From:
wolfe@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
Jul
22, 2002
Plasma operations continued at Alcator C-Mod last week. Four
run days were
scheduled, but only three were completed. The run on
Thursday was deferred in
order to provide time for trouble-shooting and
repairs of the ICRF control
system. The main goals of this week's
operation were evaluation of the first
boronization of the campaign and
continued conditioning of the ICRF
antennas. Discharge development for
planned experiments later in the campaign
was also accomplished. A total
of 38 plasma discharges were produced, with a
startup reliability of 70%.
Work continued on the Lower Hybrid and Diagnostic
Neutral Beam Systems.
Seven C-Mod physicists were off-site, participating in
the Snowmass Fusion
Summer Study. Thirty-eight abstracts
related to C-Mod
results, including 13 contributed oral presentations and
two invited talks,
were submitted to the APS to be presented at the
November meeting of the
Division of Plasma Physics in Orlando, FL.
Plasma
operations are scheduled to continue this week.
Operations
----------
The
first boronization of the present campaign was successfully carried out
on
Monday evening. Approximately 2050 A of boron was deposited; this
coating is
about the same thickness used during the previous campaign. The
run on Tuesday
was largely devoted to evaluation of and recovery from the
boronization. As is
typical, the startup reliability on the first
operating day after boronization
was degraded at first, but improved
during the day; reliability later in the
week was at the 80% level. The
H/D ratio was observed on Tuesday to be in the
3% range, a factor of two
or more reduction from the pre-boronization levels
and suitable for
hydrogen minority heating experiments. Radiated power, as
measured by the
2pi diode bolometer, was also down by over a factor of two
from
pre-boronization levels.
The remainder of the week's runs were
devoted primarily to RF antenna
conditioning. ICRF instrumentation
problems noted in the earlier runs were
identified and repaired on
Thursday. While these repairs were taking place, a
series of no plasma
shots were carried out in order to calibrate the gas puff
valves. RF
conditioning into plasmas resumed on Friday, reaching MW power
levels.
This activity will continue this week. Also on Friday, equilibrium
development
in support of future experiments was carried out, including shape
development
for a JET similarity experiment and low-triangularity equilibria
for
investigations of the shape dependence of the EDA regime.
ICRF
Systems
-------------
Antenna operation into plasma was begun
after boronization. Boronization
had
a significant negative impact on antenna conditioning, requiring
additional
vacuum conditioning shots.
Operation was further hindered by false phase
balance and voltage
faults that were identified and fixed for the run on
Friday. Antenna operation on Friday was significantly
improved over
Wednesday. Before
the run, the D and E-port were vacuum conditioned to 35 kV
(0.5 sec) and
the voltage and phase balance fault electronics were modified to
eliminate
oscillation in an instrumentation amplifier.
Operating into plasma,
D-port and E-port reached 20 kV and 25 kV
respectively. They also operated
to
~1.4 MW together. J-port had
less vacuum conditioning and its operation into
plasma reflected this
fact. J-port required a fast rise time
(~1 msec to 100
kW) at low power to avoid what appears to be discharge
formation. D and
E-port still
require more vacuum and plasma conditioning.
J-port requires
significantly more vacuum conditioning and work on
the phase feedback
instrumentation.
Diagnostic Neutral Beam
System
------------------------------
During the week, the
suppressor supply was repaired. Several
capacitors in
the accelerator bank were replaced and several open bleed
resistors were
found. Repairs on the DNB power supplies have progressed to
the point that
the beam has again started firing at nearly full parameters
(50 kV, 3 A, 40
ms). Issues
concerning the regulation of the arc current are still being
investigated. The Budker group in Novosibirsk has been
extremely helpful in
aiding our engineers on this repair. The next
operation of the beam will be
early this week and will be intended to
check the regulation of the arc
supply.
Lower Hybrid MIE
Project
------------------------
Fast current sensors to
measure body current were installed on transmitter
#3. Coax cables were
run from current sensors to the cart external interface.
The external
interface was modified on cart #3 to accept four new cables. An
interface
box consisting of resistor and diode was constructed to allow new
and old
current sensors to share same cable to the TPS. Back panels for EMI
racks for transmitters #1 & 2 were
modified to accept interface board #1, and
Rivnut installation was begun
for these modified back panels.
Travel and Visitors
-------------------
Ian
Hutchinson, Earl Marmar, Miklos Porkolab, Joe Snipes, John Rice, Amanda
Hubbard
and Ron Parker participated in the Fusion Energy Summer Study in
Snowmass,
CO.
Martha Redi visited MIT July 15-17th, working with Catherine
Fiore, Steve
Wukitch and Darin Ernst on nonlinear gyrokinetic simulations
of the C-Mod
ohmic H-mode and off-axis RF internal transport barrier
experiments. Gerd
Schilling was at
MIT July 15-19, continuing to help to bring up the ICRF
system.
-----------------------------------------------------------------------
The
contents of this message have been scanned for viruses by
the Clearswift
ES Policy Server, and no viruses were found.