From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
May
10, 2002
The cryostat was installed this week marking a
milestone in the reassembly
of Alcator C-Mod. Work continued on ICRF, LH MIE, DNB, and diagnostic
systems.
Operations
----------
A
successful hi-pot and ring was done this week on all the C-Mod
magnets. This step marks the "tokamak
complete" stage of reassembly.
Earlier in the week, all connections
between the curved bus and the coax
extensions were completed and
inspected. All cooling lines have
been
run from the tokamak to the manifold above the bus tunnel. Following
a last set of inspections,
the lower cryostat was raised, allowing
access to the lower vertical
ports. Installation of
instrumentation
below the machine is now well underway. Later in the week
both the upper
cryostat and the cryostat cover were installed. A picture of the top cover
being
installed can be found at
http://www.psfc.mit.edu/cmod/operations/EngImages/Inspection_2001-2002/Disassembly_Assembly/Machine_assembly_B/DCP_0659.JPG
Three
of the new instrumentation ports can be seen near the middle of the
photo. The boots that will soon seal the cryostat
are also shown surrounding
the horizontal ports.
Following
installation of the rf feedthroughs at D- and E-Hor earlier in the
week,
installation of the ICRF antennas has proceeded quickly with final
assembly
expected by early next week. The BN
tiles have been vacuum
baked at 400C, cooled down, and are ready for
installation. The TORVAC
pumping
station is being brought back online.
CAMAC highways and PLC
communications are being brought back up, as
are the control room workstations.
Seven more Linux workstations were
received early in the week and are now
available for use in the control
room. Work on the magnet bus, TF/TC
scanners,
and ECDC systems also continues in preparation for the next run
campaign.
Lower Hybrid MIE Project
------------------------
Two
engineers from the power supply vendor will return next week to begin
commissioning
of the HVPS. Tests conducted at the
vendor site indicate that
software problems with the control program have
been fixed.
Components needed for the forward and reflected power
measurements have been
selected and are now on order. Work continued on the PLC control
system
timing for the up coming transmitter tests, as well as the low
power realtime
control system.
The PPPL May Fin Plan Letter has
arrived with $300K additional budget
authority for the C-Mod Lower Hybrid
Project. This amount is being
borrowed against planned FY2002
diagnostics, which will be deferred,
and will be returned out of FY2003
LH funds. We now have authority
to
spend that budget and accelerate the final design and FY2003
procurements
for the LH launcher.
ICRF
----
We continue to
build up the new racks and control, fault, and diagnostic
electronics for
the transmitters. Hi-yard work is
ongoing to ready the
transmitter high voltage supplies for operation. New control electronics
for the tuners
and phaseshifters is becoming operational.
RFX DNB
-------
The
DNB racks, control computer, and PLC were repositioned so that
all the DNB
equipment is now in its final position.
PLC control and
monitoring is now being done from the control
room. Equipment is
now being
prepared invessel and on the DNB beam line to align the
beam relative to
the tokamak.
The components needed for the LN2 feedline for the DNB
and cryopump from our
main storage tank have been ordered with delivery
expected in 3 to 4 weeks.
We will continue to operate the beam using LN2
from 500l dewers until the
new line is installed. All gas delivery components are in-house,
and the
beamline duct that connects the beam to Alcator C-Mod is
undergoing leakchecks.
Diagnostics
-----------
Installation
and alignment of CXRS, MSE, and BES invessel
optics has been
completed. Spatial calibration is
partially complete.
All calibrations will be completed next week.
The
MSE diagnostic image dissector has been returned to MIT from PPPL.
This is
a new design that is much more efficient optically and operationally
than
the original image dissector, and is the last of the modified
optical
system components.
The bolometer array at K-Hor was re-installed
this week and will be
calibrated over the next few days.
Travel
and Visits
-----------------
Matt Sampsell, UT-FRC, visited
during the week and assisted
with the invessel installations.
Stew
Zweben, PPPL, worked on the Gas Puff Imaging diagnostic at MIT 5/9-10
and
gave a seminar, "Edge Turbulence Imaging In Alcator C-Mod and
NSTX,"
on 5/10.