From: irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT


            Alcator C-Mod Weekly Highlights
                  May 31, 2002


First power tests of the Alcator C-Mod magnets were conducted this week.
We continue work on the DNB, ICRF systems, and diagnostic installations.


Physics
-------

At the Physics Meeting J. Snipes presented a summary of his collaboration with
JET Task Force S2 where he participated in experiments on JET the week of
13 - 17 May attempting to feedback control the q profile in real time with
LHCD, working with X. Litaudon and D. Mazon of CEA-Cadarache.  Some very
interesting results were obtained controlling the q profile with LHCD through
a special matrix controller with coefficients for five radial positions in
the q profile.  As the current penetrated, q dropped below the requested
profile causing the LHCD feedback to turn on and within a few seconds, the
q profile was brought back to the requested values for a change in q of
about 0.5 with up to 1.7 MW of LHCD.  This experiment was only a first attempt
to demonstrate real time feedback control of the q profile with
LHCD under simplified low density (1.2 x 10^19 m^-3) conditions.  More
work needs to be done to demonstrate substantial control of the q profile under
reversed or optimised shear conditions with combined ICRF, NBI, and LHCD with
strong internal transport barriers.  Nonetheless, this was a very promising
first step in the direction of steady-state advanced tokamak operation.


Operations
----------

On Thursday liquid nitrogen cooling of the magnets and tokamak structure
was begun, following commissioning of the vessel heater system.
Power tests were begun on Friday with all EF supply and EF1 commutation
tests completed successfully.  Following the power tests, a 120 C bake of
the vessel was begun.  The bake, together with ECDC wall conditioning will
continue until the middle of next week at which point power testing of
the TF and OH supplies will begin.


Lower Hybrid MIE Project
------------------------

Work continues on the commissioning of the lower hybrid HVPS.  The supply has
now passed two wire tests indicating that it can be shut down quickly
enough to keep total dissipated energy below 15 Joules.  Dummy loads and
their associated water cooling lines are being installed on the klystron carts.


ICRF
----

Work on the new control system for the phase shifters and stub tuners
is nearly complete.  Detailed s-parameter measurements of the D, E,
and J-antennas are being made in preparation for vacuum conditioning
and plasma operations.


RFX DNB
-------

The RFX DNB is back in operation and conditioning will continue
through the remainder of this week  The fueling system is complete,
leak checked, and installed. It supplies the two separate pressures
required by the ion source.


Diagnostics
-----------

Work continues bringing back online diagnostics needed for plasma
operations.


Travel and Visits
-----------------

Gerrit Kramer, PPPL,  was at MIT 5/29 and 5/30, completing hookup and
checking out the new 130 and 140 GHz reflectometer edge fluctuation
channels.  Dale Meade, also PPPL, was at MIT 5/30 for discussions on
FIRE-relevant double-null divertor experiments planned for the coming
run campaign.  Discussions were held with Bob Granetz, Steve Wolfe,
Joe Snipes, Amanda Hubbard, Earl Marmar, Paul Bonoli, and Miklos
Porkolab.