From:
wolfe@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
July
29, 2002
Plasma operations continued at Alcator C-Mod last week. Four
run days were
scheduled and completed.
Conditioning of the ICRF Antennas continued, and
Physics Operation
began with one run day devoted to a Divertor/Edge Group
experiment. Work also continued on the Lower Hybrid and
Diagnostic Neutral
Beam Systems.
Plasma operation are scheduled
to continue this week.
Operations
----------
Plasma
operations were carried out Tuesday-Friday last week. Startup
reliability
for the week was about 70%, with a total of 64 successful
discharges being
produced. Following Tuesday's run, a small leak was
identified at one of
the Thomson Scattering laser windows. This window was
replaced on
Wednesday; at the same time a failed ratiomatic ion gauge at
G-side was
also replaced. Since these components are located behind isolating
valves,
it was not necessary to break main vacuum to carry out these repairs.
Three
of the week's runs were dedicated to conditioning of the ICRF
antennas.
The target plasmas for these runs were mainly inner-wall limited
equilibria,
in order to remain in L-mode as the power coupled to the plasma
increased
above the MW level. The loading changes associated with L-H
transitions
can lead to increased faulting which detracts from the
conditioning
process.
Thursday's run was in support of MP#313, submitted by the
Divertor/Edge Group
and Density Control Task Force. The goal of this
experiment was to quantify
the effective conductances of neutral gas
through various pathways in and
around the lower and upper divertor
structures during plasma discharges. This
information will help reconcile
some of the puzzles with respect to divertor
neutral leakage, and will
also help us understand the behavior of gas
compression in the upper
chamber and allow us to anticipate pressure changes
there in response to a
future cryopump system. Both standard
lower single
null and upper single null equilibria were investigated in
this experiment.
The primary tools were the NINJA capillary gas
puff system and divertor
flappers, in conjunction with pressure gauges
(in-vessel and ex-vessel) and
the divertor TV camera system. The new
miniature Penning gauge under the B-C
divertor module ran better than
expected, recording fast pressure changes in
this region as the B-C
flapper was opened or the B-C Bottom capillary was used
to puff gas. The divertor camera (DIV2, viewing D-alpha)
observed puffs from
the B-C and C-D capillaries located above the B-C and
C-D flappers. The
camera also was
able to record changes in local D-alpha light when the
flappers were
opened, giving us the possibly to 'calibrate' the flow through
the
flapper. In addition, the pressure
under the B-C flap was recorded by the
Penning gauge there, which should
allow us to estimate the effective
conductance through the open flap in
the presence of plasma.
Diagnostics
-----------
The
new tangential HIREX (High Resolution X-ray) spectrometer systems are
operational,
and observations of toroidal rotation profiles during ohmic and
ICRF
operation have begun.
Following repair of digitizers in the core
system, and replacement of the
Thomson laser window on Wednesday, the Edge
and Core Thomson Scattering
diagnostics began taking data last week.
The
number of FRCECE radiometer channels was increased to the full
complement
of 32 this week with installation of the detectors that
were recently
repaired by the manufacturer. The
detector problems
were due to faulty manufacture. Calibration for recent shots was
completed.
ICRF
Systems
------------
In this week, we ran RF conditioning on
Tuesday, Wednesday and Friday. The
D-port antenna has been conditioned up
to 1.2MW and the E-port antenna to
1.6MW. The D and E modulator boards
were modified to accommodate a soft-start
after faulting, This
modification has been shown to provide more reliable
operation.
We
also changed the phase feedback input system for the four-strap J-port
antenna. We added 8309 limiter boards in the feedback
path of the controllers
to improve the dynamic range of these inputs. We
have also developed an
operating strategy which allows the phase to lock on
startup at low power and
then ramp up to higher power. Using this scheme, the J-port antenna has
been
conditioned up to the 0.5MW level.
Diagnostic Neutral Beam
System
------------------------------
Work continued to
identify the source of the arc current stability problems
that have shown
up since the power supply arcdown a few weeks ago. Since
then, damaged
components in several subsystems have been replaced.
including fuses,
voltage divider resistors, pulldown resistors, bleed
resistors, protection
diodes, and one arc charging SCR. The
final repair was
to replace a feedback resistor in the control circuitry
for the arc
supply. This appears to have remedied the instability in the
arc current. The
DNB was operated for approximately 10 shots over the
weekend, with no faults
beyond those normally encountered during
conditioning. Additional conditioning
shots will be run this week, with
beam-into-plasma operation anticipated
during C-Mod operation.
Work
continues on the upgrade to the beam cryo system. The cryo distribution
panel
for the cell end of the vacuum line has been assembled, and the fill
station
end to supply the vacuum line has been re-plumbed. Remaining work
includes
installation of the line through the last diagnostic lab, mounting
the vapor
vent in the diagnostic lab, and piping the vapor vent through the
back
wall to the outside.
Lower Hybrid MIE Project
------------------------
The
back panels for the EMI/RFI cabinets were modified to accept the
coax
filtering boards. Previously only the
cabinet for Cart #3 had this
board installed, but there were clearance
issues with this panel. The new
panel
was retrofitted on the equipment rack for Cart #3. The new
mechanical arrangement has no clearance issues. The old panel which was
removed from
Cart #3's cabinet is being modified to address the clearance
issues.
The
24VDC power supplies for the water system flowmeters arrived this
week and
are being installed. The schematic for the water interface is being
modified
to include the new power supplies, and a tech request was generated
to
provide 120VAC to these supplies.
Travel and Visitors
-------------------
Phil
Ryan of Oak Ridge visited the RF Group on Tuesday to Thursday. He
participated
in the ICRF conditioning activities during C-Mod operations.
Ricky
Maqueda from LANL visited C-Mod during the week and re-installed the
infrared
imaging system. This system is now
operational.
-----------------------------------------------------------------------
The
contents of this message have been scanned for viruses by
the Clearswift
ES Policy Server, and no viruses were found.