From: irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject:  Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT


            Alcator C-Mod Weekly Highlights
                  May 17, 2002


Effort focused this week on preparations for pumpdown.  Work also continued
on ICRF, LH MIE Project, and RFX DNB systems.


Operations
----------

Invessel work this week included final assembly of the ICRF antennas,
and calibrations and checkout of many invessel diagnostics.  Thermocouples
have been added to all the antennas and will be read out with our new
fast TC scanner.   The new thermocouples behind the inner divertor are
operational and are already being read out through the scanner.  The
visible continuum array, TV views, H_alpha, and CXRS diagnostics,
among others, were also aligned and calibrated this week.  First pumpdown
is expected early next week.

The cryostat and bus tunnel have been sealed and the GN2 purge
system was checked out and debugged.  It will go into full time operation
early next week. 

We continue the migration of many of our analysis routines to the Linux
based computers.  EFIT is now fully operational on the new machines.
Some routines, the TCI analysis for example, are running 2.5 times faster
under Linux than on our fastest Alphas.

The Hybrid Plasma Control Systems has been checked out and is operational.

The magnet power systems are being brought back into operation.  Bus
Rowgoskis are being calibrated, ground fault fuses and current monitors
checked and calibrated, and bus voltage instrumentation checked.  The
bus will have a final retorque at the end of next week. 


Lower Hybrid MIE Project
------------------------

At PPPL, lab testing of the Lower Hybrid launcher prototype is continuing.
The dielectric constant of the ceramic window material has been
measured at 4.6 GHz, and a thickness has been specified for final
fabrication.  The window "bricks" are now on order.  Ethan Schartman, a
graduate student at Princeton University, will be working on
LH modeling and code development for his second year theory project.
He will develop a parallel version of the LSC code to use in scenario
development for Lower Hybrid AT experiments on C-Mod.

At MIT, the TPS Optical Interface Board 2 has been completed.  HVPS
commissioning is progressing.  The vendor estimates they will be ready
for acceptance tests within the next two weeks.


ICRF
----

We continue to work on the control and fault electronics.  Calibrations
continue on the new phase demodulator boards.  Phase plots indicating
output voltage vs input phase have been completed for all the boards.
Cabling of the new racks is well underway.  All invessel work on the
antennas was completed this week including installation of the
new thermocouples, and re-installation of the rf magnetic probes and
BN tiles.


RFX DNB
-------

The DNB was operated briefly this week to test operation following the
repositioning of some of the DNB equipment.  The DNB duct and vacuum
interface to the torus was completely assembled.  The optical bench for beam
spectroscopic monitoring was completed and installed.  The new fueling
system is nearing completion.

The DNB was aligned relative to the tokamak this week using an invessel
laser to illuminate the source grids. 

Assembly of the CXRS feedthroughs was completed.  The shutter
controls were installed and tested, and the shutter position calibrated.
The CXRS toroidal channels were spatially calibrated.  The CXRS
periscope at F-Top was installed.

Alan Lynn, UT-FRC, provided in-vessel support for CXRS, MSE, and BES
shutter assembly and for CXRS calibration.  He also began assembly of
the refurbished ECE high resolution radiometer.  He and Perry
Phillips, UT-FRC, will complete this next week.  This was Alan's last
"visit" prior to his taking up residence in Boston in June for the
duration of the campaign.  Ron Bravenec, UT-FRC, collaborated with
C-Mod personnel on assembly of the BES/MSE optics and continued BES
fiber polishing begun by Matt Sampsell a few weeks back.


Travel and Visits
-----------------

Martha Redi, PPPL,  was at MIT May 13-17, working with Catherine Fiore and
Paul Bonoli on gyrokinetic analysis of off-axis RF heated plasmas,
which exhibit internal transport barriers.  Gerrit Kramer and Jay
Kung, also PPPL, were at MIT May 15-17 to install the two new 130 and
140 GHz  reflectometer channels for fluctuation measurements farther up the
edge pedestal.