From: wolfe@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT


            Alcator C-Mod Weekly Highlights
                  June 24, 2002

Plasma operations resumed on Alcator C-Mod last week. Four run days were
scheduled and completed. A total of 23 plasma shots were produced, with a
startup reliability of 27%, which is low but not atypical for the first week
of operations after a major vent. The operation was devoted to tokamak clean-up
and conditioning; several diagnostic systems were also brought online.

Work also continued on ICRF, DNB, and Lower Hybrid Systems.

Plasma operations are planned to continue this week.

Operations
----------

Following a week of vessel conditioning (bake and ECDC), plasma operation
resumed last Tuesday. The purpose of the week's runs was to begin the process
of discharge conditioning of the tokamak in preparation for physics
operations. We also began discharge development for several new equilibrium
configurations, including higher triangularity and near-double null plasmas,
called for in the experimental plans for this campaign. In addition, we began
bringing diagnostics online, and verifying control and data system operation.
We also began to gain experience with the new Linux-based computer systems
under actual runtime conditions.

As is typical of plasma operations after a major vent, the plasmas produced
early in the week were short, disruptive, and characterized by high
resistivity and radiated power fraction, with frequent injections. Density was
typically higher than the programmed value (~1e20/m3), with most of the source
coming from the walls rather than the gas valves. As the machine began to
clean up, 800kA discharges were produced that lasted until their programmed
rampdown, and control of the density improved.

The initial discharges were programmed to be "standard" lower single null
divertor configurations. Once full-length plasmas were obtained in this
configuration, we began to modify the equilibrium toward a double null and to
increase the triangularity, taking advantage of the new inner divertor
assembly which allows more range for the lower x-point position. The purpose
of these equilibrium changes was both to begin development of new discharge
shapes required for upcoming physics experiments and to enhance the clean-up
of the vessel by moving the strike points onto previously unscoured tiles. By
the end of Friday's run, full-length discharges were produced in a near-DN
configuration (SSEP~5mm). The H/D ratio, one important indicator of machine
condition, was down to ~0.3 or less. However, progress was limited by rather
poor startup reliability. This may simply be due to inadequate wall
cleanliness; we are also investigating the possibility that the "sparker", an
invessel spark-gap system in line-of-sight to the tokamak chamber which
provides some initial ionization to assist breakdown at low loop voltage, may
have malfunctioned.


ICRF System
-----------

New RF Cell rack cabinet wiring was verified.  Some minor changes are being
made for PLC operation of stub tuner/phase shifter.  Stub tuner/phase shifter
controllers are both working with local control.  PLC operation for #1 has
been done.  PLC operation for #2 will be completed soon.

Final jumper configuration of the new fault system was done.  We have started
on J port fault circuit testing and entered and tested proper setpoints for
phase balance.  Voltage limit settings were calculated and entered and will be
tested.  Power threshold settings for J port were tested.  Delay from phase
balance fault to fault system output (in cell) was measured for several
channels and is less than 2 uS.  J fiber optic receiver boards in power room
electronics were modified to support failsafe signal operation from cell
electronics and tested.  PLC to fault board trip signals were tested and
verified.  Several problems were found and corrected.

Software modifications associated with use of the new cPCI data system for RF
operations are ongoing.


Lower Hybrid MIE
----------------

Work continued on improving the response time of the body current protection
circuits for the LH klystrons. Tests of a new breadboard circuit indicated
less than 2usec delay. New, faster response, current transducers have been
ordered.

DC power supplies for the flow-meter instrumentation have been
ordered. Mechanical work is proceeding on carts 1 and 2.

DNB Systems
-----------

The beam was operated throughout the week during the conditioning discharges.
Beam conditioning shots were run between C-Mod shots.  The beam was synched
with the firing of C-Mod shots.  A recent survey spectrum of the beam showed
lines from hydrogen only, attesting to its cleanliness.  The MSE system has
acquired data from both beam-into-plasma and beam-into-gas shots, and the
initial results look very encouraging.  A set of optical channels is being
configured for the MSE to look at the background plasma emission
(i.e. non-beam-induced) to improve the signal-to-noise even more.


Diagnostics
-----------

The two new off-axis tangential xray spectrometers were successfully tested
during plasma operation.

The Electron Cyclotron Emission diagnostics, including Michelson, GPC and
GPC2, are all operational and taking data, but not yet recalibrated. The
FRCECE diagnostic also observed ECE signals during several shots.

Work continued on the amplifier and power supply system for the Active MHD
Spectroscopy Antenna.

Travel and Visitors
-------------------

Ian Hutchinson, Joe Snipes, Miklos Porkolab, Eric Nelson-Melby, Remi Dumont,
Martha Redi, and Stewart Zweben attended the Conference on Plasma Physics and
Controlled Fusion of the European Physical Society in Montreaux, Switzerland,
last week.  Hutchinson presented a paper "Plasma Mach-probe with Unmagnetized
Ions"; Snipes presented a paper "Structure of the Quasi-Coherent Mode in
Alcator C-Mod"; Nelson-Melby (now at CRPP, Lausanne) presented "Phase Contrast
Imaging of Mode-Converted Ion Cyclotron Waves in the Alcator C-Mod tokamak";
Dumont (PPPL) presented a paper titled "ICRF wave propagation and absorption
in plasmas with non-thermal populations"; Redi (PPPL) presented a paper titled
"Gyrokinetic calculations of microinstabilities and transport during RF
H-modes on Alcator C-Mod"; and Zweben (PPPL) presented a paper titled "Edge
turbulence imaging on NSTX and Alcator C-Mod."

David Mikkelsen (PPPL) visited C-Mod for discussions with Amanda Hubbard,
Perry Phillips, and Alan Lynn about using ECE Te diagnostics and Bo
sweeps to determine temperature gradient scale lengths.




-----------------------------------------------------------------------

The contents of this message have been scanned for viruses by
the Clearswift ES Policy Server, and no viruses were found.