From:
wolfe@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
July
1, 2002
Plasma operations continued on Alcator C-Mod last week. Four
run days were
scheduled and completed. A total of 31 plasma discharges
were produced with a
startup reliability of 45%. The purpose of this
week's runs was continued
clean-up of the tokamak, diagnostic alignment
and calibration, and discharge
development for the upcoming physics
campaign. Progress also continued on
ICRF, DNB, and Lower Hybrid Systems.
Plasma operation is scheduled to continue
next week.
Operations
----------
Three
days of plasma operations in support of tokamak conditioning and startup
activities
were carried out last week. In addition, one run day was devoted to
beam-into-gas
(no plasma) shots with programmed toroidal and vertical fields
for
calibration of the MSE diagnostic.
Cleanup and conditioning of the
machine is proceeding well. By Friday, the
H/(H+D) ratio was down to less
than 15%, and the startup reliability was above
60%. Disruptivity was also
down, with 29 of 31 plasmas lasting into programmed
rampdown. A problem
with the discharge initiation sparker encountered the
previous week has
been remedied, and a new sparker system has been installed
as a
backup.
Development of new equilibria for the physics campaign also
made progress last
week. A series of double null discharges
(abs(SSEP)<2mm) were produced with
both upper and lower
triangularity>0.8 and elongations up to 1.85. These high
triangularity
configurations are possible due to the new lower inner divertor
structure
installed during the last year.
Diagnostics
-----------
Diagnostics
continue to be brought online and calibrated. The ECE system was
aligned
on a series of constant-shape discharges. Both A and F-port scanning
probes
were exercised during plasma shots, as were the divertor flappers.
The
high-pressure in-vessel Penning gauge recently installed under the
B-C outer
divertor module was connected to a new high voltage bias
circuit last
thursday. The cathode/anode geometry of this gauge
was custom-built with
dimensions approximately a factor of 10 times
smaller than the standard
commercial units used at other locations
in C-Mod. The miniature Penning
gauge was designed to take advantage
of the high magnetic field strengths
in C-Mod, extending the
useful pressure measurement range to the 10s of
mtorr level and
allowing a direct, fast time-response measurement of the
high
pressures under an outer divertor module. During last friday's run,
the gauge was successfully operated, reporting divertor pressures of
up to 100 mtorr during local capillary gas injection tests. Pressure
readings taken during discharge 'fizzles' are found to generally
agree
with readings from other gauges connected to the vessel, lending
confidence to the gauge's operation. The gauge appears to maintain
a
discharge at moderate to high neutral pressures which is more stable than
the three other Penning gauges in the torus (commerical units).
Thus,
plans are already developing to replace the 3 commerical gauges with
custom-built
units. Experiments are planned to use the miniature gauge to
calibrate
divertor neutral leakage rates during the physics phase of the present
run
campaign. New capillaries in the upper and lower regions of the
chamber are
also operational, and should shed new light on plasma fueling
and pumping.
The visible continuum array diagnostic became
operational last week.
Additional new inner divertor diagnostics
are also coming on-line. The halo
and eddy current rogowski coils (20
coils) are now all operational.
One of the two Gunn oscillators
used for the upgraded reflectometer system was
found to have failed and
will be sent to the commercial vendor for repairs.
TV plasma-imaging
systems are being brought on-line, including two wide-angle
views of the
discharge from A- and F-ports, which will provide a nearly
complete view
of the plasma chamber; a divertor view; and a fast framing
camera view
used to image turbulence in the SOL region near the
midplane. Problems
with data acquisition for these cameras have apparently
been resolved, and
the image data are now being automatically stored in the
MdsPlus
tree.
ICRF Systems
------------
The ICRF
system is coming on-line. Following resolution of some issues in the
new
control and fault protection systems, the J-port four-strap antenna was
vacuum
conditioned
up to 35kV on Friday. Low-power (~30kW) conditioning pulses into
plasma
were then obtained on the final few shots of the day. Plasma
conditioning
of the J-antenna should proceed this week. Operation of D- and
E-port
antennas is also imminent.
DNB Systems
-----------
The
beam was operated on three days last week, On Tuesday and Wednesday, it
was
fired in synch with C-Mod pulses. On
Thursday, a beam-into-gas experiment
was completed for MSE
calibration. The TF, and EF3 and EF4
coils were
energized during these calibrations to simulate the fields due
to plasma
current. The BES system
was operated for measurement of the beam width. On
the last day of the week, there was a fault in the
charging power supply
circuit which is being evaluated. Blown fuses were found but operation of
the
beam will be continued only after consultation with the Budker
team.
Travel and Visitors
-------------------
Miklos
Porkolab visited the Ecole Polytechnique Federale De Lausanne/CRPP,
Lausanne,
after the EPS meeting, June 24, and gave the Colloquium with the
title:
The MIT Plasma Science and Fusion Center: A Paradigm of How to Operate
a
major Fusion Laboratory in a University Environment. The colloquium was
well attended. Discussions followed by
the Director, Prof. Tran and
Dr.
Appert, Associate Director, about possible collaborations between the two
laboratories.
Gerrit
Kramer (PPPL) was at MIT 6/25-26 to check out the two-channel
reflectometer
upgrade and participate in MSE diagnostic startup with
the RFX beam. Steve Scott (PPPL) has joined the C-Mod
team; this was his
first week onsite. Steve will be working on the MSE
diagnostic.
Gerd Schilling was at MIT 6/25-28 to participate in the ICRF
startup.
-----------------------------------------------------------------------
The
contents of this message have been scanned for viruses by
the Clearswift
ES Policy Server, and no viruses were found.