feedline
for the
cell. Work continued on PLC control
software.
Diagnostics
-----------
Work
continued on invessel installations and alignments of MSE, CXRS, fast
imaging
fluctuation telescope, MHD antennas, the bolometer array, Penning
gauges,
and new divertor thermocouples.
At PPPL, modification of the image
bisector for the C-Mod MSE diagnostic
has
been completed by the outside vendor, and the unit is back onsite.
To
allow for the image bisector to be focused, external parts from C-Mod
were
sent back to PPPL for modification as well.
These reworks should
be done by the end of next week.
The fiber optic ferrules are already at
MIT for fiber installation
and polishing. A major goal of these
reworks
was to make the internal optics mounts more robust against
disruption forces.
Travel and Visits
-----------------
Catherine
Fiore made a visit to the University of Iowa to attend the Committee
on
the Status of Women in Physics of the APS meeting (funded by U of Iowa).
David
Mikkelsen, PPPL, spent the week with
the C-Mod group discussing and
evaluating methods of measuring the
electron temperature gradient.